Resolved
RESOLVED THAT COMMITTEE: Approve the 2023/24 revised estimate of £54,750 for this Committee’s capital programme.
Economic Development approved this item on Thursday 25 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: Approve the 2023/24 revised estimate of £54,750 for this Committee’s capital programme.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO ECONOMIC DEVELOPMENT COMMITTEE
meeting date: 25 JANUARY 2024 title: REVISED CAPITAL PROGRAMME 2023/24 AND FUTURE CAPITAL PROGRAMME REVIEW AND NEW BIDS submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: LAWSON ODDIE
1 PURPOSE 1.1 To approve the 2023/24 revised estimate for this Committee’s capital programme. 1.2 In addition, the outcome of the review of this Committee’s future capital programme for 2024/25 to 2028/29 is reported to members. 1.3 Relevance to the Council’s ambitions and priorities: Community Objectives – none identified. Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs. Other Considerations – none identified. 2 2023/24 CAPITAL PROGRAMME BACKGROUND 2.1 There was 1 capital scheme that was originally approved for this committee totalling £54,750. The approved scheme had been moved from the 2022/23 capital programme to the 2023/24 capital programme. 3 REVISING THE 2023/24 CAPITAL PROGRAMME 3.1 We have now discussed the capital programme scheme with the budget holder and revised the capital programme to reflect scheme progress and estimated full year expenditure. 3.2 There has been no spend on the Economic Development initiatives scheme to date. This is because there were no appropriate economic development opportunities in progress at the end of December 2023 which were likely to be funded from this economic development capital budget. 3.3 It is proposed that the Economic Development initiatives scheme budget of £54,750 be left within the 2023/24 revised capital programme, should any opportunities arise before the end of the financial year. 3.4 The table below shows the budget and expenditure to date on this Committee’s one capital programme scheme. Actual Expenditure including Cost Budget Total commitments Scheme Centre Original Moved Approved Revised Budget as at end of Estimate from Budget Estimate Moved to December 2023/24 2022/23 2023/24 2023/24 2024/25 2023 £ £ £ £ £ £
ECDVI Economic Development Initiatives 0 54,750 54,750 54,750 0 0
Total Economic Development Committee 0 54,750 54,750 54,750 0 0
3-24ed 1 of 2 4 FUTURE CAPITAL PROGRAMME REVIEW AND NEW BIDS 4.1 In the current cycle of meetings service committees are receiving reports on the review of the future capital programme for 2024/25 to 2028/29. This includes a review of any scheme already approved for the 2024/25 to 2027/28 period and the submission of new bids for the 2028/29 financial year. 4.2 For this Committee there are no previously approved capital schemes for 2024/25 and 2027/28 and no new bids have been submitted for 2028/29. 4.3 Whilst there have been no bids made by Heads of Service, members have the opportunity to consider any capital bid suggestions or amendments that they may wish to make at this stage. 5 RISK ASSESSMENT 5.1 The approval of this report may have the following implications: Resources – Approval of the revised capital programme will see no change to the level of financing resources needed within the 2023/24 financial year. Technical, Environmental and Legal – None. Political – None. Reputation – Sound financial planning for known capital commitments safeguards the reputation of the Council. Equality and Diversity – Equality and Diversity issues are examined as part of the capital bid appraisal process. 6 CONCLUSION 6.1 The revised estimate for this Committee’s 2023/24 capital programme is £54,750. 6.2 For this Committee’s future capital programme, there were no previously approved capital schemes for 2024/25 to 2027/28 to review and no new capital scheme bids were submitted for 2028/29. 7 RECOMMENDED THAT COMMITTEE 7.1 Approve the 2023/24 revised estimate of £54,750 for this Committee’s capital programme.
HEAD OF FINANCIAL SERVICES DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE
ED3-24/LO/AC 17 January 2024
3-24ed 2 of 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revised Capital Programme 2023/24 and Future Capital Programme Review and New BidsReport | 88 KB | DownloadRead as text |
Follow Economic Development at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | 2026/2027 Climate Change Action PlanRESOLVED THAT COMMITTEE: Approve the 2026/27 Climate Change Action Plan at Appendix 1 of the report for formal adoption. | Approved | Open |
| 11 Jun 2026 | 2025/2026 Climate Change Annual ReportRESOLVED THAT COMMITTEE: Note the content of the 2025/2026 Annual Climate Change Report that includes an update on th... | Noted | Open |
| 11 Jun 2026 | Lobbying letter to Government re. Fuel Duty and VATRESOLVED THAT COMMITTEE: Approve the letter at Appendix 1 of the report to use the Council's influence to lobby Gover... | Approved | Open |
| 11 Jun 2026 | Tourism Budget and Service ChangesRESOLVED THAT COMMITTEE: 1. Approve the proposed virement to create a temporary staffing budget. 2. Confirm acceptanc... | Approved | Open |
| 11 Jun 2026 | Appointment to Working GroupsRESOLVED THAT COMMITTEE: Approve the continuation of the Climate Emergency Working Group for 2026/27 municipal year w... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.