Resolved
RESOLVED THAT COMMITTEE: Approve the slippage of £237,902 as set out at paragraph 3.6 of the report.
Community Services approved this item on Tuesday 27 May 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: Approve the slippage of £237,902 as set out at paragraph 3.6 of the report.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: 27 MAY 2025 title: CAPITAL OUTTURN 2024/25 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: JEAN WADDINGTON
1 PURPOSE
1.1The purpose of this report is to review the final outturn of the 2024/25 capital programme for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2024/25 financial year to the 2025/26 financial year.
1.2Relevance to the Council’s ambitions and priorities: • Community Objectives – none identified. • Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need. • Other Considerations – none identified.
2 2024/25 CAPITAL PROGRAMME BACKGROUND
2.1There were 15 capital schemes for this Committee’s original estimate budget (including budget and schemes moved from 2023/24), totalling £2,084,410. These were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2024 and March 2024 respectively.
2.2In addition, at the end of the 2023/24 financial year a total budget of £287,850 covering 9 schemes was unspent at year end and was moved to the 2024/25 financial year (including two schemes where budget had also previously been moved from the 2023/24 financial year and one scheme where budget was added to a ‘rolling programme’).
2.3This unspent budget that was moved is known as slippage and was moved into the 2024/25 capital programme budget after approval by this Committee in May 2024.
2.4One further capital scheme was approved in year, and additional budget approved for another totalling an additional £63,730.
2.5One scheme, Play Areas Refurbishment, had £100k transferred to a different scheme under a different Committee (Salthill Play Area under Policy and Finance Committee).
2.6Another scheme with a budget of £135k, JCB Loadall Replacement, previously approved for 2025/26 was brought forward to 2024/25.
2.7As a result of the above elements, the total approved budget for this Committee’s capital programme of 23 schemes was £2,470,990.
2.8Later in the year the capital programme budget was revised to £1,035,065 in respect of 23 schemes and was then approved by the Special Policy and Finance Committee in February 2025. This followed a review of progress on all schemes in the capital programme and included moving budget of £1,542,370 on 4 schemes into the 2025/26 financial year. The revised estimate budget is shown at Annex 1.
8-25cm 1 of 32 2.9 Following the Policy and Finance meeting of February 2025 it was agreed that spending could take place on three further schemes. One was Langho Northcote Sports Facilities which was entirely funded by S106 monies and had no impact on the Council financially. Two other schemes were part of the approved 2025/26 capital programme. Preliminary surveys for these schemes were undertaken in 2024/25 with the costs to be carried forward as ‘negative’ slippage and charged against the 2025/26 budgets.
2.10During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.
3 CAPITAL OUTTURN 2024/25
3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2025/26. The table below summarises the final outturn position.
Total Requested Budget Original Slippage Additional Approved Revised Budget Actual Slippage Moved from Estimate from Approvals Budget Estimate Moved to Expenditure into 2023/24 2024/25 2023/24 2024/25 2024/25 2024/25 2025/26 2024/25 2025/26 £ £ £ £ £ £ £ £ £
1,644,240 440,170 287,850 225,740 2,598,000 1,035,065 1,542,370 809,997 237,900
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Outturn 2024/25Report | 468 KB | DownloadRead as text |
Follow Community Services at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Aug 2026 | Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... | Agreed | Open |
| 25 Aug 2026 | Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... | Decided | Open |
| 25 Aug 2026 | Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... | Approved | Open |
| 25 Aug 2026 | Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... | Decided | Open |
| 26 May 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.