Resolved
RESOLVED THAT COMMITTEE: Approved the future capital programme for this Committee’s services for onward recommendation to Special Policy and Finance Committee for the period 2026/27 to 2029/30, based on the proposals included in the report.
AI summaryRibble Valley Policy and Finance Committee approved a four-year capital programme of £320,800 for 2026/27 to 2029/30, a reduction of £69,760 after moving the fire alarm upgrade to 2025/26, and sent it to the Special Policy and Finance Committee.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED THAT COMMITTEE: Approved the future capital programme for this Committee’s services for onward recommendation to Special Policy and Finance Committee for the period 2026/27 to 2029/30, based on the proposals included in the report.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 20 JANUARY 2026 title: CAPITAL PROGRAMME REVIEW submitted by: DIRECTOR OF RESOURCES principal author: JEAN WADDINGTON
1. PURPOSE 1.1. To ask Committee to consider the future capital programme for this Committee, covering the period 2026/27 to 2029/30. 2. BACKGROUND 2.1. This report reviews the schemes that were approved into the capital programme in March 2025, for the financial years 2026/27 to 2029/30. 2.2. Due to the uncertainty regarding the outcome of the finance reforms and also local government reorganisation, at their meeting on 16 September 2025, Policy and Finance Committee gave guidance that no bids for 2030/31 of the capital programme should be invited and that the existing programme should be reviewed for any schemes that could be reprofiled to a later year. 2.3. In respect of 2030/31, Heads of Service have instead been asked to identify essential capital schemes or items that are necessary for the continuation of ‘business as usual’, so that these can be separately noted. If these were to be brought forward as proposals for inclusion in the capital programme in the future, this would involve the submission of detailed capital bids and consideration by committee. 3. REVIEW OF THE EXISTING CAPITAL PROGRAMME 2026/27 TO 2029/30 3.1. For this Committee there were originally 5 schemes approved for the financial years 2026/27 to 2029/30, totalling £390,560. 3.2. One scheme (Council Offices Fire Alarm Upgrade) totalling £69,760 has since been brought forward from 2027/28 to 2025/26. 3.3. This amendment has resulted in a capital programme for this committee of 4 schemes totalling £320,800 and is shown at Annex 1. 3.4. Further amendments to the capital programme 2026/27 are likely to occur as a result of the review of the current year capital programme that takes place at Revised Estimate. These changes are covered in a separate report presented to this Committee. 3.5. A summary of the reviewed Capital Programme is given below:
Scheme Name 2026/27 2027/28 2028/29 2029/30 TOTAL
Current Approved 43,600 69,760 0 277,200 390,560 Capital Programme
Council Offices Fire Alarm -69,760 -69,760 Upgrade
Capital Programme 43,600 0 0 277,200 320,800 Following Review
7-26pf 1 of 3 4. CONCLUSION 4.1. The proposed amendments to the previously approved capital programme would decrease the capital programme by £69,760 to £320,800. 5. RISK ASSESSMENT 5.1. The approval of this report may have the following implications: • Resources – The proposed amendments to the existing approved capital programme would decrease the capital programme by £69,760. • Technical, Environmental and Legal – None. • Political – None. • Reputation – Sound financial planning for known capital commitments safeguards the reputation of the Council. • Equality and Diversity – Equality and Diversity issues are examined as part of the capital bid appraisal process. 6. RECOMMENDED THAT COMMITTEE 6.1. Consider and propose a future capital programme for this Committee’s services for onward recommendation to Policy and Finance Committee for the period 2026/27 to 2029/30, based on the proposals included in this report.
SENIOR ACCOUNTANT DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE PF7-26/JW/AC 8 January 2025
For further background information please ask for Jean Waddington. BACKGROUND PAPERS – None
7-26pf 2 of 3 ANNEX 1 Policy and Finance Committee Proposed Four Year Capital Programme 2026/27 to 2029/30
2026/27 2027/28 2028/29 2029/30 TOTAL SCHEME TITLE £ £ £ £ £
Replacement ICT Equipment for 43,600 43,600 Councillors Civic Suite Upgrade of AV 126,960 126,960 Equipment
Civic Suite Replacement Boilers 37,550 37,550
Council Offices Replacement 112,690 112,690 Boilers Total Policy and Finance 43,600 0 0 277,200 320,800 Committee
7-26pf 3 of 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Review 2026/27: 2029/30Report | 127 KB | DownloadRead as text |
Follow Policy and Finance at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: 1. Approved slippage of £1,756,430 on the main Policy and Finance Committee capital schemes ... | Approved | Open |
| 16 Jun 2026 | Returning Officers’ Scale of Fees 2026/27 – Borough and Parish ElectionsRESOLVED THAT COMMITTEE: Agreed the Returning Officers’ Scale of Fees for any Borough or Parish By Election in 2026/2... | Agreed | Open |
| 16 Jun 2026 | Government Consultation - High Value Council Tax SurchargeRESOLVED THAT COMMITTEE: 1. Approved the consultation response attached at Annex 1 subject to minor amendments as dis... | Approved | Open |
| 16 Jun 2026 | Town and Parish Council Traffic Management Plan Grant Scheme 2026-27RESOLVED THAT COMMITTEE: 1. Approved the grant scheme criteria and conditions as set out at paragraph 3.1 with the co... | Approved | Open |
| 16 Jun 2026 | Appointment to Working GroupsRESOLVED THAT COMMITTEE: 1. Approved the continuance of the following working groups under the remit of this committe... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.