CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council

BDR Project Update

Noted Committee 1 paper

Barnsley, Doncaster and Rotherham Joint Waste Board noted this item on Friday 14 December 2012. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

Resolved :- That the report be received and its contents noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Barnsley, Doncaster and Rotherham Joint Waste Board, 4 pages

BDR MANAGER UPDATE REPROT

BDR WASTE PFI BDR M AN AGER UPD ATE REPORT 30/11/2012

.

1.0Governance

Waste Infra-Structure Development Programme (WIDP) Transactors from the Department of Environment Food and Rural Affairs (DEFRA) carried out a Contract Management Review of the BDR Waste PFI on the 7th and 8th November 2012. Officers from all three Councils were interviewed along with representatives of the Contractor and the Technical Advisors. The aim of the review was to assess the progress of the BDR Waste PFI Contract. A report is expected shortly.

2.0Project Delivery

2.1Bolton Road

Item Percentage Target Actual Comments Complete Completion Completion Date Date Bridge design 100% 24/9/2012 17/8/2012 Bridge construction to adoptable standards for 20 year life Planning Bolton 100% 10/8/2012 9/8/2012 Full planning consent obtained Judicial Road Review period ended on 9/8/2012 no issues were raised. Discharge of 65% 1/7/2015 The Bolton Road planning consent had planning 28 conditions attached of those 6 conditions conditions have been discharged 19 are in the process of being discharged, 3 will continue through the operating phase e.g. opening hours. Bolton Road 80% July 2012 in Permit received from Environment permit process Final Agency on 5/10/2012. There are 4 pre- Business operational conditions. Case (FBC) • An odour management plan is to be submitted before the facility becomes operational • Background sampling of bio- aerosols must be undertaken • Further information on noise must be submitted • Evidence of the technical competence of the Site Manager must be supplied Judicial Review Period will end on 6/1/2013

1 Item Percentage Target Actual Comments Complete Completion Completion Date Date Site possession 100% Shanks Contractor onsite Construction, Shanks Design and Management advisor checked Method Statements and Quality Systems, enabling works underway. Mobilisation for 100% 15/10/2012 13/8/12 Shanks Contractor mobilised Enabling Works Enabling works 80% 23/12/2012 All consents in place for working on the Bolton Road access road. Culvert in place, backfilling well underway although adverse weather conditions have caused some delays this is not expected to impact on the overall programme. Mobilisation for 20% 12/12/12 3SE construction sub-contractor Birse Construction partially mobilised for the construction of Bolton Road the main facility. Power on to 0% 26/8/2014 permanent works Buildings 0% 29/9/2014 complete excluding planting Roads and 1% 01/10/2014 weighbridge complete Intelligent 0% 7/4/2015 Transfer Station (ITS) Commissioning ITS Acceptance 0% 20/5/2015 Tests Anaerobic 0% 12/5/2015 Digestion (AD) Commissioning Animal By- 0% 12/5/2015 Products Regulations (ABPR) Compliance AD Acceptance 0% 16/6/2015 Tests Progress 5% 1/7/2015 towards Service Commencement 2.2 Ferrybridge

Ferrybridge 60% July 2012 Public consultation on the Ferrybridge Permit ended permitting in FBC on 21st November 2012. If no concerns are raised a process final permit is expected to be issued mid-December 2012 Judicial Review period will end 3 months after this expected mid-March 2013. Discharge of The Ferrybridge planning consent had 75 conditions planning attached of those 13 conditions have been discharged conditions with 5 in the process of being discharged. Enabling works 80% 17/12/2012 Cricket Pavilion completed, new car parking area Ferrybridge completed, work on access underway Main Works Hot 0% 12/10/2014 Commissioning Operational 0% 5/4/2015 Testing Facility 0% 5/4/2015 Operational

3.0Technical

Further intrusive site investigations are underway to finalise the assessment of ground conditions at Bolton Road; a report on the results is expected early December 2012.

3SE have formally submitted 4 items under the review procedure for comment by BDR. These were in regard to the Visitors Centre design, the Gatehouse design and the access road requirements. There are no material changes and no cost impact arising from these changes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BDR Project UpdateReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. BDR Project UpdateThis decision
  2. BDR Joint Waste Project - Manager's ReportAgreed
  3. BDR Joint Waste Project - Manager's Annual Report 2017-2018Agreed
  4. BDR Joint Waste Project - Manager's ReportAgreed
  5. BDR Joint Waste Project - Manager's ReportAgreed
  6. BDR Joint Waste Project - Manager's ReportAgreed

More from Rotherham Barnsley, Doncaster and Rotherham Joint Waste Board

All decisions
MeetingDecisionOutcome
16 Nov 2026 Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. Approved Open
16 Nov 2026 BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. Agreed Open
16 Nov 2026 BiffaThat the update be noted. Noted Open
16 Nov 2026 Risk RegisterThat the report be noted. Noted Open
3 Feb 2026 Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies