Agreed :- the Joint Waste Board expressed its preference for the partnership approach to the management of the contract. (b) The Bolton Road facility – the permit is deemed as being satisfactory, the Judicial Review period having ended on 6 th January 2013; Section 73 applications will be submitted in order to obtain planning consent for minor material amendments to the application, as a consequence of detailed design work. (c) Good progress overall continues to be made with the Ferrybridge site; the judicial review period for the S.S.E . Environmental Permit has now ended (d) Health and Safety – there were no issues of concern to report; (e) an information sharing protocol has been drafted for the three local authorities; (f) Finance – operational management costs are projected to be within budget for the current, 2012/13, financial year; (g) Communications – the ground-breaking photo-call with Elected Members, on Monday, 18 th February, 2013, had been very well publicised, some minor inaccuracies in the press reporting had now been corrected; discussions continued with the liaison group to provide information about traffic issues around the Bolton Road facility; the importance of providing regular information bulletins was acknowledged; details would shortly be available about the forthcoming project partnership awards for the Best Waste Project; (h) Preparation of the Contract Manuals is continuing. Resolved :- That the report be received and its contents noted.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Barnsley, Doncaster and Rotherham Joint Waste Board
ITEM 3 BDR MANAGER UPDATE REPROT
BDR WASTE PFI BDR M AN AGER UPD ATE REPORT 4/03/2013
.
1.0Governance
The WIDP Contract Management Review report was received on 15/1/2013 overall the review was positive. WIDP made some recommendations to ensure the continued effective management of the contract. These focussed around knowledge management, including the completion of the contract manuals and work instructions, communications between the collection managers and the BDR PFI team and reviewing the organisational structure of the team to ensure it remains fit for purpose in the various phases of the Contract.
The operational management team are working towards completing the contract manuals by the summer 2013.
The June Joint Waste Board will be the Annual General Meeting at which point the Chair will rotate.
2.0Project Delivery
2.1Bolton Road
Item Percentage Target Actual Comments Complete Completion Completion Date Date Bridge design 100% 24/9/2012 17/8/2012 Bridge construction to adoptable standards for 120 year life Planning Bolton 100% 10/8/2012 9/8/2012 Full planning consent obtained Judicial Road Review period ended on 9/8/2012 no issues were raised. Detail design work will require some minor-material amendments to be made to the application. These are due to some slight practical variations in the design of the gatehouse, visitors centre, architectural treatment and surface treatment. Discharge of 75% 1/7/2015 The Bolton Road planning consent planning conditions that require more work to be conditions undertaken are the drainage, odour management, contamination and noise.
Item Percentage Target Actual Comments Complete Completion Completion Date Date
1 Bolton Road 100% July 2012 in 7/01/2013 Permit received from Environment permit process Final Agency on 5/10/2012. There are 4 pre- Business operational conditions. Case (FBC) • An odour management plan is to be submitted before the facility becomes operational • Background sampling of bio- aerosols must be undertaken • Further information on noise must be submitted • Evidence of the technical competence of the Site Manager must be supplied Judicial Review Period ended on 6/1/2013 the permit is now deemed satisfactory as Shanks have not raised any issues. Site possession 100% Shanks Contractor onsite Construction, Shanks Design and Management advisor checked Method Statements and Quality Systems, enabling works underway. Mobilisation for 100% 15/10/2012 13/8/12 Shanks Contractor mobilised plant for Enabling Works main works on site. Shanks and Birse leased office space at Patrick Tobin Business Park. The Independent Certifier has commenced his review of the design and build. Enabling works 100% 23/12/2012 All consents in place for working on the Bolton Road access road. Culvert in place, backfilling complete Mobilisation for 85% 12/12/12 7/12/2013 3SE construction sub-contractor Birse Construction mobilised for the construction of the main Bolton Road facility excavation works commenced. The EA are consulting on the discharge of dewatering effluent from site. Power on to 11% 26/8/2014 Way leaves have been applied for. permanent works Buildings 0% 29/9/2014 complete excluding planting Roads and 1% 01/10/2014 weighbridge complete Intelligent 0% 7/4/2015 Transfer Station (ITS) Commissioning ITS Acceptance 0% 20/5/2015 Tests Anaerobic 0% 12/5/2015 Digestion (AD) Commissioning Animal By- 0% 12/5/2015 Products Regulations (ABPR) Compliance AD Acceptance 0% 16/6/2016 Tests Progress 5% 1/7/2015 towards Service Commencement
2.2Ferrybridge
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.