CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council

BDR Manager's Report

Agreed Committee 1 paper

Barnsley, Doncaster and Rotherham Joint Waste Board agreed this item on Friday 15 March 2013. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

Agreed :- the Joint Waste Board expressed its preference for the partnership approach to the management of the contract. (b) The Bolton Road facility – the permit is deemed as being satisfactory, the Judicial Review period having ended on 6 th January 2013; Section 73 applications will be submitted in order to obtain planning consent for minor material amendments to the application, as a consequence of detailed design work. (c) Good progress overall continues to be made with the Ferrybridge site; the judicial review period for the S.S.E . Environmental Permit has now ended (d) Health and Safety – there were no issues of concern to report; (e) an information sharing protocol has been drafted for the three local authorities; (f) Finance – operational management costs are projected to be within budget for the current, 2012/13, financial year; (g) Communications – the ground-breaking photo-call with Elected Members, on Monday, 18 th February, 2013, had been very well publicised, some minor inaccuracies in the press reporting had now been corrected; discussions continued with the liaison group to provide information about traffic issues around the Bolton Road facility; the importance of providing regular information bulletins was acknowledged; details would shortly be available about the forthcoming project partnership awards for the Best Waste Project; (h) Preparation of the Contract Manuals is continuing. Resolved :- That the report be received and its contents noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Barnsley, Doncaster and Rotherham Joint Waste Board

ITEM 3 BDR MANAGER UPDATE REPROT

BDR WASTE PFI BDR M AN AGER UPD ATE REPORT 4/03/2013

.

1.0Governance

The WIDP Contract Management Review report was received on 15/1/2013 overall the review was positive. WIDP made some recommendations to ensure the continued effective management of the contract. These focussed around knowledge management, including the completion of the contract manuals and work instructions, communications between the collection managers and the BDR PFI team and reviewing the organisational structure of the team to ensure it remains fit for purpose in the various phases of the Contract.

The operational management team are working towards completing the contract manuals by the summer 2013.

The June Joint Waste Board will be the Annual General Meeting at which point the Chair will rotate.

2.0Project Delivery

2.1Bolton Road

Item Percentage Target Actual Comments Complete Completion Completion Date Date Bridge design 100% 24/9/2012 17/8/2012 Bridge construction to adoptable standards for 120 year life Planning Bolton 100% 10/8/2012 9/8/2012 Full planning consent obtained Judicial Road Review period ended on 9/8/2012 no issues were raised. Detail design work will require some minor-material amendments to be made to the application. These are due to some slight practical variations in the design of the gatehouse, visitors centre, architectural treatment and surface treatment. Discharge of 75% 1/7/2015 The Bolton Road planning consent planning conditions that require more work to be conditions undertaken are the drainage, odour management, contamination and noise.

Item Percentage Target Actual Comments Complete Completion Completion Date Date

1 Bolton Road 100% July 2012 in 7/01/2013 Permit received from Environment permit process Final Agency on 5/10/2012. There are 4 pre- Business operational conditions. Case (FBC) • An odour management plan is to be submitted before the facility becomes operational • Background sampling of bio- aerosols must be undertaken • Further information on noise must be submitted • Evidence of the technical competence of the Site Manager must be supplied Judicial Review Period ended on 6/1/2013 the permit is now deemed satisfactory as Shanks have not raised any issues. Site possession 100% Shanks Contractor onsite Construction, Shanks Design and Management advisor checked Method Statements and Quality Systems, enabling works underway. Mobilisation for 100% 15/10/2012 13/8/12 Shanks Contractor mobilised plant for Enabling Works main works on site. Shanks and Birse leased office space at Patrick Tobin Business Park. The Independent Certifier has commenced his review of the design and build. Enabling works 100% 23/12/2012 All consents in place for working on the Bolton Road access road. Culvert in place, backfilling complete Mobilisation for 85% 12/12/12 7/12/2013 3SE construction sub-contractor Birse Construction mobilised for the construction of the main Bolton Road facility excavation works commenced. The EA are consulting on the discharge of dewatering effluent from site. Power on to 11% 26/8/2014 Way leaves have been applied for. permanent works Buildings 0% 29/9/2014 complete excluding planting Roads and 1% 01/10/2014 weighbridge complete Intelligent 0% 7/4/2015 Transfer Station (ITS) Commissioning ITS Acceptance 0% 20/5/2015 Tests Anaerobic 0% 12/5/2015 Digestion (AD) Commissioning Animal By- 0% 12/5/2015 Products Regulations (ABPR) Compliance AD Acceptance 0% 16/6/2016 Tests Progress 5% 1/7/2015 towards Service Commencement

2.2Ferrybridge

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BDR Manager's ReportReport 43 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 9 attended
RS
Councillor Richard S. RussellMember, present
SA
Councillor Shaukat AliMember, apologies
DB
David Burton, StreetprideOfficer, absent
AG
Adrian GabrielOfficer, absent
IG
Ian GledhillOfficer, absent
TH
Tracy HolmesOfficer, absent
LK
Liz KempOfficer, absent
KB
Karl BattersbyOfficer, absent
AT
Ann ToddOfficer, absent

On this subject at Rotherham

Search all
  1. BDR Manager's ReportThis decision
  2. BDR Managers ReportAgreed
  3. BDR Managers ReportNoted
  4. BDR Managers ReportNoted
  5. BDR Managers ReportNoted
  6. BDR Managers ReportNoted

More from Rotherham Barnsley, Doncaster and Rotherham Joint Waste Board

All decisions
MeetingDecisionOutcome
16 Nov 2026 Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. Approved Open
16 Nov 2026 BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. Agreed Open
16 Nov 2026 BiffaThat the update be noted. Noted Open
16 Nov 2026 Risk RegisterThat the report be noted. Noted Open
3 Feb 2026 Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies