Rotherham MBC 04 March 2013
Risk Status Report
Current Risk Rating Controlled Control Measures
Risk Ref Risk Register Details 06/12 09/12 12/12 03/13 Rating Target Date Not Started In Progress Implemented Total % Implemented WPFIT0001 Waste PFI Waste volumes change 4 4 4 4 2 02/03/2015 0 4 1 5 20% Transition Phase WPFIT0002 Waste PFI Off site works costs increase 6 6 6 6 4 28/06/2013 0 3 1 4 25% Transition Phase WPFIT0003 Waste PFI Planning Delay 6 1 1 1 3 0 0 8 8 100% Transition Phase WPFIT0004 Waste PFI Planning Failure 8 1 1 1 4 0 0 5 5 100% Transition Phase WPFIT0005 Waste PFI Permitting Delay 12 16 8 1 8 0 0 6 6 100% Transition Phase WPFIT0006 Waste PFI Permitting Failure 8 8 1 1 4 0 0 4 4 100% Transition Phase WPFIT0007 Waste PFI Legislative Change 12 12 12 12 9 29/03/2013 0 3 2 5 40% Transition Phase WPFIT0008 Waste PFI Transport Movements 9 6 6 6 4 01/04/2014 2 1 1 4 25% Transition Phase WPFIT0009 Waste PFI Major incident at ITS/AD 12 8 8 8 8 01/07/2015 0 7 0 7 0% Transition Phase WPFIT0010 Waste PFI ITSAD fails commissioning tests 12 12 12 12 8 01/07/2015 1 3 0 4 0% Transition Phase WPFIT0011 Waste PFI Business Continuity 9 9 9 9 6 31/07/2013 0 2 3 5 60% Transition Phase WPFIT0012 Waste PFI Business Continuity 12 6 6 6 6 01/07/2015 0 5 3 8 38% Transition Phase WPFIT0013 Waste PFI Design Changes result in scope creep n/i 8 8 8 4 01/07/2015 0 7 0 7 0% Transition Phase WPFIT0014 Waste PFI Construction delay n/i 8 8 8 8 29/03/2013 0 2 0 2 0% Transition Phase 14 110 105 90 83 78 3 37 34 74 46%
Report produced by JCAD RISK © 2001-2013 JC Applications Development Page 1 of 1
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk RegisterReport | 48 KB | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. | Approved | Open |
| 16 Nov 2026 | BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. | Agreed | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.