Barnsley, Doncaster and Rotherham Joint Waste Board agreed this item on Friday 11 March 2016. Below is the council's own wording, with the papers it was decided on.
It was agreed that, in order to avoid any duplication of effort, the Internal Auditor be asked to confirm the period of time during which the requirement to check 100% of the tickets should apply. Agreed :- (1) That the report be received and its contents noted. (2) That a further report, updating the Waste Treatment Facility action plan and detailing the extent of compliance with each of the recommendations, be submitted to the next meeting of the BDR Joint Waste Board to be held on 10th June, 2016. (3) That the response of the Internal Auditor in respect of recommendation 6 of the action plan be reported to the next meeting of the BDR Joint Waste Board.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Barnsley, Doncaster and Rotherham Joint Waste Board
Appendix B Waste Treatment Facility – Action Plan Priority *** Fundamental (Action considered necessary to avoid exposure to high risk) ** Significant (Action considered necessary to avoid exposure to a significant risk) * Merits Attention (Action desirable to enhance control or value for money)
Rec. Recommendations. Priority. Responsibility. Agreed. Comments. Date. The mitigating actions detailed in the Council BDR Manager Yes The BDR Team have been Risk Register need to be progressed to full BDR Administrator notified that Jcad will no longer completion. There should be a reasonable be used for the Risk Register. timescale stated for each action and progress against this should be highlighted Currently populating the new 5.2.16 at the Joint Waste Board meetings. Any system per corporate instruction areas where there is no progress being 1 made should be highlighted to the Board for * Risk Register is considered as their information and their consideration of part of Steering Committee and whether to prioritise / allocate additional Joint Waste Board meetings resource to aid completion. Confirmation received that JCAD obsolete
The Client Team need to ensure that the BDR Administrator Yes Draft is in place 5.2.20 current risks on the Council’s Jcad system BDR Manager is to be Risk 16 are transferred to the equivalent of Jcad Register trained date to be 2 (spreadsheet format) within the service and * confirmed. the progress against these is regularly monitored.
The error highlighted in the calculation of the BDR Compliance Yes This has been highlighted to monthly Transfer Loading Station Facility Officer contractor and rebate has been 10.1.1 3 Payment to 3SE should be corrected for * applied 6 payments already made to the contractor and in the calculation of future payments for
Page 1 of 4 Appendix B Waste Treatment Facility – Action Plan Rec. Recommendations. Priority. Responsibility. Agreed. Comments. Date. waste management services to the contractor.
A base tonnage reconciliation exercise BDR Manager Yes Base tonnage reconciliations 31.10. should be performed at the end of the third BDR Compliance have already been completed. 15 quarter and quarterly thereafter. Any Officer Forecastes are monitored against revision to the base tonnage figure should be actuals each month with quarterly And applied to payments to the contractor as per adjustments made when 2/2/16 the contract payment mechanism. required.
One adjustment has been made Year 4 * in October and a further in end February. reconci liation An annual reconciliation will be – made, however the aim is for the 1.5.16 forecast adjustments to be as close to the actuals reducing the year end reconciliation. The Client Team should ensure that BDR Manager Yes Financial advisor has been 5.2.16 resources are in place to address the year- appointed to assist with the end cost/profit or pain/gain process as refinance and savings and will specified in the contract. The process assist in the year end resolutions. should be documented in order to produce a 5 formal work instruction to identify each step * Work instructions are being 1.5.16 of the process along with the roles and currently being progressed but responsibilities of staff. will not be finalised until post year reconciliation to ensure that any unforeseen items can be documented In order to gain assurance that the Council’s BDR Compliance Yes BDR Compliance Officer is 24.3.1 6 municipal waste data reporting to ** Officer checking 100% of the tickets 6 government is accurate, the Client Team retrospectively. Ticket information
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.