Rotherham Metropolitan Borough Council

BDR Joint Waste Project - Manager's Report

Agreed Committee 1 paper

Barnsley, Doncaster and Rotherham Joint Waste Board agreed this item on Friday 30 September 2016. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Agreed :- That the BDR Manager’s report be received and its contents noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Barnsley, Doncaster and Rotherham Joint Waste Board, 13 pages

BDR MANAGER UPDATE REPORT

BDR WASTE PFI BDR MA NAGER UPDATE REPORT

JUNE 2016 – AUGUST 2016

1.0Governance

1.0Inter-Authority Agreement

The IAA3 has now been signed by all 3 LA’s. The IAA3 sets out the legal framework that the three authorities adhere to wherever joint working is involved.

1.2South Yorkshire Leaders Meeting

The BDR Manager attended the South Yorkshire Leaders Meeting and presented the Annual Report. The Leaders requested further information on the recycling rates across the partnership. This information has been provided.

2.0Audit

RMBC are undertaking their second audit of the procedures and processes of the BDR contract compliance team. The first report in 2015/16 scored the BDR project as adequate; the scale for the audit report was either adequate or inadequate.

3.0Contract Performance

2.1Bolton Road

2.1.1 Contractors Representative

The Contractors Representative for the BDR PFI Contract since 2012 has previously been responsible for both the BDR and the Wakefield Contract. Shanks Waste Management has decided that it would benefit both Contracts to have a dedicated Contractors Representative.

An interim Contractors Representative is in place and will be covering the BDR Contract 4 days a week. The recruitment process for a replacement BDR Contractors Representative has commenced.

The operational management team remains the same.

1 2.1.2 Recycling and Diversion

Table 1 contains the information about the number of tonnes processed and the contract performance. There have been some issues which have impacted on the recycling performance of the facility:

• The market for recycling plastics from an MBT is poor at the moment. The price of oil is low, this means the virgin plastic material is cheap and consequently lowers the value of the recyclable material.

• Grounds maintenance waste is not being delivered to the facility.

• The SRF Offtake facility has had some downtime due to boiler and crane issues. This has impacted on the turnaround times at the Ferrybridge.

The Contractor has mitigated the impact of these issues by;-

• Paying to get plastics reprocessed

• Assigned a project team to further optimise performance and quality.

Table 2 - Tonnes Processed 1st April 2016 to 31st August 2016

Target (contract Type Tonnes Percentage estimate) Variance Total Waste Contract delivered waste only 76,403.91 Landfill 841.76 1.10% 5% +3.9% Recovery Ferrybridge 58,459.20 58.6% Other 457.30 0.5% Total 58,916.5 59.5% n/a Recycling Ferrous 1,004.28 1.21% Non-ferrous 135.74 0.15% Fines 3,768.48 5.17% Glass and 1,883.30 1.43% Stone Plastic 3,922.88 4.64% Total 10,714.68 13.60% 19.00% -5.40%

Moisture Loss 29,207.98 29.3% n.b. above figures are unaudited and subject to change. The landfill diversion target for the contract is 95% with only 5% to landfill. The contract is over performing by diverting 98.9% with only 1.10% to landfill.

2.2.4 – Waste Composition

Table 3 – Waste Composition

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BDR Joint Waste Project: Manager's ReportReport 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. BDR Joint Waste Project - Manager's ReportThis decision
  2. BDR Joint Waste Project - Manager's ReportAgreed
  3. BDR Joint Waste Project - Manager's Annual Report 2017-2018Agreed
  4. BDR Joint Waste Project - Manager's ReportAgreed
  5. BDR Joint Waste Project - Manager's ReportAgreed
  6. BDR Joint Waste Project - Manager's ReportAgreed

More from Rotherham Barnsley, Doncaster and Rotherham Joint Waste Board

All decisions
MeetingDecisionOutcome
16 Nov 2026 Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. Approved Open
16 Nov 2026 BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. Agreed Open
16 Nov 2026 BiffaThat the update be noted. Noted Open
16 Nov 2026 Risk RegisterThat the report be noted. Noted Open
3 Feb 2026 Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies