It was RESOLVED that a) the RIBA stage 3 design and cost plan recommended by the Member Group as detailed in Appendix 1 and 2 of the report, in line with the approved budget, be approved; and b) the additional costs associated with the inclusion of carbon reduction measures in line with the Council’s commitment to carbon management be approved.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1The Council’s Corporate Strategy Action Plan (2019-2023) identifies the projects the Council is dedicated to delivering. The action plan establishes development of a new leisure centre, community hall and separate office building on a Council owned site at Chapel Lane in Bingham as a priority in order to provide employment and leisure opportunities and meet the needs of a growing community.
1.2On 12 February 2019, Cabinet authorised procurement of a professional team to progress designs for the leisure and office scheme, requiring the process to be overseen by a Cabinet-led Member Group. Cabinet also approved the inclusion of £20m in the Council’s Capital Programme in order to deliver the scheme. This was subsequently supported by Council on 7 March 2019.
1.3This report provides Cabinet with an update on the designs and cost plan which have been developed with oversight from the Member Group to RIBA (Royal Institute of British Architects) stage 3. In response to the new corporate priority of The Environment, the designs incorporate a range of energy efficiency measures to minimise the carbon emissions from the facilities.
1.4A further report covering tender evaluation will be brought to Cabinet by autumn 2020 seeking approval to appoint a construction contractor.
1.5This report does not cover the ongoing positive negotiations for future operational management of the new leisure centre or the renegotiation of the joint use agreement with Nova Education Trust for continued community use of the sports halls and outdoor sports facilities at Toot Hill School.
Recommendation
It is RECOMMENDED that Cabinet:
a) Approves the RIBA stage 3 design and cost plan recommended by the Member Group as detailed in Appendix 1 and 2 in line with the approved budget; and
b) Approves the additional costs associated with the inclusion of carbon reduction measures in line with the Councils commitment to carbon management. 3. Reason for Recommendation
3.1The Member Group met four times between June and December 2019, shaping the design development process and endorsing the RIBA stage 3 designs which were submitted for planning approval on 18 December. The designs contribute to the delivery of the Bingham Master Plan, are energy efficient and meet the needs of both community leisure users and competitive swimmers.
4. Supporting Information
4.1An invitation to tender for a project management led multi-disciplinary design team was advertised through ESPO framework 2664. Eight companies submitted tenders, which following evaluation and interview resulted in the appointment of Henry Riley in July 2019.
4.2Henry Riley subsequently led a series of regular design team meetings with Council officers, and input from stakeholders such as Swim England and sports clubs. Further consultation took place through an on-line sports club user survey, public displays of draft plans, intelligence gathering from other local authority leisure providers, Bingham Growth Board, a Bingham Town Council facilitated public meeting, Network Rail and Nova Education Trust.
4.3A Cabinet-led cross party Member Group was set up to oversee the project. The group met four times in 2019, with a summary of the meeting dates and content as follows:
June – Councillors agreed the project objectives, project management structure, budget and delivery timeline.
September – Councillors commented on the findings of the on-line club survey, design considerations in relation to site layout, community hall, swimming pool spectator seating and moveable floor options for the swimming pool.
October – Councillors considered updated designs and the RIBA stage 2 cost plan for the leisure and office buildings including building finishes and carbon reduction options.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.