It was RESOLVED that: a) the RIBA stage 4 design and cost plan recommended by the Member Group as detailed in Appendix 1 and 2 of the report, which is in line with the approved budget be approved; b) the Procurement Strategy as recommended by the Member Group to use the Procurement Partnerships Framework be approved; c) responsibility for proceeding to tender be delegated to the Executive Manager for Communities in consultation with the Section 151 Officer and the Portfolio Holder for Business and Transformation and the Portfolio Holder for Finance. d) a report be brought back to Cabinet with the outcome of any tender exercise to seek approval for any phasing of the build, the procurement timetable and to appoint a construction contractor; and e) negotiation and completion of the Basic Asset Protection Agreement (BAPA) with Network Rail be delegated to the Executive Manager for Communities in consultation with the Section 151 Officer, the Monitoring Officer, the Portfolio Holder for Business and Transformation and the Portfolio Holder for Finance.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1The Council’s Corporate Strategy Action Plan (2019-2023) identifies the projects the Council is dedicated to delivering. The action plan establishes development of a new leisure centre, community hall and separate office building on a Council owned site at Chapel Lane in Bingham as a priority in order to provide employment and leisure opportunities in the area, and meet the needs of a growing community.
1.2On 12 February 2019, Cabinet authorised procurement of a professional team to progress designs for the leisure and office scheme, requiring the process to be overseen by a Cabinet-led Member Group. Cabinet also approved the inclusion of £20m in the Council’s Capital Programme to deliver the scheme. This was subsequently supported by Council on 7 March 2019.
1.3On 14 January 2020, Cabinet approved the RIBA (Royal Institute of British Architects) stage 3 design and cost plan in line with agreed budgets; and also approved the additional costs associated with the inclusion of carbon reduction measures in line with the Council’s commitment to carbon management.
1.4This report provides Cabinet with an update on the designs and cost plan, which have been developed with oversight from the Member Group to RIBA stage 4. In response to the technical challenges of the site and following value engineering exercises, the report incorporates several changes to minimise unnecessary cost whilst maximising the energy efficiently and sustainability of the facilities.
1.5On 10 March and 2 June 2020, the Bingham Leisure Centre Member Group provided oversight and feedback in relation to the design proposals, cost plan, existing leisure contract, proposals for naming of the leisure/community hall and office buildings, and the procurement strategy.
1.6A further report covering tender evaluation will be brought to a future Cabinet seeking approval to appoint a construction contractor. 1.7. This report does not cover:
the ongoing negotiations for future operational management of the new leisure centre, these will be presented to a future Cabinet meeting;
the renegotiation of the joint use agreement with Nova Education Trust for continued community use of the sports halls and outdoor sports facilities at Toot Hill School; and
the tender timetable in response to the Covid-19 global pandemic. It seeks to delegate responsibility to the Executive Manager for Communities, in consultation with the Portfolio Holder for Business and Transformation, to satisfy themselves that proposals are appropriate and invitations to tender are not issued until the market can respond accordingly.
1.8The Council is currently considering all Capital Programme projects in light of the current Covid-19 crisis, the development and phasing of the Bingham Chapel Lane development will be considered as part of this process.
Recommendation
It is RECOMMENDED that Cabinet:
a) Approves the RIBA stage 4 design and cost plan recommended by the Member Group as detailed in Appendix 1 and 2, which is in line with the approved budget.
b) Approves the Procurement Strategy as recommended by the Member Group to use the Procurement Partnerships Framework.
c) Delegates responsibility for proceeding to tender to the Executive Manager for Communities in consultation with the Portfolio Holder for Business and Transformation.
d) Agrees that a report be brought back to Cabinet with the outcome of any tender exercise to seek approval for any phasing of the build, the procurement timetable and to appoint a construction contractor.
e) Delegates negotiation and completion of the Basic Asset Protection Agreement (BAPA) with Network Rail to the Executive Manager for Communities in consultation with the Section 151 officer and the Monitoring Officer.
Reasons for recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.