It was RESOLVED that a) firm D be appointed as the preferred contractor for the full development, subject to external funding being secured; Or b) if external funding for the office is not secured, the tender be accepted for the leisure centre and community hall build only, with a further report to be submitted to a future Cabinet meeting, to seek a way forward regarding the office element of the development prior to accepting tender for the full development.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1The Council’s Corporate Strategy Action Plan (2019-2023) identifies the projects the Council is dedicated to delivering. The Action Plan establishes development of a new leisure centre, community hall and separate office building on a Council owned site at Chapel Lane in Bingham, as a priority in order to provide employment and leisure opportunities in the area and meet the needs of a growing community.
1.2On 12 February 2019, Cabinet approved the inclusion of £20m in the Council’s Capital Programme to deliver the scheme. This was subsequently supported by Council on 7 March 2019.
1.3On 14 January 2020, Cabinet approved the RIBA (Royal Institute of British Architects) stage 3 design and cost plan in line with agreed budgets; and approved the additional costs associated with the inclusion of carbon reduction measures in line with the Council’s commitment to carbon management.
1.4On 9 June 2020, Cabinet approved the RIBA stage 4 design and cost plan recommended by the member group in line with agreed budget, approved the procurement strategy as recommended by the member group to use the Procure Partnership Framework. Cabinet delegated the responsibility for proceeding to tender and the negotiation and completion of the Basic Asset Project Agreement (BAPA) to the Executive Manager for Communities, in consultation with the Section 151 Officer and the Portfolio Holder for Business and Transformation and the Portfolio Holder for Finance. This was completed on 11 August 2020.
1.5The member group has met seven times between June 2019 and November 2020, shaping the design development process. The designs contribute to the delivery of the Bingham Master Plan, are energy efficient and meet the needs of both community leisure users and competitive swimmers.
1.6On 26 November 2020, the member group met to consider and endorse the tender report and shape the recommendation to Cabinet. The member group was satisfied with the proposals and supported the approval of the development. The member group was however particularly concerned that if the external funding is not achieved then the office development may not proceed. They suggested that if this was the case, a further report should be brought back to Cabinet to consider the best way forward for this element of the development, within the period for approval of the tender.
1.7This report provides details of the procurement exercise for the appointment of the main contractor for the redevelopment of the Chapel Lane site to provide a combined leisure centre and community hall, and a separate office hub to be used by the business community.
1.8The report identifies that, on a cost and quality basis, Firm D should be appointed as the preferred contractor for this development. It also identifies that Firm D proposed a contract period of 64 weeks which should form the basis of the contract with Firm D. The build cost for the project is currently estimated to be £17.9m.
1.9Whilst positive negotiations are ongoing, this report does not cover;
the future operational management of the new leisure centre with Parkwood Leisure, options will be presented to a future Cabinet meeting; or
the renegotiation of the joint use agreement with Nova Education Trust for continued community use of the sports halls and outdoor sports facilities at Toot Hill School.
Recommendation
It is RECOMMENDED that Cabinet:
a) Appoints Firm D as the preferred contractor for the full development subject to external funding being secured
Or
b) If external funding for the office is not secured, the tender be accepted for the leisure centre and community hall build only. A further report will be brought back to a future Cabinet to seek a way forward regarding the office element of the development prior to accepting tender for the full development.
Reasons for recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.