Resolved
RESOLVED that (i) The latest Capital Programme monitoring position, as set out in Report No. FIN1932, be noted ; and (ii) the additional capital requests for 2019/20, as set out in the Report, be approved.
Cabinet noted this item on Tuesday 12 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that (i) The latest Capital Programme monitoring position, as set out in Report No. FIN1932, be noted ; and (ii) the additional capital requests for 2019/20, as set out in the Report, be approved.
This report informs Members of the latest forecast of the Council’s Capital Programme for 2019/20 based on the monitoring exercise carried out during September 2019.
Members are requested to:
i) Note the latest Capital Programme position, as set out in Tables 1 and 2. ii) Approve the additional capital requests during 2019/20, as set out in paragraph 3.7
1 INTRODUCTION
1.1This report informs Members of the latest forecast regarding the Council’s Capital Programme for the first two quarters of 2019/20, based on the monitoring exercise carried out during September.
3.1There are some projects of major financial significance included in the Council’s approved Capital Programme for 2019/20. These projects are: (a) Aldershot Town Centre Integration and Union Street (b) Civic Quarter development (c) finalisation of a loan to Farnborough International, and, (d) further acquisition of investment properties.
2.1Financial Services, in consultation with relevant budget officers, carry out regular monitoring of the Capital Programme.
2.2A summary of the overall position is shown in Appendix A.
2 CURRENT POSITION
3.2The Council approved the Capital Programme of £70.231m on 21 February 2019 with the latest budget for the Capital Programme being £72.284m, an increase of £2.053m largely due to slippage from 2018/19. Table 1 shows the reconciliation of budget changes together with the projected actual capital expenditure for the year 2019/20. Table 1: Analysis of capital expenditure and approved budget 2019/20 £000’s
Total approved budget for the year 2019/20 70,231
Less: Additional budget approvals made for the year 2019/20 * (31,359)
Add: Slippage form 2018/19 ** 34,012
Total approved budget for 2019/20 72,884
Actual plus commitments as at Quarter 2 32,191
Forecast capital expenditure for the year 62,495
Net favourable variance (against approved budget) (10,389)
Projected Slippage/(Pre-spend) to 2020/21 *** 9,954
* Cabinet Reports RP1902 (08/01/2019), RP1903 (05/02/2019) and RP1904 (05/03/2019) included cabinet decisions that brought forward capital budget from 2019/20 to 2018/19. Net total includes additional in-year budget changes ** As reported to Cabinet in the General Fund Provisional Outturn report FIN1920 (28/05/2019) *** Projected slippage based on the forecast at Q2.
3.3Table 2 shows the outturn forecast for each scheme with a a Portfolio summary of all approved projects is shown at Appendix A to this report. This Appendix includes a list of all expenditure and grant/contribution variations that have been approved since Full Council approved the Estimate for 2019/20 on 21 February 2019.
3.4The Capital Programme is a significant undertaking for the Council in terms of magnitude and complexity. The scale of the projected slippage into 2019/20 and variation in programme highlights the need for close monitoring and clear project management across the whole Council.
3.5During the year to date actual expenditure including commitments is £32.2m. £30.3m is due to be spent by the year-end, predominantly as part of programmed regeneration and investment property purchases. Given the nature of the capital projects, there is a degree of risk in the outturn forecast given the level of expenditure required in Q3 and Q4 to match the outturn forecast.
3.6Additional approvals of -£31.4m since budget approval relates to funds being drawn forward into 2018/19 to facilitate regeneration and investment property purchases. The timing of any property purchase can be fluid and any movement in the capital programme is reported for approval.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME MONITORING AND FORECASTING 2019/20: POSITION AS AT SEPTEMBER, 2019Report | 292 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.