CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushmoor Borough Council
Cabinet, Tuesday 14 July 2020 at 5.00pm

REGENERATING RUSHMOOR PROGRAMME - UNION STREET, ALDERSHOT REGENERATION SCHEME

Noted Executive 1 paper

Cabinet noted this item on Tuesday 14 July 2020. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that (i) the update on the due diligence being undertaken and the proposed decision making process, as set out in Report No. RP2011, be noted; (ii) the progression of the demolition of the site, including the procurement of demolition services and the awarding of contracts (up to £1.25 million) through an appropriate framework, to clear and prepare the site for construction as soon as practicable, be approved; (iii) the meeting of the demolition and site clearance costs from the capital budgets already set aside for the regeneration of Union Street, Aldershot be approved; (iv) the establishment of an internal (client) project team be noted and the appointment of other advisers and the procurement of advice, as necessary, to complete the due diligence process and support the demolition and clearance of the site be approved, with the costs being met from budgets already agreed for the regeneration programme; (v) in relation to planning application no. 20/00171/FULPP, t he entering into the necessary legal agreement(s) in relation to the planning obligations set out in Section 4.4 to secure planning consent in a timely manner be approved; (vi) the appointment of external solicitors to progress the Agreement for Lease and associated documents with the University for the Creative Arts be noted; and (vii) the formal approval by the Enterprise M3 LEP of grant funding of £1.2 million be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Summary

This report set outs a progress update in relation to the redevelopment of Union Street, Aldershot. It also seeks the necessary approvals to undertake demolition and clearance of the site and maintain the development timetable that ensures the Council can make best use of external grant funding that has been secured against the scheme.

Recommendation

That Cabinet;

1. Notes the update on the due diligence being undertaken and proposed decision making process. 2. Agrees to move forward with the demolition of the site including procurement of demolition services and award of contracts through an appropriate framework to clear and prepare the site for construction as soon as practicable. 3. That the costs of demolition and site clearance be met from the capital budgets already set aside for the regeneration of Union Street. 4. Notes the establishment of an internal (client) project team and approves appointment of other advisors and procurement of advice as necessary to complete the due diligence and support the demolition and clearance of the site with the costs being met from budgets already agreed for the regeneration programme. 5. In relation to planning application (ref: 20/00171/FULPP) to agree to enter into the necessary legal agreement(s) in relation to the planning obligations set out in section 4.4 to secure planning approval in a timely manner. 6. Notes the appointment of external solicitors to progress with the Agreement for Lease and associated documents with the University for the Creative Arts (UCA). 7. Notes that £1.2m of grant funding from the Enterprise M3 LEP has now been formally approved. 1. INTRODUCTION

1.1The regeneration of land at Union Street in Aldershot Town Centre is a Council priority. Delegated authority was provided to the Executive Head of Regeneration and Property (RP2005) to submit planning applications and secure the appropriate permissions as required to enable the Union Street regeneration scheme in Aldershot Town Centre. The planning application was submitted in early March 2020 and was approved by the Development Management Committee on 24 June.

1.2Cabinet Report RP2008 outlined the next steps and shared the Rushmoor Development Partnership’s Project Plan in relation to the redevelopment of the site. The report detailed what could be progressed, what was being reviewed, set out arrangements for due diligence and highlighted the potential delays in the programme for other elements.

1.3This Report provides Cabinet with a further update as at end June 2020 and seeks a range of approvals to progress the scheme.

Background

2.1The regeneration of Aldershot Town Centre is a corporate priority and Union Street is identified as a key site allocation for regeneration within the Rushmoor Local Plan (adopted February 2019) and the Aldershot Prospectus SPD. It has formed part of the portfolio of sites being progressed by the RDP since its inception in late 2018.

2.2Following Cabinet approval (RP2005), a planning application was submitted to the Local Authority by the RDP on the 4 th March 2020 for a mixed use scheme comprising 100 residential units, purpose built student accommodation (PBSA) (128-bed spaces) for the University for the Creative Arts (UCA) and ground floor commercial uses (2,237sqm GEA) focused around a central yard with an independent trader focus. The submission followed on from a period of public consultation in January/February 2020, with two public drop-in sessions held in Aldershot town centre on the 16th and 18th January. From the responses received to the feedback forms, approximately 80% of respondents supported the proposals that were presented and 97% agreed that Aldershot town centre needs regeneration. The planning application seeks to be planning policy compliant in providing 20% of housing units as affordable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REGENERATING RUSHMOOR PROGRAMME: UNION STREET, ALDERSHOT REGENERATION SCHEMEReport 155 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
MM
Councillor Marina MunroCommittee Member, present
AN
Councillor Adrian NewellCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. REGENERATING RUSHMOOR PROGRAMME - UNION STREET, ALDERSHOT REGENERATION SCHEMEThis decision
  2. Regenerating rushmoor programme - the galleries progress update and next stepsApproved
  3. Regenerating rushmoor programme - farnborough projects funding requirementApproved
  4. Regenerating rushmoor programme - union yard regeneration schemeNoted
  5. Appointment of an investment partner to support the regenerating rushmoor programmeApproved
  6. Regenerating rushmoor programmeApproved

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies