RESOLVED (a) that the outcomes of the further due diligence, as set out in Report No. RP2106 and in the reports by Grant Thornton UK LLP and Lambert Smith Hampton Investment Management, in respect of development viability and financial modelling, be noted; (b) to proceed with the Union Yard scheme, on the basis of a fixed price contract with the project budget, as set out in the Restricted Minute appended; (c) to enter into a contract with Hill Partnerships Limited, by means of a Joint Contracts Tribunal (JCT) Design and Build contract, for the delivery of the scheme ; (d) that the additional energy efficiency improvements, as set out in the Report, not be progressed; (e) that a Union Yard Project Board ne established for the next stage of the ... view the full minutes text for item 19.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
This report sets out the further due diligence and financial modelling that has been undertaken since the report considered by Cabinet in April (RP2103) in respect of the Union Yard scheme and updates the project risks. The report principally seeks a recommendation to Council for the funding to proceed with the main build contract and Cabinet approval to enter into contract with Hill Partnerships Limited.
Recommendation
That Cabinet:
1. Note the outcomes of the further due diligence set out in this report and in the reports by Grant Thornton UK LLP (GT) and Lambert Smith Hampton Investment Management (LSHIM) in respect of development viability and financial modelling;
2. Agree to proceed with the Union Yard scheme on the basis of a fixed price contract with the proposed project budget set out at exempt Appendix E comprising the direct and indirect costs and recommend to Council to amend the capital programme accordingly;
3. Agree to enter into contract with Hill Partnerships Limited by means of a JCT Design and Build contract for the delivery of the scheme;
4. Consider the proposals and cost implications relating to energy efficiency improvements that can be achieved from further changes to the scheme design and agree any variations; 5. Agrees to the establishment of a Union Yard Project Board for the next stage of the project. The Board to include the Major Property and Projects Portfolio Holder, the Corporate Services Portfolio Holder and the Leader of the Labour Group to work alongside officers in providing oversight on the delivery of the consented scheme;
6. Recommended the Council to delegate authority to the Executive Head of Finance to amend the Treasury Management Strategy and associated prudential indicators in accordance with Council’s decision regarding the scheme.
7. Note the next steps.
1. INTRODUCTION
1.1The Cabinet meeting held on the 20th April considered a substantial report setting out due diligence work that had been undertaken to date in relation to the Union Street redevelopment, now known as Union Yard. At that meeting, Cabinet agreed to move forward to the next stage of development and the appointment of Hill Partnerships Limited for technical design and site preliminary works. Cabinet also agreed that up to £2.2m Housing Infrastructure Fund grant funding be used to cover the costs associated with RIBA Stage 4: Technical Design and preliminary works associated with the consented scheme in order to minimise delay in the delivery of the scheme.
1.2Cabinet noted the next steps and that a further report would be presented to Cabinet in due course to enable a final decision to proceed with the scheme with a recommendation to Council to approve further capital expenditure required to deliver the Union Street development.
1.3This report sets out the further due diligence and financial modelling that has been undertaken since the April report and updates the project risks. It seeks the necessary financial approvals to proceed with the main build contract and seeks to establish the appropriate project governance required in order to provide oversight and manage risk as the build progresses.
Background
2.1The regeneration of Aldershot Town Centre is a corporate priority and Union Street is identified as a key site allocation for regeneration within the Rushmoor Local Plan (adopted February 2019) and the Aldershot Prospectus SPD. It has formed part of the portfolio of sites being progressed by the RDP since its inception in late 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.