REGENERATING RUSHMOOR PROGRAMME - UNION YARD REGENERATION SCHEME

Noted Executive 2 papers

Cabinet noted this item on Wednesday 28 July 2021. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

RESOLVED (a) that the outcomes of the further due diligence, as set out in Report No. RP2106 and in the reports by Grant Thornton UK LLP and Lambert Smith Hampton Investment Management, in respect of development viability and financial modelling, be noted; (b) to proceed with the Union Yard scheme, on the basis of a fixed price contract with the project budget, as set out in the Restricted Minute appended; (c) to enter into a contract with Hill Partnerships Limited, by means of a Joint Contracts Tribunal (JCT) Design and Build contract, for the delivery of the scheme ; (d) that the additional energy efficiency improvements, as set out in the Report, not be progressed; (e) that a Union Yard Project Board ne established for the next stage of the ... view the full minutes text for item 19.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Summary

This report sets out the further due diligence and financial modelling that has been undertaken since the report considered by Cabinet in April (RP2103) in respect of the Union Yard scheme and updates the project risks. The report principally seeks a recommendation to Council for the funding to proceed with the main build contract and Cabinet approval to enter into contract with Hill Partnerships Limited.

Recommendation

That Cabinet:

1. Note the outcomes of the further due diligence set out in this report and in the reports by Grant Thornton UK LLP (GT) and Lambert Smith Hampton Investment Management (LSHIM) in respect of development viability and financial modelling;

2. Agree to proceed with the Union Yard scheme on the basis of a fixed price contract with the proposed project budget set out at exempt Appendix E comprising the direct and indirect costs and recommend to Council to amend the capital programme accordingly;

3. Agree to enter into contract with Hill Partnerships Limited by means of a JCT Design and Build contract for the delivery of the scheme;

4. Consider the proposals and cost implications relating to energy efficiency improvements that can be achieved from further changes to the scheme design and agree any variations; 5. Agrees to the establishment of a Union Yard Project Board for the next stage of the project. The Board to include the Major Property and Projects Portfolio Holder, the Corporate Services Portfolio Holder and the Leader of the Labour Group to work alongside officers in providing oversight on the delivery of the consented scheme;

6. Recommended the Council to delegate authority to the Executive Head of Finance to amend the Treasury Management Strategy and associated prudential indicators in accordance with Council’s decision regarding the scheme.

7. Note the next steps.

1. INTRODUCTION

1.1The Cabinet meeting held on the 20th April considered a substantial report setting out due diligence work that had been undertaken to date in relation to the Union Street redevelopment, now known as Union Yard. At that meeting, Cabinet agreed to move forward to the next stage of development and the appointment of Hill Partnerships Limited for technical design and site preliminary works. Cabinet also agreed that up to £2.2m Housing Infrastructure Fund grant funding be used to cover the costs associated with RIBA Stage 4: Technical Design and preliminary works associated with the consented scheme in order to minimise delay in the delivery of the scheme.

1.2Cabinet noted the next steps and that a further report would be presented to Cabinet in due course to enable a final decision to proceed with the scheme with a recommendation to Council to approve further capital expenditure required to deliver the Union Street development.

1.3This report sets out the further due diligence and financial modelling that has been undertaken since the April report and updates the project risks. It seeks the necessary financial approvals to proceed with the main build contract and seeks to establish the appropriate project governance required in order to provide oversight and manage risk as the build progresses.

Background

2.1The regeneration of Aldershot Town Centre is a corporate priority and Union Street is identified as a key site allocation for regeneration within the Rushmoor Local Plan (adopted February 2019) and the Aldershot Prospectus SPD. It has formed part of the portfolio of sites being progressed by the RDP since its inception in late 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REGENERATING RUSHMOOR PROGRAMME: UNION YARD REGENERATION SCHEMEReport 226 KB DownloadRead as text
PDF
Regenerating Rushmoor Programme: Union Yard regeneration scheme: Appendix DAppendix 472 KB Download

At this meeting

Whole meeting
18MINUTESOn the agenda
19REGENERATING RUSHMOOR PROGRAMME - UNION YARD REGENERATION SCHEMEThis decision

Who was there

6 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, apologies
MM
Councillor Marina MunroCommittee Member, present
AN
Councillor Adrian NewellCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. REGENERATING RUSHMOOR PROGRAMME - UNION YARD REGENERATION SCHEMEThis decision
  2. Regenerating rushmoor programme - the galleries progress update and next stepsApproved
  3. Regenerating rushmoor programme - farnborough projects funding requirementApproved
  4. Regenerating rushmoor programme - union street, aldershot regeneration schemeNoted
  5. Appointment of an investment partner to support the regenerating rushmoor programmeApproved
  6. Regenerating rushmoor programmeApproved

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies