Salford City Council and Salford Community Leisure Management Agreement - Extension to Contract

Approved Committee 2 papers

Procurement Board approved this item on Wednesday 28 March 2018. Below is the council's own wording, with the papers it was decided on.

Item5a

Resolved

Salford City Council - Record of Decision I Paul Dennett, City Mayor , in exercise of the powers contained within the City Council constitution do hereby: approve an extension agreement on behalf of the City Council with Salford Community Leisure Limited (SCL) for a 5 year period from 31 st March 2020, to expire on 31 st March 2025. The Reasons are: SCL are a trusted partner and in order to deliver the recently approved Indoor Sports Facility Improvement Programme and Library Service Improvement Plan, together with delivering the existing savings programme and income targets, SCL must continue to invest and maintain a high level of customer experience. SCL have delivered efficiencies and the cost to the Council has reduced over the period of the contract by an annual £4.5m (management fee reduction), whilst at the same time SCL continue to deliver quality services and good performance. As well as providing contracted services SCL has engaged pro-actively across the Council to support health and wellbeing initiatives and the Council's anti poverty strategy. Longevity of the arrangements provides reassurance to the Board and management of SCL to continue to reinvest surpluses in the facilities to reinvest income and commercial opportunity further. The work with Sport England and National Governing Bodies on facility strategies will provide a medium and long term strategy for sports facilities across the City. To achieve the outcomes it is likely the process will be phased over a number of years. The extension of the arrangements with SCL provide confidence, consistency and stability for Sport England, National Governing Bodies and other funders. The extension also provides the Board of SCL the confidence to raise and provide capital within this ‘invest to save programme’. Options considered and rejected was the termination of the contract but the effectiveness of SCL to the Council and the terms of the contract allowed for the extension. Assessment of Risk : LOW The source of funding is the Revenue Budget Legal Advice obtained: Yes . Financial Advice obtained: Yes . Procurement Advice obtained: Yes. The following documents have been used to assist the decision process. SCL Agreement, KKP Independent report Contact Officer: David Seager Tel No 0161 925 1115 * This decision is not subject to consideration by another Lead Member * The appropriate scrutiny committee to call-in the decision is the Overview & Scrutiny Board. Signed: PAUL DENNETT Dated: 18 APRIL 2018 City Mayor FOR DEMOCRATIC SERVICES USE ONLY * This decision was published on 18 April 2018 * This decision will come in force at 4.00 p.m. on 25 April 2018 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendations

That Procurement Board approves an extension agreement on behalf of the City Council with Salford Community Leisure Limited (SCL) for a 5 year period from 31st March 2020, to expire on 31st March 2025.

Detail required Contract Reference Title/Description of Contracted Salford Community Leisure Management Service/Supply/Project Agreement Name of Contractor Salford Community Leisure Type of organisation Registered Charity (to be supplied by Corporate Procurement) Status of Organisation SME (to be supplied by Corporate Procurement) Value of Contract Extension £4.1M Mgt Fee Choose an item. Existing Contract Term 01/04/2004 to 31/03/2020 Extension Period Requested 01/04/2020 to 31/03/2025 Contact Officer (Name & number) Dave Seager

Lead Service Group Place

Funding Source Revenue Budget

Executive summary

The report details a proposed extension agreement between Salford City Council and Salford Community Leisure that will extend the agreement for a further 5 years. This will enable both parties, with other key partners, to continue to plan, invest and work on delivering the indoor sports facility improvement programme, playing pitch improvements, library service improvement programme and other works across the leisure and culture sector.

1 BACKGROUND DOCUMENTS:

Community Leisure & Facilities Management Agreement 2003

KEY DECISION: Yes

KEY COUNCIL POLICIES: City Plan, Health and Wellbeing Strategy, Salford Locality Plan, Salford 2025 Regeneration Strategy

EQUALITY IMPACT ASSESSMENT AND IMPLICATIONS:

There are no equality impact issues arising from this decision. Salford Community Leisure is a community benefit society with the following values:  Openness – nobody’s perfect, and we won’t hide it when we’re not  Honesty – we are honest about what we do and the way we do it  Social responsibility – we encourage people to take responsibility for their own actions and their community  Caring for others – we support local charities and we always strive to think about the consequences of our actions on others.

SCL’s co-operative values  Self help – we help people and groups to help themselves  Self-responsibility – we take responsibility for, and answer to our actions  Democracy – we give members a say in the way we run the organisation  Equality – every member has one vote  Equity – we operate fairly and are unbiased  Solidarity – we share interests and common purposes with our members and other similar organisations.

ASSESSMENT OF RISK: Low

LEGAL IMPLICATIONS Supplied by: Tony Hatton, Principal Solicitor, 0161 219 6323

When commissioning contracts for the provision of goods, services or the execution of works, the Council must comply with the provisions of the Public Contracts Regulations 2015 (the Regs) and its own Contractual Standing Orders (CSO’s) as set out in the Constitution, failing which the award of a contract may be subject to legal challenge.

It is an established principle that an existing public contract is capable of being extended (or modified providing any modification does not affect the overall nature of the contract), and CSO’s also allow for contract extensions to be made, where the parties agree and where the original contract makes provision for such an extension of the original term. In view of the value of the extension the approval should be made by Procurement Board recommending the same to the City Mayor for decision.

When the contract was originally put out to tender by way of a fully compliant OJEU process, and subsequently awarded to SCL, it was made clear in the documentation that the original 16 year term would be subject to a potential extension of up to five years, hence any risk that the proposed extension would be subject to realistic challenge by an aggrieved provider, on

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05(a): App 1: KKP Evaluation of SCLAppendix 6.1 MB Download
PDF
Salford City Council and Salford Community Leisure Management Agreement: Extension to ContractReport 195 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 6 attended
PB
Paula BoshellCommittee Member, apologies
PD
Paul DennettCommittee Member, apologies
CF
Christine FliskCouncil Staff, expected
JH
Joanne HardmanCouncil Staff, expected
BH
Bill HindsChair, present
JM
John Merry CBECommittee Member, present

On this subject at Salford

Search all
  1. Salford City Council and Salford Community Leisure Management Agreement - Extension to ContractThis decision
  2. Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Approved
  3. City of Salford (Camp Street, Grecian Street, Neptune Gardens, & Trojan Gardens, Broughton) (No Waiting At Any Time) Order 2025.Refused
  4. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  5. Better Bus Routes - Salford Crescent to MediaCityUK - Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)Approved
  6. Better Bus Routes - Salford Crescent to MediaCityUK - the Bund going out to tender/ competition (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies