Salford City Council - Record of Decision I Councillor Paula Boshell, Deputy City Mayor In exercise of the powers contained within the City Council constitution do hereby approve the proposed programme of work for the Highway Drainage Investment Programme (DIP) and the Culvert Investment Programme (CIP) for 2018/19 The Reasons are to facilitate continuous improvement of the highway drainage infrastructure as part of the defined Network Recovery Plan as part of the ongoing rolling programme of drainage repair works Options considered and rejected were : None Assessment of Risk : Medium – It is important that the existing highway drainage infrastructure improvements continue in order to ensure that surface flooding is minimised and that the capacity of existing systems is maximised, especially in view of the recent weather conditions that have been experienced within the City. The source of funding is : Prudential Code funding (Capital) Legal Advice obtained: Yes- Tony Hatton- Principal Solicitor-0161 219 6323 Financial Advice obtained: Yes – Alison Woods, Finance Officer, Tel . 925 1135 Procurement Advice obtained: Yes- Christine Flisk, Category Manager level 2 ext 6245 The following documents have been used to assist the decision process. Report submitted to Property/Regeneration Briefing held on 14 th May 2018 Contact Officer: Steve Mangan Tel No 0161 603 4034 This decision is not subject to consideration by another Assistant Mayor /Director The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed : Councillor Paula Boshell Deputy City Mayor Dated: 14 th May 2018 * This decision was published on Monday, 14 th May 2018 . * This decision will come in force at 4.00 pm on Monday, 21 st May 2018 # unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting.Source: sccdemocracy.salford.gov.uk
That the City Mayor approves the proposed programme of work for the Highway Drainage Investment Programme (DIP) and the Culvert Investment Programme (CIP) for 2018/19 as outlined in the report.
Executive summary
The financial provision for the Highway Drainage Investment Programme for 2018/19 and the Culvert Investment Programme for 2018/19 has been confirmed as £700,000 (£600,000 and £100,000 respectively). The budget apportionments given in the report and detailed within the background document outline the 2018/19 scheme proposals as part of the ongoing rolling programme of drainage repair works. The works identified for inclusion within the Culvert Investment Programme are also outlined in the report.
BACKGROUND DOCUMENTS:
KEY DECISION: Yes: All wards are affected
DETAILS:
1. The Highway Drainage Investment Programme
1 1.1 Initial surveys and investigations into the condition of the highway drainage infrastructure identified many defective gullies and connections. The cause of many of these defects is attributed to damaged pipe work, which over time has allowed water to erode the carriageway foundation and cause failures. The repairs required usually consist of a small excavation to expose and repair the damaged sections of pipe work followed by backfill and reinstatement. 1.2 To date 5,564 of these defects have been addressed as summarised below in Table 1
Blocked Number of gullies covers lifted cleared with and greased New New concentrated following Gully Gully Gully General jetting & concentrated Connection Pots Covers Drainage Neighbourhood cleansing effort. Repairs installed installed Repairs Totals Irlam & Cadishead 377 75 70 25 60 12 619 Claremont & Weaste 190 165 30 87 135 7 614
Profit Difference (13%-8.15%) depot works costs 0.0485 23,921
Total Budget for programme 600,000 Table 2 – proposed apportionment of DIP allocation. *Please note that the specified overhead figures are provisional percentages and are subject to final approval from Salford City Council
1.4The rolling programme of repairs will continue during 2017/18 to reduce the identified backlog of repairs. Details are as shown in Table 3 below. The programme has been prioritised using a risk-based approach to ensure that the worst areas of flooding and structural defects are addressed first. The programme has been identified in response to the following criteria:
where flooding affects, or is likely to affect property;
locations adjacent to well used footways;
where standing water is at critical turning or braking points; and
where flooding is frequent and has been persistent for some years.
1.5The proposed programme of work is highlighted in Table 3 below
Neighbourhood General Highway Drainage Repairs Claremont & Weaste 24
3 East Salford 6 Eccles 43 Irlam & Cadishead 11 Ordsall & Langworthy 35 Swinton 68 Walkden & Little Hulton 65 Worsley & Boothstown 43 Grand Total 295 Table 3 - Proposed Programme of Works
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.