Salford City Council - Record of Decision I Paul Dennett, City Mayor , in exercise of the powers contained within the City Council constitution do hereby: Approve the proposed programmes of work for the Highways Investment Programme (HIP) for 2020/21 The Reasons are: To facilitate continuous improvement of the highway infrastructure as part of the defined Network Recovery Plan as part of the ongoing rolling programme of repair works Options considered and rejected were : No other options were considered for this report. Assessment of Risk : Low – The targeted spend of available funding will ensure that the City Council’s statutory obligations are met while at the same time facilitating continuous improvement of the highway infrastructure. The source of funding is : Prudential Code funding (Capital) Legal Advice obtained : Tony Hatton Principal Solicitor 219 6323 Financial Advice obtained : Alison Woods Finance Officer Capital 0161 925 1135 Procurement Advice obtained Tom Woods Procurement Officer 0161 686 6296 The following documents have been used to assist the decision process. Report to Property/Regeneration Briefing held on 22 June 2020 Contact Officer: Steve Mangan Tel No 0161 603 4034 The appropriate scrutiny panels to call-in the decision are the Overview and Scrutiny Board and the Growth and Prosperity Scrutiny Panel______________________ Signed: Paul Dennett City Mayor Dated: 22 June 2020 This decision was published o n Monday 22 June 2020 This decision will come in force at 4.00 p.m. on Monday 29 June 2020 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting.Source: sccdemocracy.salford.gov.uk
That the City Mayor notes the proposed programmes of work for the Highways Investment Programme (HIP) for 2020/21, and subject to any matters arising, the report is submitted for approval on the 8th June. .
EXECUTIVE SUMMARY: The financial provision for the Highway Investment Programme funding for 2020/21 is at £1,800,000. The budget apportionments outlined in the report, and detailed within the background document, outline the 2020/21 scheme proposals as part of the ongoing Network Recovery Programme.
BACKGROUND DOCUMENTS:
Appendix A Highway Investment Programme- List of Provisional Schemes 2020/21
KEY DECISION: Yes
1 DETAILS:
1. The Highway Investment Programme
1.1The Capital allocation for highway structural maintenance during 2020/21 is £1,800,000. 1.2 Salford City Council implemented a Network Recovery Plan (delivered through the Highway Investment Programme) in 2009/10. This was implemented to arrest the deterioration of the highway network initially and to enable the Council to tackle the critical sections of highway thereafter. 1.3 Since its commencement in 2009/10, the Network Recovery Plan has seen an improvement in overall carriageway and footway condition, across all classifications of the adopted highway network, as shown in Tables 1 and 2 below. % of classification within each category Target %age 2010- 2011- 2012- 2013- 2014- 2015- 2016- 2017- 2018- 2019- 2020- Classification Rating 11 121 132 14 15 16 17 18 19 20 21*
Table 1 – Carriageway Condition Index Summary (The Highway Improvement Programme commenced in 2009/10) *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment and these are therefore currently affected by the investment levels provided which is less than the investment requested. The indices provided are based on the current investment levels provided
% of classification within each category Condition 2010- 2011- 2012- 2013- 2014- 2015- 2016- 2017- 2018- 2019- 2020- category 11 12 13 14 15 16 17 18 19* 20 21
Table 2 – Footway Condition Index Summary (The Highway Improvement Programme commenced in 2009/10)
2 *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment and these are therefore currently affected by the investment levels provided which is less than the investment requested. The indices provided are based on the current investment levels provided
1.4Due to the reduced funding provision from 2016/17, the request put forward for funding for 2019/20 was £3.8million however the allocation has been provided at £1.8 million. This is likely to result in deterioration of the network due to this lower level of funding provision. However, it should be noted that there will still be some benefit provided by historic funding levels. The targets for steady state are based on this year’s funding provision of £1.8 million.
1.5The anticipated rise in the percentage of critical carriageways is due in part to some of the early Micro Asphalt treatments that were applied at the start of the Highway Investment Programme are now reaching the end of their projected lifecycle and are showing signs of deterioration.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.