CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Salford City Council
Property / Regeneration Briefing, Monday 26 January 2026 at 3.00pm

Highways Investment Programme 2026/27

Approved Committee 1 paper

AI summarySalford's Deputy City Mayor has approved the £4.3 million Highways Investment Programme for 2026/27, prioritising carriageway resurfacing over footways, subject to final budget approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedHighways Investment Programme 2026/27 works approved
Money£4,300,000 capital bidSubject to final budget approval
What happens nextFinal budget confirmationFramework extension to August 2026 expected
Who it affectsAll Salford wardsCarriageway and footway schemes citywide

What was decided

Approved the proposed programmes of work for the Highways Investment Programme for 2026/27, including a £4,300,000 capital allocation split between carriageway and footway works. Report P7, 1.4

Of the total, £3,550,000 is allocated to carriageway resurfacing and reconstruction, and £750,000 to footway refurbishment with kerb repairs. Report P24, P25, P26

The programme will proceed subject to final budget confirmation, with the scheme list to be amended if the approved settlement differs from the bid. Report 1.8

Why

To meet statutory duties as highway authority under section 41 of the Highways Act 1980 and strengthen the section 58 defence against third-party claims. Report 1.2

To arrest the managed decline in carriageway condition, which has risen in the red category as early micro-asphalt treatments reach the end of their lifecycle. Report 1.5, 1.7, P12

To reduce rising reactive repair orders and address increased customer and member complaints about deterioration. Report 1.7, 1.14

What happens next

Final budget approval for the £4.3 million capital bid is required before the scheme list is locked in. Report P1, 1.8

Engineering assessments, contractor involvement and current survey data will determine finalised scheme details, with progress reported to the Lead Member through briefing notes from July 2025. Report 1.12

Works will be delivered through the SCC Technical and Highways Works Framework, in place until February 2026 and expected to be extended to August 2026 to allow a new compliant framework to be procured. Report P2

The money

  • £4,300,000 Total capital provision for the 2026/27 Highways Investment Programme Report P7, P26, P36
  • £3,550,000 Carriageway refurbishment, surface inlay and reconstruction Report P25, P32
  • £750,000 Footway refurbishment, surface inlay and kerb repairs Report P24, P28
  • £3,073,326.98 Direct works costs for carriageway reconstruction, inlay and treatments Report P33
  • £476,673.02 Depot overheads (15.51%) for carriageway works Report P34
  • £649,294.43 Direct works costs for footway refurbishment Report P29
  • £100,705.57 Depot overheads (15.51%) for footway works Report P30

Options considered

  • Rejected: No alternative options considered. The decision record states options considered and rejected were: None

Implications

  • Legal: Works delivered under Highways Act 1980, Road Traffic Regulation Act 1984, and SCC Standing Orders; programme supports section 58 statutory defence.
  • Equalities: Positive impact expected for elderly, mobility-impaired and visually impaired people through tactile paving and dropped kerbs at junctions. Report P55, 1.17
  • Financial: Programme assumes full approval of the £4.3 million capital bid; any change in settlement will require the programme to be revised. Report P1, 1.8
  • Risk: Risk assessed as low; targeted allocation supports statutory obligations and continuous improvement of the network. Report P56
  • Other: Climate change implications: none identified. Report P57, P58

Who and where

  • All Salford wards, with specific schemes in Barton and Winton, Boothstown and Ellenbrook, Broughton, Cadishead and Lower Irlam, Claremont, Eccles, Kersal, Ordsall, Pendlebury, Swinton, Walkden, Worsley and Westwood Park Report P64

Timeline

  • 2026/27: Financial year in which the approved programme will be delivered Report P7, 1.4
  • July 2025 onwards: Briefing notes to the Lead Member for Transport, Planning and Sustainable Development, ward councillors, neighbourhood managers and community Report 1.12
  • February 2026: Current SCC Technical and Highways Works Framework expires Report P2
  • August 2026: Expected extension of the existing framework while a new compliant framework is procured Report P2

Plain English for the jargon

  • Highway Investment Programme: Salford's ongoing capital programme, introduced under the 2009/10 Network Recovery Plan, to maintain and improve the road and footway network.
  • Carriageway Condition Index: Classification of road sections as red, amber or green based on condition survey data.
  • Footway Condition Index: Classification of footway sections as red, amber, yellow or green based on condition survey data.
  • Surface inlay: A resurfacing treatment that removes and replaces the upper road or footway layer.
  • Tactile paving: Textured paving surfaces at junctions and crossings to assist visually impaired pedestrians.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4a

Resolved

Salford City Council - Record of Decision I Councillor Jack Youd, Deputy City Mayor and Lead Member for Finance, Support Services and Regeneration in exercise of the powers contained within the City Council Constitution do hereby approve the proposed programmes of work for the Highway Investment Programme for 2026/2027 The Reasons are to facilitate continuous improvement of the highway infrastructure. Approval is granted for the proposed programmes of work for the Highways Investment Programme for 2026/27, as outlined in the report. The programme will proceed subject to final budget confirmation. Options considered and rejected were: None Assessment of Risk: Low – The targeted allocation of £4.3 million will ensure the City Council meets its statutory obligations under the Highways Act 1980 while facilitating continuous improvement of the highway network. The programme prioritises resurfacing and reconstruction of critical carriageway and footway sections, reducing long-term costs and improving public safety. Source of Funding: The programme is based on a capital funding bid of £4.3 million for 2026/27. This allocation is subject to final approval. Should the confirmed funding differ from the bid amount, the programme will be amended accordingly to align with the approved budget. Legal Advice Obtained: Under section 41 of the Highways Act 1980, the Council, as highway authority, is under a duty to maintain highways at public expense. Section 58 provides a statutory defence where the authority can demonstrate a reasonable regime of inspection and maintenance. The proposed programme strengthens the Council’s position in defending third-party claims and supports compliance with statutory obligations. Works will be delivered in accordance with relevant legislation, including the Road Traffic Regulation Act 1984 where Traffic Regulation Orders are required. Procurement will comply with SCC Standing Orders, Financial Regulations, and public procurement legislation. Procurement Advice Obtained: Works will be delivered through the SCC Technical and Highways Works Framework, which is in place until February 2026 and expected to be extended to August 2026. This ensures compliance with SCC Standing Orders and the Procurement Act 2023. Alternative frameworks or standalone procurement routes may be considered where appropriate. Procurement Advice obtained: Heather Stanton, Procurement Category Manager Financial Advice Obtained: The programme assumes full approval of the £4.3 million capital bid for 2026/27. If the confirmed allocation differs, the programme will be revised to reflect the approved funding level. Financial Advice obtained: Ian Cowburn, Senior Accountant Equality Impact Assessment: The programme will have a positive impact on all equality groups by improving accessibility and safety for pedestrians, including the elderly and those with mobility impairments. Works will include tactile paving and dropped kerbs at junctions. Climate Change Implications: None identified. HR Advice obtained: N/A ______________________________________________________________ Climate Change Advice obtained: N/A Wards to Which Report Relates: All. Contact Officer: Lewis Barnett, Group Engineer Highway Asset Management Telephone number: [phone removed] - This decision is subject to consideration for briefing purposes by the Lead Member for Planning, Transport and Sustainable Development. The Lead Member is supportive of the decision. - This decision is not subject to approval by another Lead ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Financial implications

Ian Ian Cowburn, Senior Accountant, Finance Division Date : 25/11/2025 Comments : This a request for the Lead Member for Planning and Sustainable Development to approve the proposed Highways Investment Programme for 2026/27. The Programme has been prepared on the basis that the 2026/27Capital funding bid of £4.3M submitted for the Programme will be approved in full. If the amount of funding approved for 2026/27 differs from the bid amount, the Programme for 2026/27 will require amendment to bring it into line with the amount of the approved funding. ________________________________________

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Investment Programme 2026/27Report 255 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 14 attended
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, present
PC
Philip CusackInvitee, in attendance
PD
Paul DennettCommittee Member, apologies
TK
Tracy KellyCommittee Member, apologies
BK
Brendan KevilleCommittee Member, in attendance
MM
Mike McCuskerCommittee Member, present
JM
John Merry CBECommittee Member, absent
WN
Wilson NkurunzizaInvitee, in attendance
TP
Teresa PepperCommittee Member, apologies
MR
Mike RelphSecretary, expected
GR
Gina ReynoldsInvitee, in attendance

All 14 on the meeting page

On this subject at Salford

Search all
  1. Highways Investment Programme 2026/27This decision
  2. Highways Investment Programme 2025/26Approved
  3. Highways Investment Programme 2023/24Approved
  4. Highways Investment Programme 2021/22Approved
  5. Highways Investment Programme 2020/21Approved
  6. Highways Investment Programme 2019/20Approved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open
24 Aug 2026 Two New BaileySalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies