Highways Investment Programme 2025/26

Approved Committee 1 paper

Property / Regeneration Briefing approved this item on Monday 28 April 2025. Below is the council's own wording, with the papers it was decided on.

Item3a

Resolved

Salford City Council – Record of Decision I Councillor Jack Youd , Deputy City Mayor and Lead Member for Finance, Support Services and Regeneration , in exercise of the powers contained within the City Council Constitution and following consultation with Cabinet Members at the Property/ Regeneration Briefing, do hereby approve the proposed programmes of work for the Highways Investment Programme (HIP) for 2025/26. The Reasons are : · Highways play an essential role in making travel more expedient, be that by car, public transport, cycling or walking. · Highways provide connectivity between conurbations both locally and strategically. Well maintained highways ensure the network is kept open, minimises delays and promotes economic growth in the local areas which they serve along with job opportunities. · By adequately maintaining our highway infrastructure, this will enhance and preserve the benefits derived from a good, sound highway infrastructure. It is crucial therefore that highways are enhanced and maintained. Planned, preventative maintenance is far more economic than reactive maintenance. Options considered and rejected were: None Assessment of Risk : Low - The targeted spend of available funding will ensure that the City Council’s statutory obligations are met while at the same time facilitating continuous improvement of the highway infrastructure. The source of funding is : Highways Capital Investment 2025/26 set at £3,800,000 Legal Advice obtained : Helen Chapman, Principal Solicitor Section 41 of the Highways Act 1980 places the Highway Authority under a duty to maintain a highway, and maintenance is therefore a statutory requirement. The proposals individual schemes for highway maintenance, once finalised will strengthen the Council’s position in defending 3 rd party highway/tripping claims. Whilst it is legally accepted that it is not possible to maintain the highway completely free of all defects, section 58 of the Highways Act 1980 provides a possible defence to a claim if it can adequately show that there was a sufficiently robust regime in place to inspect and maintain the highway provided it is adequately carried out and the Council had no prior knowledge of the defect before an alleged incident. Once works have been carried out in accordance with the schemes referred to the Council will be better placed to either repudiate more third party claims entirely or reduce the level of damages payable should settlement be deemed appropriate. Any works to be undertaken as part of the HIP referred to in the body of the report should be procured in accordance with the Council’s Contractual Standing Orders and the Public Contract Regulations 2015, and the Council should use a framework to appoint contractors where a suitable one is available, such as its own Technical and Highways Works Framework and each appointment should have its own approval by way of DDN. Should the value of any such works exceed £150,000, a separate report will need to be presented to Procurement Board for decision. Financial Advice obtained: Adam Flaherty, Senior Accountant, Finance Division There is sufficient funding within the 2025/26 Highways Capital Investment programme, to fund the £3,800,000 works identified ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Helen Chapman, Principal Solicitor 11th March 2025 Section 41 of the Highways Act 1980 places the Highway Authority under a duty to maintain a highway, and maintenance is therefore a statutory requirement. The proposals in the report for highway maintenance, once finalised scheme details within each of the specified categories of work have been submitted, will strengthen the Council’s position in defending 3rd party highway/tripping claims. Whilst it is legally accepted that it is not possible to maintain the highway completely free of all defects, section 58 of the Highways Act 1980 provides a possible defence to a claim if it can adequately show that there was a sufficiently robust regime in place to inspect and maintain the highway provided it is adequately carried out and the Council had no prior knowledge of the defect before an alleged incident. Once works have been carried out in accordance with the schemes referred to the Council will be better placed to either repudiate more third party claims entirely or reduce the level of damages payable should settlement be deemed appropriate. Any works to be undertaken as part of the HIP referred to in the body of the report should be procured in accordance with the Council’s Contractual Standing Orders and the Public Contract Regulations 2015, and the Council should use a framework to appoint contractors where a suitable one is available, such as its own Technical and Highways Works Framework and each appointment should have its own approval by way of DDN. Should the value of any such works exceed £150,000, a separate report will need to be presented to Procurement Board for decision. ________________________________________

Financial implications

Adam Flaherty, Senior Accountant, Finance Division 12th March 2025 There is sufficient funding within the 2025/26 Highways Capital Investment programme, to fund the £3,800,000 works identified for the Highway Improvement Programme. All expenditure should be closely monitored to ensure that these schemes are delivered within the allocated resources. ________________________________________

PROCUREMENT IMPLICATIONS:

Heather Stanton, Category Manager Tel: 6241 7th March 2025 This is a statutory requirement. The Technical and Highways Works Framework will be used to complete the works required. This will ensure that all works carried out are compliant with SCC Standing Orders and PCR’s 2015. Any efficiencies and savings opportunities need to be considered as part of this procurement activity. ________________________________________

HR IMPLICATIONS: Not applicable to this report ________________________________________

BACKGROUND DOCUMENTS: Appendix A – List of provisional carriageway and footway schemes 2025/26. ________________________________________

KEY DECISION: YES ________________________________________

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Investment Programme 2025/26Report 190 KB DownloadRead as text

At this meeting

Whole meeting
3aHighways Investment Programme 2025/26This decision

Who was there

5 of 13 attended
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, apologies
PC
Philip CusackInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
CH
Chris HowlSecretary, present
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, apologies
JM
John Merry CBECommittee Member, apologies
TP
Teresa PepperCommittee Member, present
MR
Mike RelphSecretary, apologies
GR
Gina ReynoldsInvitee, in attendance
HR
Hannah Robinson-SmithCommittee Member, apologies

All 13 on the meeting page

On this subject at Salford

Search all
  1. Highways Investment Programme 2025/26This decision
  2. Highways Investment Programme 2026/27Approved
  3. Highways Investment Programme 2023/24Approved
  4. Highways Investment Programme 2021/22Approved
  5. Highways Investment Programme 2020/21Approved
  6. Highways Investment Programme 2019/20Approved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open
24 Aug 2026 Two New BaileySalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies