Salford City Council - Record of Decision I, Councillor Tracy Kelly, Deputy City Mayor, in exercise of the powers contained within the City Council constitution do hereby the proposed programmes of work for the Highways Investment Programme (HIP) for 2023/24. The Reasons are the financial provision for the Highway Investment Programme funding for 2023/24 has been set at £3,700,000, the budget apportionments outlined in the accompanying report, outline the 2023/24 scheme proposals as part of the ongoing Highway Investment Programme and which the above approval now allows to proceed. Assessment of Risk : Low The source of funding is : n/a Legal Advice Obtaine d: Yes - Helen Chapman, Shared Legal Service Financial Advice obtained : Yes - Adan Flaherty, Senior Accountant Procurement Advice obtained: Heather Stanton, Category Manager HR Advice obtained: n/a Climate Change Advice obtained: Mike Hemingway, Principal Officer Climate Change and Will Horsfall, Team Leader Environment Policy The following documents have been used to assist the decision process. Report submitted to Property/Regeneration Briefing on 22 May 2023 Contact Officer: Steve Mangan, Group Engineer, Highway Asset Management Tel No 0161 603 4034 This decision is not subject to consideration by another Lead Member /Strategic Director The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: Councillor Tracy Kelly Deputy City Mayor Date : 22 May 2023 * This decision was published on Monday 22 May 2023 . * This decision will come in force at 4.00 pm on Tuesday 30 May 2023 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting.Source: sccdemocracy.salford.gov.uk
That the Deputy City Mayor approves the proposed programmes of work for the Highways Investment Programme (HIP) for 2023/24, as outlined in the report.
EXECUTIVE SUMMARY: The financial provision for the Highway Investment Programme funding for 2023/24 has been set at £3,700,000. The budget apportionments outlined in the report, and detailed within the background document, outline the 2023/24 scheme proposals as part of the ongoing Highway Investment Programme.
BACKGROUND DOCUMENTS:
Appendix A -Highway Investment Programme- List of Provisional Footway Schemes 2023/24 and beyond
Appendix B- Highway Investment Programme-List of Provisional Carriageway Schemes 2023/24 and beyond
KEY DECISION: Yes-this report will be presented to the City Mayor for briefing and approval
1 DETAILS: 1. The Highway Investment Programme
1.1The Capital allocation for the Highway Investment Programme during 2023/24 has been specified as £3,700,000. 1.2 Salford City Council implemented a Network Recovery Plan (delivered through the Highway Investment Programme) in 2009/10. This was implemented to arrest the deterioration of the highway network initially and to enable the Council to tackle the critical sections of highway thereafter. 1.3 Since the start of the current Highway Investment Programme in 2010, the following condition indices for both footway and carriageway have been achieved.Targets are the aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment and these are therefore currently affected by the investment levels provided which has been less than the investment requested. Tables 1 and 2 below provide the overall condition indices for the carriageways (Table 1) and footways (Table2). The indices provided are based on the current investment levels provided.
Table 1 – Carriageway Condition Index Summary % of classification within each category
(The Highway Improvement Programme commenced in 2009/10) *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment and these are therefore currently affected by the investment levels provided which is less than the investment requested
red 2 1.4 2 2 3.4 4 4 5 2.2 2.3 amber 19.6 14.2 16 17 17.9 18 17 16 6.1 6.2 yellow 57 50.4 61 60 43 43 41 32 15.8 16.6 green 21.4 34 21 21 35.7 35 38 47 75.9 74.9 (The Highway Improvement Programme commenced in 2009/10) *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment and these are therefore currently affected by the investment levels provide d. £1.2m provides investment so that the overall footway condition remains at a steady state.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.