Salford City Council
Procurement Board, Monday 27 July 2026 at 2.00pm

Approval for an Exception to Contractual Standing Orders to award a contract for the reception reconfiguration at Two New Bailey (Janine Olarte)

Approved Committee 1 paper

AI summarySalford City Council's Lead Member for Finance and Support Services approves an exception to Contractual Standing Orders to award a £268,731 reception reconfiguration contract at Two New Bailey to ADT Workplace.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDirect award to ADT Workplace for Two New Bailey reception reconfiguration
Money£268,731.00Funded from Capital Programme via New Bailey reserves, no extra funding needed
What happens nextContract starts 03/08/2026Ends 28/09/2026, two months duration
Who it affectsOrdsall ward, Two New Bailey buildingPlace Directorate, reception area fit out

What was decided

An exception to Contractual Standing Orders is approved to directly award a reception reconfiguration contract at Two New Bailey to ADT Workplace without competitive tendering. Report P1, P7

The exception is granted on the ground that the direct award delivers best value to the Council, as ADT Workplace has proven experience on similar projects and familiarity with the Council's standards. Report 1.0, 1.1, P14, P5

Why

ADT Workplace previously carried out fit out works on 100 Embankment, another Grade A office in the Council's portfolio, and won industry awards including the Architizer A+ Award for Best Remote Work and Co-Working Space for 2024. Report 1.1

ADT Workplace has already completed the design for the scheme, so an alternative contractor would need to redesign the project or deliver a design they did not produce, risking quality and incurring further costs. Report 1.7

The project is important for letting the remaining vacant floors at Two New Bailey, making consistent quality a critical requirement. Report 1.7

What happens next

The contract is to be instructed as soon as possible, with the programme of works expected to be delivered in seven weeks, monitored through regular site meetings and progress reports led by the Council's project manager. Report 1.5, 1.6

The Council will publish a Contracts Details Notice in line with Procurement Act 2023 requirements, and lessons from this project will feed into forward planning to reduce future CSO exceptions. Report P42, 1.9

ADT Workplace must evidence alignment with the Council's Social Value Framework through proportionate reporting. Report 1.3, 1.4

The money

  • £ 268,731.00 Contract value, funded from the Council's approved Capital Programme using revenue reserves already allocated for New Bailey reserves Report P3, P4, P35

Options considered

  • Chosen: Award the contract directly to ADT Workplace as an exception to CSOs on best value grounds. Proven track record, design already completed, continuity reduces risk, avoids extra redesign costs Report 1.0, 1.1, 1.7, P5
  • Rejected: Run a competitive tender via The Chest e-tendering platform as normally required for contracts above £150,000. Would risk compromising quality, duplicate design work, delay letting of vacant floors, and increase costs Report 1.7, P29, P41

Implications

  • Financial: One-off cost of £268,731.00 met from existing approved Capital Programme budgets with no need for additional funding; financial risk assessed as low. Report P35, P36
  • Legal: Contract value is below the Procurement Act 2023 threshold for works contracts, so a sealed tender is not legally required; risk of challenge from a third party is considered low. Report P29, P31
  • Equalities: Two New Bailey is a CAT A building and is fully compliant with building equality standards. Report P25
  • Risk: Overall risk assessed as low; the direct award avoids cost increases, delays, and redesign risks associated with bringing in a new contractor. Report P26, P36, P37
  • Other: Procurement implications: subject to approval, a Contracts Details Notice must be published in line with PA23 requirements; the contractor is an SME and an Accredited Living Wage Employer. Report P42, P3, P6

Who and where

  • Place Directorate and Ordsall ward residents and users of Two New Bailey Report P3, P50
  • ADT Workplace as the appointed contractor Report P3
  • Council's Building and Facilities Management team, with technical oversight by the Head of Building and Facilities Management Report 1.7

Timeline

  • 19th May 2026: Financial implications supplied by Senior Accountant Report P34
  • 3rd June 2026: Procurement implications supplied by Corporate Procurement Team Report P40
  • 2026-07-27: Procurement Board decision date
  • 03/08/2026: Contract start date Report P5
  • 28/09/2026: Contract end date after two months Report P5

Plain English for the jargon

  • CSO: Contractual Standing Orders, the Council's internal rules for procuring works, goods and services.
  • CAT A: A category of office fit-out providing a basic, finished shell ready for a tenant's specific fit-out; CAT A buildings meet standard compliance requirements.
  • PA23: Procurement Act 2023, the UK legislation governing how public bodies award contracts above set thresholds.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6g

Resolved

Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Finance and Support Services and Chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve an exception to the Contractual Standing Orders to approve the award of a contract for the reception reconfiguration at Two New Bailey Square, as detailed in the table below Detail required Answers Title/Description of Contracted Service/Supply/Project Reception Reconfiguration at Two New Bailey Procurement Reference Number (DN and CR, supplied by Procurement) S2028 Name of Successful Contractor ADT Workplace Supplier Registration Number (to be supplied by Procurement) 05177834 Proclass Classification No. (to be completed by procurement) 210000 Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) SME Contract Value (£) £ 268,731.00 Total Contract Value including extensions (£) £ 268,731.00 Contract Duration 2 months Contract Start Date 03/08/2026 Contract End Date 28/09/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Choose an item. Contact Officer (Name & number) Janine Olarte & 078606994023 Lead Service Group Place Reason for CSO Exception: The goods / services / works are only obtainable from one provider and there is no other provider available to allow genuine competition Tick if it applies ? Reason for CSO Exception: The execution of works or the supply of goods or services is controlled by a statutory body Tick if it applies ? Reason for CSO Exception: Delivers Best Value to the Council Tick if it applies ? Reason for CSO Exception: Special education, health or social care contracts, if it is considered in the Council’s best interests and to meet the Council’s obligations under relevant legislation Tick if it applies ? Reason for CSO Exception: The execution of works or the supply of goods and services is required so urgently as not to permit compliance with the requirements of competition Tick if it applies ? Reason for CSO Exception: Security works where the publication of documents or details in the tendering process could prejudice the security of SCC and Salford residents Tick if it applies ? Reason for CSO Exception: Procurements made through, or on behalf of, any consortium, local authority, statutory or similar body, provided that tenders or quotations are invited and contracts placed in accordance with national or EU legislation. Tick if it applies ? Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter No EC: Committed to sign up to the Mayor’s Employment Charter Choose an item. EC: Committed to the principles outlined in the Mayor’s Employment charter Choose an item. EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living Wage Employer N/A The Reasons are : ADT successfully carried out fit out works on 100 Embankment: Another grade A office building within the Council’s portfolio to which they received significant recognition in the industry for their fit out works on the first and second floor, including numerous awards ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That the Procurement Board recommends Councillor Philip Cusack, the Lead Member for Corporate Services, approves an exception to Contractual Standing Orders as permitted within the City Council Constitution for the reason(s) highlighted in the table below and the award of the Contract for reception reconfiguration at Two New Bailey as detailed in the table below:

Detail required Answers Title/Description of Contracted Service/Supply/Project Reception Reconfiguration at Two New Bailey

Procurement Reference Number (DN S2028 and CR, supplied by Procurement) Name of Successful Contractor ADT Workplace Supplier Registration Number 05177834 (to be supplied by Procurement) Proclass Classification No. (to be completed by procurement) 210000

Type of organisation Private Limited Company (to be supplied by Procurement) Status of Organisation SME (to be supplied by Procurement) Contract Value (£) £ 268,731.00 Total Contract Value including £ 268,731.00 extensions (£) Contract Duration 2 months

Sample C – Exception to CSO’S Detail required Answers Contract Start Date 03/08/2026 Contract End Date 28/09/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Choose an item. Period? Contact Officer (Name & number) Janine Olarte & 078606994023 Lead Service Group Place Reason for CSO Exception: The Tick if it applies ☐ goods / services / works are only obtainable from one provider and there is no other provider available to allow genuine competition Reason for CSO Exception: The Tick if it applies ☐ execution of works or the supply of goods or services is controlled by a statutory body Reason for CSO Exception: Delivers Tick if it applies ☒ Best Value to the Council Reason for CSO Exception: Special Tick if it applies ☐ education, health or social care contracts, if it is considered in the Council’s best interests and to meet the Council’s obligations under relevant legislation Reason for CSO Exception: The Tick if it applies ☐ execution of works or the supply of goods and services is required so urgently as not to permit compliance with the requirements of competition Reason for CSO Exception: Security Tick if it applies ☐ works where the publication of documents or details in the tendering process could prejudice the security of SCC and Salford residents Reason for CSO Exception: Tick if it applies ☐ Procurements made through, or on behalf of, any consortium, local authority, statutory or similar body, provided that tenders or quotations are invited and contracts placed in accordance with national or EU legislation.

Sample C – Exception to CSO’S Detail required Answers Funding Source Capital Programme Ethical Contractor (EC): Mayor’s No Employment Charter EC: Committed to sign up to the Choose an item. Mayor’s Employment Charter EC: Committed to the principles Choose an item. outlined in the Mayor’s Employment charter EC: Accredited Living Wage Yes Employer EC: Committed to becoming N/A Accredited Living Wage Employer

Executive summary

The purpose of this report is to request an exception to Contractual Standing Orders to approve the award of a contract for the reception reconfiguration at Two New Bailey Square.

BACKGROUND DOCUMENTS:

1. Approved Part 2 Property and Regeneration Briefing Board Paper for Reception Reconfiguration at Two New Bailey

KEY DECISION: No

DETAILS:

1.0This exception is requested on the basis that the proposed direct award represents best value for the Council. ADT Workplace have been chosen as the contractor for this project due to their proven expertise and track record with similar projects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval for an Exception to Contractual Standing Orders to award a contract for the reception reconfiguration at Two New Bailey (Janine Olarte)Report 159 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, absent
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Approval for an Exception to Contractual Standing Orders to award a contract for the reception reconfiguration at Two New Bailey (Janine Olarte)This decision
  2. Approval for an Exception to Contractual Standing Orders to award an extension of the Technical and Highways Works Framework Agreement (Steve Hands/ Sharon Walls)Approved
  3. Approval for an exception to Contractual Standing Orders to direct award contracts to Northern Care Alliance (NCA) to support delivery of the Experts at Hand offer as part of the SEND Reforms (Cathy Starbuck/ Emma Finnie)Approved
  4. Approval for an Exception to Contractual Standing Orders to award a contract for the Supply and Maintenance of Cameras to facilitate Enforcement of Moving Traffic Offences under Part 6 of the Traffic Management Act 2004 - associated with the GM Clean Air Plan (Rob Owen)Approved
  5. Approval for an Exception to Contractual Standing Orders to award a contract for the purchase of one electric refuse collection vehicle (Alan Fitzsimons)Approved
  6. Approval for an Exception to Contractual Standing Orders to award a contract for water quality monitoring at Salford Quays (Tracy Squirrel)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open