That (1) the lowest tender submitted by ROK Build Ltd. of Rochdale in the sum of £2,236,039 in respect of the building refurbishment contract for the be accepted; (2) the outcome of the due diligence exercise carried out on the Business Plan be noted; (3) the reduced overall scheme cost from £3.222m to £3.032m with the consequent reduction in capital financing costs be noted; (4) the improved viability of the project owing to the increased letting space to generate additional income contained within the revised Business Plan be noted; and (5) it be noted that the proposal was a Key Decision but, unfortunately, had not been included in the Council’s Forward Plan of Key Decisions. Consequently, the Chair of the Overview and Scrutiny Committee (Performance and Corporate Services) had been consulted under Rule 15 of the Access to Information Procedure Rules of the Constitution, to the decision being made by the Cabinet as a matter of urgency on the basis that it was impracticable to defer the decision until the commencement of the next Forward Plan because the tender is only valid for the duration of the current Forward Plan.
Word for word from the decision Sefton published for this meeting.Source: modgov.sefton.gov.uk
5th Aug 2010 DATE: Southport Indoor Market SUBJECT:
WARDS Dukes AFFECTED:
REPORT OF: Bill Millburn, Strategic Director (Communities)
Tony Corfield, Asst Dir, Leisure & Tourism (2315) CONTACT Andy Dunsmore, Technical Services (2766) OFFICER:
EXEMPT/ No CONFIDENTIAL:
PURPOSE/SUMMARY:
To update Cabinet on progress with the development of the refurbishment proposals for Southport Market and associated Business Plan and to seek Members direction with regard to the award of the Building Contract
REASON WHY DECISION REQUIRED: Cabinet have previously resolved that the Market Hall should remain on its existing site and be refurbished to ensure its ongoing viability. On 17 December 2009 Cabinet resolved that approval be given to the further development of the Indoor Market Refurbishment Scheme to enable Officers to invite tenders for the scheme, and that the project be phased to enable traders to continue trading during the period of the refurbishment works. On 15 April Cabinet approved a list of Contractors and requested Officers to invite tenders Cabinet is now requested to provide direction with regard to the award of the Contract to the successful tenderer.
RECOMMENDATION(S): Cabinet is recommended to:
a) Approve the award of the tender for the Construction Contract to the tenderer having submitted the lowest price b) Note the outcome of the due diligence exercise carried out on the Business Plan. c) Note the reduced overall scheme cost from £3.222m to £3.032m with the consequent reduction in capital financing costs. d) Note the improved viability of the project owing to the increased letting space to generate additional income contained within the revised Business Plan. e) Approve the scope of the proposed Public Realm Improvements, subject to approval from Southport Area Committee to the associated Traffic Regulation Orders.
KEY DECISION: Yes A Rule 15 Form has been submitted to the Chair of the Overview and Scrutiny Committee FORWARD PLAN: (Performance and Corporate Services)
Immediately following the call in period for the IMPLEMENTATION DATE: Minutes of the Cabinet Meeting
ALTERNATIVE OPTIONS: Cabinet have previously decided that the Market should be refurbished on its existing site and subsequently chose a preferred option. The prime alternative options from this point therefore relate to the timeline and manner in which funding and operational support is incorporated into the project. However, should the delivery programme not prove acceptable, other courses of action are possible up to the point of contracts for construction being awarded.
IMPLICATIONS: Financial resources were provided in the Medium Budget/Policy Framework: Term Financial Plan for this proposal as part of the 2010/11 budget process.
Financial:
2010/ 2011/ 2012/ 2013/ 2011 2012 2013 2014 CAPITAL EXPENDITURE £’000 £’000 £’000 £’000 Gross Reduction in Capital Expenditure -190 Funded by: Sefton Capital Resources -190 Specific Capital Resources REVENUE IMPLICATIONS Gross reduction in Revenue 0 -126 -104 Expenditure Funded by: Sefton funded Resources 0 -126 -104 Funded from External Resources Does the External Funding have an When? expiry date? Y/N How will the service be funded post expiry?
Legal: N/A
Risk In June 2008 Cabinet made the decision that the Market should Assessment: continue on its existing site and that options for its refurbishment should be developed. In March 2009 Cabinet chose a preferred refurbishment option and in January 2010 gave officers permission to work up the scheme to tender stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.