Cabinet, Thursday 5 August 2010

Southport Cycle Town Work Programme 2010/11

Noted Executive 1 paper

Cabinet noted this item on Thursday 5 August 2010. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

That (1) the Cycle Town Work Programme be included in the Capital Programme for 2010/11; and (2) it be noted that the revenue implications within the report would be funded from the Cycling England / Department for Transport Grant.
Word for word from the decision Sefton published for this meeting. Source: modgov.sefton.gov.uk

Follow this further

Built from Sefton's papers

What the report saysPro

Report to Cabinet, 5 pages

REPORT TO: Cabinet th DATE: 5 August 2010

SUBJECT: Southport Cycle Town Work Programme 2010/11

WARDS AFFECTED: Dukes, Kew, Birkdale, Cambridge, Meols, Ainsdale, Norwood

REPORT OF: W Millburn Strategic Director - Communities

CONTACT OFFICER: Dave Marrin, Traffic Services Manager 0151 934 4295

EXEMPT/ No CONFIDENTIAL:

PURPOSE/SUMMARY:

To seek entry of the Cycle Town Work Programme into the 2010/11 Capital Programme.

REASON WHY DECISION REQUIRED:

To approve the Cycle Town Work Programme which will facilitate delivery of projects in 2010/11

RECOMMENDATION(S):

It is recommended that Cabinet:

i) Approve the Cycle Town Work programme as part of the Capital programme for 2010/11: ii) Note that the revenue implications within the report are funded from the Cycling England / Department for Transport Grant.

KEY DECISION: Yes

FORWARD PLAN: Yes

IMPLEMENTATION DATE: Following the expiry of the ‘call in’ period for the minutes of the meeting ALTERNATIVE OPTIONS:

None

IMPLICATIONS:

Budget/Policy Framework: The project will be funded through Department for Transport Grants, Local Transport Plan and revenue resources.

Financial:

2010/ 2011/ 2012/2 2013/ 2011 2012 013 2014 CAPITAL EXPENDITURE £ £ £ £ Gross Increase in Capital Expenditure 560,000

Funded by:

Sefton Capital Resources

Specific Capital Resources 560,000

REVENUE IMPLICATIONS Gross Increase in Revenue Expenditure 280,000

Funded by:

Sefton funded Resources

Funded from External Resources 280,000

Does the External Funding have an expiry date? Y 31.3.11 How will the service be funded post expiry?

Legal: N/A Risk Assessment: N/A Asset Management: N/A CONSULTATION UNDERTAKEN/VIEWS – FD445 THE INTERIM HEAD OF FINANCE & INFORMATION SERVICES HAS BEEN CONSULTED AND HIS COMMENTS HAVE BEEN INCORPORATED INTO THE REPORT. CORPORATE OBJECTIVE MONITORING:

Corporate Positive Neutral Negative Objective Impact Impact Impact 1 Creating a Learning Community ✔ 2 Creating Safe Communities ✔ 3 Jobs and Prosperity ✔ 4 Improving Health and Well-Being ✔ 5 Environmental Sustainability ✔ 6 Creating Inclusive Communities ✔ 7 Improving the Quality of Council Services and ✔ Strengthening local Democracy 8 Children and Young People ✔

LIST OF BACKGROUND PAPERS RELIED UPON IN THE PREPARATION OF THIS REPORT

None Southport Cycle Town – Working Programme 2009/10

1.0Introduction

1.1A report was submitted to the Cabinet Member – Technical Services at his meeting of th the 8 October 2008 which outlined the whole of the Cycle Town Project to be delivered over three years between April 2008 and March 2011.

1.2The report further indicated that the grant of £1.8m of revenue and capital funding from the Department for Transport through the delivery agency Cycling England was subject to an annual work programme being agreed with Cycling England. The funding was to be split £300k in 2008/9, £750k in 2009/10 and £750k in 2010/11.

The work programme for 2010/11 has been submitted to Cycling England and has now been approved. This report seeks the inclusion of the Work programme in the Capital programme for 2010/11.

2.0Details of the Work Programme 2009/10

2.1The work programme for 2010/11 is detailed in 2.2 below. This has been over - programmed by £150k with a scheme to upgrade the Transpennine Trail between Selworthy Road and Weld Road, which will be developed to feasibility stage initially, in case of problems delivering other elements of the programme. The total expenditure on the programme for 2010/11 will not exceed the £560,000 allocation. 2.2 Work Programme – Cycling England Contributions

Capital £’000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southport Cycle Town Work Programme 2010/11Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Sefton

Search all
  1. Southport Cycle Town Work Programme 2010/11This decision
  2. Southport Cycle Town - East West LinkNoted
  3. Southport Cycle Town Portland Street Cycling Improvements - Acceptance Of TenderApproved
  4. Southport Cycle Town - Proposed Cycle Track - Birkdale To AinsdaleDecided
  5. Southport Cycle Town - East West LinkNoted
  6. Southport Cycle Town - Proposed Cycle Track - Birkdale To AinsdaleNoted

More from Sefton Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Previous MeetingDecision Made: That the Minutes of the meeting held on 23 July 2026 be confirmed as a correct record. Decided Open
3 Sep 2026 Review of Adult Social Care Charging PolicyThe recommendations in the report had been developed following a review of Adult Social Care charging arrangements, e... Approved Open
3 Sep 2026 Approval of Legal Documentation for Academy Conversions – Voluntary ConversionsThe Archdiocese of Liverpool had determined that all Catholic schools in Sefton would become part of the Pope Francis... Agreed Open
3 Sep 2026 Procurement of Supported Lodgings Accommodation for Young People Aged 16+The proposed procurement would secure a compliant, regulated and more financially sustainable Supported Lodgings arra... Refused Open
3 Sep 2026 Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a... Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies