Resolved
That the contents of the report be noted.
Audit Committee noted this item on Thursday 25 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
The Audit Plan for Shropshire County Pension Fund
Year ended 31 March 2015 25 February 2015
John Gregory Engagement Lead T [phone removed] E [email removed]
Ashley Wilson Audit Manager T [phone removed] E [email removed]
Kieran Armitage Executive T 0121 232 5422 E [email removed]
© 2015 Grant Thornton UK LLP | The contents of this report relate only to the matters which have come to our attention, which we believe need to be reported to you as part of our audit process. It is not a comprehensive record of all the relevant matters, which may be subject to change, and in particular we cannot be held responsible to you for reporting all of the risks which may affect the Council or any weaknesses in your internal controls. This report has been prepared solely for your benefit and should not be quoted in whole or in part without our prior written consent. We do not accept any responsibility for any loss occasioned to any third party acting, or refraining from acting on the basis of the content of this report, as this report was not prepared for, nor intended for, any other purpose. Contents Section
1. Understanding your business 2. Developments relevant to your business and the audit 3. Our audit approach 4. Significant risks identified 5. Other risks 6. Results of interim work 7. Key dates 8. Fees and independence 9. Communication of audit matters with those charged with governance
© 2015 Grant Thornton UK LLP | Understanding your business In planning our audit we need to understand the challenges and opportunities the Pension Fund is facing. We set out a summary of our understanding below.
Challenges/opportunities 1. New governance arrangements 2. Pensions Regulator 3. Future structural reform 4. Local government outsourcing • The new governance regulations have • The Public Services Pension Act also • In May 2014 DCLG consulted on the • As many councils look to outsourcing and introduced further changes for LGPS which provides for the extension of the work of opportunities for collaboration, cost savings the set up of external organisations as a take effect from April 2015. These The Pensions Regulator to the LGPS from and efficiencies in the management of more cost effective way to provide services, introduce a Local Pension Board for each 1 April 2015. LGPS funds. While the outcome of this is the impact on the LGPS fund needs to be fund. These boards will work with the • The Fund will need to monitor compliance still awaited there is clearly a growing considered. administering authority to help ensure with requirements set by the regulator. momentum for structural change. • Funds need to carefully consider requests compliance and effective governance and • In the meantime the growing use of shared for admission to the scheme and where administration of the scheme. In addition arrangements is delivering real benefits to possible mitigate any risks to the fund. the regulations also establish a National funds through reduced costs, increasing Scheme Advisory Board and a funding cap. • An increased number of admitted bodies access to relevant expertise and improved may increase the risks for the fund in the • There is a potential for overlap for many quality. event of those bodies failing. It is also likely schemes between existing Pension to increase the administration costs of the Committees and the new Local Pension scheme overall. Boards, with a real challenge for administering authorities to meet the statutory requirements, but in a way which delivers visible improvements in the governance of the funds.
Our response
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit: Pension fund audit plan 2014/15Report | 231 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.