Resolved
Resolved – That the financial allocation for 2.05 Newbury Sandleford Park be increased from £2,000,000 to £2,900,000.
Berkshire Local Transport Body decided this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the financial allocation for 2.05 Newbury Sandleford Park be increased from £2,000,000 to £2,900,000.
1. To consider the case for increasing the funding allocated to scheme 2.05 Newbury Sandleford Park from £2,000,000 to £2,900,000
2. Elsewhere on this agenda is a report on the independent assessment of the Full Business Case for this scheme, which has been prepared on the basis of the higher costs and LEP contribution for this scheme.
3. You are recommended to increase the financial allocation for 2.05 Newbury Sandleford Park from £2,000,000 to £2,900,000.
Other Implications
Financial
4. There is an existing allocation of £2,000,000 for this scheme. An increase of £900,000 would mean accessing part of the unallocated capital sum and would need to be considered alongside any other requests and the potential of future requests.
5. At the start of the meeting the unallocated capital sum is £5,827,000. There are two further requests for additional funds. The three requests together total £5,150,000.
6. There are 23 named schemes in the programme:
The Wokingham Distributor Roads are funded from DfT retained funds 3 13 schemes have had full business cases approved and are either 13 complete, on site or ready to go on site 3 schemes have requested additional funds arising from design or 3 specification changes (the three on tonight’s agenda) 4 schemes have not yet submitted full business cases 4 Total 23
7. The remaining four scheme promoters are aware that the unallocated sum may be committed as a result of the current requests.
8. The risk management arrangements already put in place by the Local Transport Body are as follows:
Item 4: BLTB 21 July 2016 Request for additional funding for 2.05 Newbury Sandleford Park The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes AECOM have been appointed as Independent Assessors and have provided a full written report (see item elsewhere on this agenda) on the full business case for the scheme. White Young Green (WYG) the contracted independent assessors have a conflict of interest as they are acting as planning consultants to one of the developers, and have therefore withdrawn. The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
10. The scheme will help to deliver the Sandleford Park strategic housing site to the south of Newbury through provision of supporting infrastructure in the form of two new accesses for all modes of travel onto the A339 Newtown Road and A343 Andover Road, to the east and west of the Sandleford Park development area respectively.
11. The scheme will help to deliver a site which has the potential to significantly contribute to housing delivery, including 40% affordable units. The accesses will ensure permeability through the Sandleford Park site, better managing the impact on the highway network, improving links for sustainable modes of travel and unlocking additional development land south of Newbury College for employment and educational uses.
12. Given the size of the proposed housing development and its many infrastructure requirements, LEP funding was sought in order to accelerate access to all parts of the site and therefore ensure more efficient and timely delivery of housing. The funding will also help to ensure that the maximum number of units will be achieved on the site rather than fewer units being delivered as a result of a limited access strategy for the development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Request for additional funding for 2.05 Newbury Sandleford ParkReport | 124 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.