Request for additional funding for 2.06 Reading: Green Park Railway Station

Decided Committee 1 paper

Berkshire Local Transport Body decided this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Resolved – That the financial allocation for 2.06 Reading: Green Park Station be increased from £6,400,000 to £9,150,000.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider the case for increasing the funding allocated to scheme 2.06 Reading Green Park Station from £6,400,000 to £9,150,000.

2. The original scheme received financial approval at your meeting in November 2014.

Recommendation

3. You are recommended to increase the financial allocation for 2.06 Reading Green Park Station from £6,400,000 to £9,150,000.

Other Implications

Financial

4. There is an existing allocation of £ 6,400,000 for this scheme. An increase of £2,750,000 would mean accessing part of the unallocated capital sum and would need to be considered alongside any other requests and the potential of future requests.

5. At the start of the meeting the unallocated capital sum is £5,827,000. There are two further requests for additional funds. The three requests together total £5,150,000.

6. There are 23 named schemes in the programme:

The Wokingham Distributor Roads are funded from DfT retained funds 3 13 schemes have had full business cases approved and are either 13 complete, on site or ready to go on site 3 schemes have requested additional funds arising from design or 3 specification changes (the three on tonight’s agenda) 4 schemes have not yet submitted full business cases 4 Total 23

7. The remaining four scheme promoters are aware that the unallocated sum may be committed as a result of the current requests.

Risk management

8. The risk management arrangements already put in place by the Local Transport Body are as follows:

Item 7: BLTB 21 July 2016 Request for additional funding for 2.06 Reading: Green Park Station  The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  The original business case was assessed by White Young Green and you approved the financial contribution in 2014. The revised scheme has been reassessed for Value for Money asset out in paragraph 13 below.  The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

10. The proposal is for the construction of a new railway station and related infrastructure at Green Park, Reading. The station is to be located on the Reading to Basingstoke line, to the south of Reading West and north of Mortimer station in Hampshire. The scheme was ranked as the 2nd highest priority from the 28 transport schemes submitted to the LEP as part of the first Growth Deal round in 2014.

11. An assessment of forecast passenger demand for the station was undertaken in 2013 in partnership with Great Western Railway and Network Rail to support development of the full business case for the scheme. The concept design for the station and interchange was based on this forecast passenger demand, resulting in the requirement to design the station facilities in line with Department for Transport guidance for Category F stations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request for additional funding for 2.06 Reading: Green Park Railway StationReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
PB
Councillor Phillip BicknellCommittee Member, apologies
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, apologies, sent representative
FA
Councillor Fiza A MatloobCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilCommittee Member, present
MR
Councillor Malcolm RichardsCommittee Member, present
GS
Councillor Garth Simpson West Berkshire CouncilCommittee Member, apologies, sent representative
CE
Charles Eales Thames Valley Berkshire LEPCommittee Member, apologies
IF
Ingrid FernandesCommittee Member, present
IF
Ian Frost Thames Valley Berkshire LEPCommittee Member, apologies
PH
Peter Howe Thames Valley Berkshire LEPCommittee Member, present
GS
Graeme Steer Thames Valley Berkshire LEPCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEPCommittee Member, present

All 18 on the meeting page

On this subject at Slough

Search all
  1. Request for additional funding for 2.06 Reading: Green Park Railway StationThis decision
  2. Request for additional funding for 2.05 Newbury Sandleford ParkDecided
  3. Request for additional funding for 2.15 Bracknell: Martins Heron RoundaboutDecided

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies