Resolved
Resolved – That the financial allocation for 2.06 Reading: Green Park Station be increased from £6,400,000 to £9,150,000.
Berkshire Local Transport Body decided this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the financial allocation for 2.06 Reading: Green Park Station be increased from £6,400,000 to £9,150,000.
1. To consider the case for increasing the funding allocated to scheme 2.06 Reading Green Park Station from £6,400,000 to £9,150,000.
2. The original scheme received financial approval at your meeting in November 2014.
3. You are recommended to increase the financial allocation for 2.06 Reading Green Park Station from £6,400,000 to £9,150,000.
Other Implications
Financial
4. There is an existing allocation of £ 6,400,000 for this scheme. An increase of £2,750,000 would mean accessing part of the unallocated capital sum and would need to be considered alongside any other requests and the potential of future requests.
5. At the start of the meeting the unallocated capital sum is £5,827,000. There are two further requests for additional funds. The three requests together total £5,150,000.
6. There are 23 named schemes in the programme:
The Wokingham Distributor Roads are funded from DfT retained funds 3 13 schemes have had full business cases approved and are either 13 complete, on site or ready to go on site 3 schemes have requested additional funds arising from design or 3 specification changes (the three on tonight’s agenda) 4 schemes have not yet submitted full business cases 4 Total 23
7. The remaining four scheme promoters are aware that the unallocated sum may be committed as a result of the current requests.
8. The risk management arrangements already put in place by the Local Transport Body are as follows:
Item 7: BLTB 21 July 2016 Request for additional funding for 2.06 Reading: Green Park Station The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes The original business case was assessed by White Young Green and you approved the financial contribution in 2014. The revised scheme has been reassessed for Value for Money asset out in paragraph 13 below. The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
10. The proposal is for the construction of a new railway station and related infrastructure at Green Park, Reading. The station is to be located on the Reading to Basingstoke line, to the south of Reading West and north of Mortimer station in Hampshire. The scheme was ranked as the 2nd highest priority from the 28 transport schemes submitted to the LEP as part of the first Growth Deal round in 2014.
11. An assessment of forecast passenger demand for the station was undertaken in 2013 in partnership with Great Western Railway and Network Rail to support development of the full business case for the scheme. The concept design for the station and interchange was based on this forecast passenger demand, resulting in the requirement to design the station facilities in line with Department for Transport guidance for Category F stations.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Request for additional funding for 2.06 Reading: Green Park Railway StationReport | 120 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.