Berkshire Local Transport Body, Thursday 21 July 2016 at 4.00pm

Financial approval 2.05 Newbury Sandleford Park

Approved Committee 2 papers

Berkshire Local Transport Body approved this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Resolved – That scheme 2.05 Newbury Sandleford Park be given full financial approval in the sum of £2,900,00 over three financial years (2017/18, 2018/19, 2019/20) on the terms of the funding agreement set out at paragraph 14 step 5 of the report.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.05 Newbury Sandleford Park.

2. The proposal is to deliver additional accesses to Sandleford Park, a strategic development site that will deliver up to 2,000 dwellings. This will ensure permeability through the site and better manage the impact on the highway network. There are two main elements: i) a new access from the A339, and ii) new junction arrangements on the A343 and the upgrading of a route to provide a suitable access. The scheme will also unlock land for a new primary school and for new enterprises seeking to build better links between business and education.

3. The scheme described in the Full Business Case and referred to here is the revised scheme. The proposal has been assessed on the basis that the LEP contribution will be increased from £2million to £2.9million as recommended elsewhere on this agenda.

Recommendation

4. You are recommended to give scheme 2.05 Newbury Sandleford Park full financial approval in the sum of £2,900,000 over three financial years (2017/18, 2018/19, 2019/20) on the terms of the funding agreement set out at paragraph 14 step 5 below.

Other Implications

Financial

5. Scheme 2.05 Newbury Sandleford Park is a named scheme in the Thames Valley Berkshire Local Growth Deal 2i announced in January 2015.

6. This report recommends that West Berkshire Council be authorised to draw down the capital sum £2,900,000 from the Local Transport Body funding for this scheme.

7. The funding agreement set out at paragraph 14 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay,

Item 6 BLTB 21 July 2016 Financial Approval 2.05 Newbury Sandleford Park consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

8. The risk management arrangements already put in place by the Local Transport Body are as follows:  The Assurance Frameworkii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  AECOM have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme  White Young Green (WYG) who are the LTB’s contracted Independent Assessors withdrew from the assessment of this scheme because they are also acting as planning consultant to one of the developers. AECOM are Enterprise M3 LEP’s retained independent assessor.  The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

10. The scheme will be carried out by West Berkshire Council working with the Developer(s) of the strategic housing site.

11. In June and July 2016, AECOM reviewed the Full Business Case submission for the scheme.

12. At Appendix 1 is the final report from AECOM the Independent Assessors recommending full approval for this scheme. The detailed technical appendixes are available on request.

13. The full details of the scheme are available from the West Berkshire Council websiteiii. A summary of the key points is given below:

Task Timescale Detailed design update Summer 2016 Procurement Autumn/Winter 2016/7 Construction April 2017 Completion of Construction March 2020

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
to Item 6 BLTB 21 July 2016 Independent Assessors Report on 2.05 Newbury Sandleford ParkAppendix 1 162 KB Download
PDF
Financial approval 2.05 Newbury Sandleford ParkReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
PB
Councillor Phillip BicknellCommittee Member, apologies
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, apologies, sent representative
FA
Councillor Fiza A MatloobCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilCommittee Member, present
MR
Councillor Malcolm RichardsCommittee Member, present
GS
Councillor Garth Simpson West Berkshire CouncilCommittee Member, apologies, sent representative
CE
Charles Eales Thames Valley Berkshire LEPCommittee Member, apologies
IF
Ingrid FernandesCommittee Member, present
IF
Ian Frost Thames Valley Berkshire LEPCommittee Member, apologies
PH
Peter Howe Thames Valley Berkshire LEPCommittee Member, present
GS
Graeme Steer Thames Valley Berkshire LEPCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEPCommittee Member, present

All 18 on the meeting page

On this subject at Slough

Search all
  1. Financial approval 2.05 Newbury Sandleford ParkThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies