Resolved
Resolved – That the reports from the scheme promoter and the independent assessor be noted.
Berkshire Local Transport Body noted this item on Thursday 16 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the reports from the scheme promoter and the independent assessor be noted.
1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year-on impact reports for BLTB funded local transport schemes
2. This report introduces the first of these to be completed, for scheme 2.07 Bracknell Coral Reef.
3. You are recommended to note the reports from the scheme promoter and the independent assessor.
Other Implications
Financial
4. There are no direct financial implications of this report.
5. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one and five years post implementation.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.
Supporting Information
7. Bracknell Forest Council received £2.1m towards the £3.0m cost of this scheme. Therefore, it has been treated as a “small” scheme being below the £5m threshold.
Item 7: BLTB 16 November 2017 2.07 Bracknell Coral Reef - One Year Impact Report 8. The one-year on impact report is attached at Appendix 1; the guidelines approved in March 2017 are at Appendix 2; and the independent assessor’s report is attached at Appendix 3.
Conclusion
9. There is no further action required
10. Correspondence
Item 7: BLTB 16 November 2017 2.07 Bracknell Coral Reef – One Year Impact Report Appendix 1 Coral Reef Signalised Junction 12 Month Evaluation Report
Appendix 1 Item 7: BLTB 16 November 2017 2.07 Bracknell Coral Reef - One Year Impact Report 1.0 Introduction
1.1.1 The Coral Reef junction is located on the busy A322 / A329 corridor. This route provides a key strategic link between the M3 and M4 motorways, and runs through the centre of Bracknell, linking Surrey and Hampshire in the South, to Berkshire and Oxfordshire in the North. The route is forecast to see considerable growth in traffic over the next five to ten years, as Bracknell and the region see significant new development generating more trips, and increasing the population of the area as a result of the adopted Site Allocations Local Plan and also a new regenerated Town Centre.
1.1.2 In response this forecast demand Bracknell has invested heavily over the last 5 years to improve the A322 / A329 corridor, as shown in Appendix 1, and provide more reliable journey times and create more capacity for growth in the borough. Much of these improvements so far have centred on improving capacity at key junctions and the application of Intelligent Transport Systems to allow us to manage movement along and across the corridor for all users. To date this work has been funded by a mix of Borough capital, government funding initiatives such as the Local Pinch Point Programme and the Local Growth Deal as well as developer contributions
1.1.3 The Coral Reef Junction is the most significant as it involved the complete removal of a large roundabout, replaced with a signalised 4-way junction. These works took just under a year to complete, and as expected did result in some disruption and likely diversion of traffic, however the works were delivered ahead of schedule and on budget.
1.2Travel Demand on the Corridor
1.2.1 The A329/A322 corridor is the one of the region’s busiest and most important routes, passing through Bracknell's urban areas, carrying in excess of 50,000 vehicles per day.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.07 Bracknell Coral Reef: One Year Impact ReportReport | 1.1 MB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.