Resolved – That scheme 2.23 Reading: South Reading MRT Phases 3 and 4 be given full financial approval in the sum of £10,148,000 over three years (2017/18-2019/20) on the terms of the funding agreement set out at paragraph 11 step 5 of the report.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.23 Reading: South Reading MRT Phases 3 and 4. This is one scheme that was split into two phases in anticipation of there being insufficient funds to approve the whole of the necessary works. In the event both phases 3 and 4 have received funding and the proposal is to manage this as one scheme through to completion.
2. The proposal is a new public transport link between central Reading and Mereoak Park and Ride to the south of the M4 at Junction 11. Phases 5 and 6 have yet to be funded. A diagram showing the scheme and its phases is attached at Appendix 1.
Recommendation
3. You are recommended to give scheme 2.23 Reading: South Reading MRT Phases 3 and 4 full financial approval in the sum of £10,148,000 over three years (2017/18-2019/20) on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
4. Scheme 2.23 Reading: South Reading MRT Phases 3 and 4 was a named scheme in the Thames Valley Berkshire Growth Deal 3i, announced by the Government on 2 February 2017ii.
5. This report recommends that Reading Council be authorised to draw down the capital sum £10,148,000 from the Local Transport Body funding for Phases 3 and 4 of this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Item 6 BLTB 16 November 2017 Financial Approval 2.23 Reading: South Reading MRT Phases 3 and 4 Risk Management
7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes White Young Green (WYG) have been appointed as Independent Assessors and have provided a full written report (see Appendix 2) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they must act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
9. The scheme will be carried out by Reading Borough Council.
10. The full details of the scheme are available from the Reading BC websiteiv. A summary of the key points is given below:
Task Timescale Detailed design update December 2017 Procurement January 2018 Construction start March 2018 Construction finish March 2020
Activity Funder Cost (approx) Scheme development Reading Borough Council Major scheme funding Berkshire Local Transport Body £10.148m Private sector funding s.106 and other sources £2.536m Total £12.684m
11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of the full Assurance Frameworkv.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.