Resolved
Resolved – That the revenue support proposal and the drawdown of BRRP funds by Slough Borough Council as set out in appendix 1 to the report be approved.
Berkshire Local Transport Body approved this item on Thursday 14 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the revenue support proposal and the drawdown of BRRP funds by Slough Borough Council as set out in appendix 1 to the report be approved.
1. In March 2018 you agreed to issue calls for bids for funding via the Business Rates Retention Pilot (BRRP) and the associated re-prioritisation of schemes in the Growth Deal 3 list; in July 2018 you agreed to “top-slice” the £25m BRRP allocation by £600,000 in order to establish a scheme for providing revenue support to local authorities for the development of a strong pipeline of future infrastructure schemes.
2. In November 2018 and January 2019, you approved the revenue support proposals and the drawdown of BRRP funds by Reading, West Berkshire, Windsor and Maidenhead, Wokingham and Bracknell Forest.
3. This report recommends a further payment under the revenue support scheme to Slough.
4. You are recommended to approve the revenue support proposal and the drawdown of BRRP funds by Slough Borough Council set out in appendix 1.
Other Implications
Financial
5. The lead authority for BRRP and the process of operating the Business Rates element (agreeing baseline amounts, managing the pool of retained funds) is Bracknell Forest Council. The planning figure of £25m for 2018-19 is based on current estimates of business rates collection in 2018-19, and no revisions are anticipated.
6. The lead authority for the control of Local Growth Funds allocated to infrastructure or regeneration projects is the Royal Borough of Windsor & Maidenhead, the LEP’s Accountable Body.
7. The BRRP has been approved for financial year (2018-19); MHCLG has since approved a second year of the pilot (2019/20) and a planning number of c.£11m has been calculated for new infrastructure investment.
Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support 8. At your meeting in July 2018, you prioritised the following schemes from BRRP1:
Scheme £’000’s Slough Mass Rapid Transit (SMaRT) Phase 2 10.242 South Reading MRT Phases 3 and 4 7.898 Wokingham Winnersh Relief Road Phase 2 6.260 Revenue Support for Scheme Development 0.600 Total 25.000
9. The risks associated with large scale infrastructure investments are well known, and the BLTB has established risk management arrangements for the LGF transport capital programme (£111m over 6 years), referred to as the Assurance Framework1.
10. As part of the LGF oversight, government officials have reviewed this assurance framework and found it fit for purpose.
11. The Berkshire authorities have identified the LEP and its associated processes as an appropriate framework for managing the BRRP sums available; in this instance this means programme management by the BLTB and ultimate sign- off by the LEP Forum. The LEP Forum ratified this approach on 27 March 2018.
12. The implication is that promoters of infrastructure projects seeking funding from the BRRP will need to follow the same assurance framework as for LGF. This means acceptance at “programme entry” stage, followed by submission and independent assessment of a WebTAG compliant Full Business Case before being considered for financial approval.
Human Rights Act and Other Legal Implications
13. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the BRRP.
Supporting Information
Revenue Support for Business Case Preparation
14. In July 2018 you agreed that the £25m BRRP allocation for major capital schemes should be “top-sliced” by £600,000, which should then be allocated to the six Berkshire authorities. This would be a contribution to the development costs associated with major infrastructure projects identified in each of the emerging Local Plans.
15. The revenue support proposal has the following details:
1 http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Business Rates Retention Pilot: Revenue SupportReport | 128 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.