Resolved – That scheme 2.29 Wokingham: Winnersh Triangle Park & Ride be given conditional financial approval in the sum of £250,000 in 2019/20 and £2,600,000 in 2020/21 on the terms of the funding agreement set out a paragraph 11 step 5 of the report, subject to meeting the following conditions: (i) Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes. (ii) Or: Provision of updated VISUM model and TUBA model outputs that demonstrate both positive and consistent impacts across all user classes. (iii) Provision of benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. (iv) Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and South Western Railway (SWR). (v) Provision of confirmation of SWR management arrangements for delivering the internal station works. (vi) That the scheme retains high or better value for money once these conditions have been met.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.29 Wokingham: Winnersh Triangle Park and Ride (previously referred to as Wokingham: Winnersh Parkway).
2. The purpose of this scheme is to redevelop the transport links at Winnersh Triangle. The redevelopment will include double-decking the new park and ride site to add at least 250 additional car parking spaces, improvement of the station building including the surrounding area, reorganising the highways layout. These arrangements would complement growth plans of Frazer Centrepoint who are intensifying the use of Winnersh Triangle Business Park.
Recommendation
3. You are recommended to give scheme 2.29 Wokingham: Winnersh Triangle Park and Ride conditional financial approval in the sum of £250,000 in 2019/20 and £2,600,000 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:
3.1Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provision of updated VISUM model and TUBA model outputs that demonstrate both positive and consistent impacts across all user classes. 3.2. Provision of benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. 3.3. Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and South Western Railway (SWR). 3.4. Provision of confirmation of SWR management arrangements for delivering the internal station works. 3.5. That the scheme retains high or better value for money once these conditions have been met.
Other Implications
Financial 4. Scheme 2.29 Wokingham: Winnersh Triangle Park and Ride is a scheme being funded from the Thames Valley Berkshire Growth Deali. This scheme received funding on the basis of scheme 2.16 Maidenhead Station Access being awarded financial approval for a lesser amount on 16 November 2017 (minute 18a refers)ii.
5. This report recommends that the Wokingham Borough Council be authorised to draw down the capital sum £2,850,000 from the Local Transport Body funding for this scheme, subject to meeting the conditions set out in the recommendation.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
9. The scheme will be carried out by Wokingham Borough Council.
10. The full details of the scheme are available from the Wokingham Borough Council websiteiv. A summary of the key points is given below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.