Berkshire Local Transport Body, Thursday 14 March 2019 at 4.00pm

Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride

Approved Committee 2 papers

Berkshire Local Transport Body approved this item on Thursday 14 March 2019. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

Resolved – That scheme 2.29 Wokingham: Winnersh Triangle Park & Ride be given conditional financial approval in the sum of £250,000 in 2019/20 and £2,600,000 in 2020/21 on the terms of the funding agreement set out a paragraph 11 step 5 of the report, subject to meeting the following conditions: (i) Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes. (ii) Or: Provision of updated VISUM model and TUBA model outputs that demonstrate both positive and consistent impacts across all user classes. (iii) Provision of benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. (iv) Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and South Western Railway (SWR). (v) Provision of confirmation of SWR management arrangements for delivering the internal station works. (vi) That the scheme retains high or better value for money once these conditions have been met.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.29 Wokingham: Winnersh Triangle Park and Ride (previously referred to as Wokingham: Winnersh Parkway).

2. The purpose of this scheme is to redevelop the transport links at Winnersh Triangle. The redevelopment will include double-decking the new park and ride site to add at least 250 additional car parking spaces, improvement of the station building including the surrounding area, reorganising the highways layout. These arrangements would complement growth plans of Frazer Centrepoint who are intensifying the use of Winnersh Triangle Business Park.

Recommendation

3. You are recommended to give scheme 2.29 Wokingham: Winnersh Triangle Park and Ride conditional financial approval in the sum of £250,000 in 2019/20 and £2,600,000 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:

3.1Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provision of updated VISUM model and TUBA model outputs that demonstrate both positive and consistent impacts across all user classes. 3.2. Provision of benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. 3.3. Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and South Western Railway (SWR). 3.4. Provision of confirmation of SWR management arrangements for delivering the internal station works. 3.5. That the scheme retains high or better value for money once these conditions have been met.

Other Implications

Financial 4. Scheme 2.29 Wokingham: Winnersh Triangle Park and Ride is a scheme being funded from the Thames Valley Berkshire Growth Deali. This scheme received funding on the basis of scheme 2.16 Maidenhead Station Access being awarded financial approval for a lesser amount on 16 November 2017 (minute 18a refers)ii.

5. This report recommends that the Wokingham Borough Council be authorised to draw down the capital sum £2,850,000 from the Local Transport Body funding for this scheme, subject to meeting the conditions set out in the recommendation.

6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

7. The risk management arrangements already put in place by the Local Transport Body are as follows:  The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme  The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

8. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Supporting Information

9. The scheme will be carried out by Wokingham Borough Council.

10. The full details of the scheme are available from the Wokingham Borough Council websiteiv. A summary of the key points is given below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & RideReport 161 KB DownloadRead as text
PDF
TVB LEP Independent Assessors Report: Winnersh Triangle Park and RideReport 337 KB Download

At this meeting

Whole meeting

Who was there

12 of 21 attended
PB
Councillor Phillip Bicknell The Royal Borough of Windsor & MaidenheadCommittee Member, present
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, apologies, sent representative
MF
Councillor Martin F. Carter Slough Borough CouncilCommittee Member, present
JC
Councillor Jeanette Clifford West Berkshire CouncilCommittee Member, present
PJ
Councillor Pauline JorgensenCommittee Member, apologies, sent representative
TP
Councillor Tony Page Reading Borough CouncilChair, present
SA
Stuart Atkinson Thames Valley Berkshire LEP (Director& Chairman of Stuart Michael Associates, consulting engineers)Committee Member, present
CE
Charles Eales Thames Valley Berkshire LEP (Head of Strategic Partnerships, Microsoft UK)Vice-Chair, apologies
MK
Malcolm KemptonCommittee Member, present
BM
Bob MountainCommittee Member, present
SR
Simon RatcliffeCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEP (Group Compliance and Health & Safety Manager, Stewart's Coaches Ltd)Committee Member, present

All 21 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & RideThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies