Resolved
Resolved – That programme entry status be granted for scheme 2.42 Wokingham: Barkham Bridge for £4,265,431.
Berkshire Local Transport Body decided this item on Thursday 14 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That programme entry status be granted for scheme 2.42 Wokingham: Barkham Bridge for £4,265,431.
1. To give consideration to granting programme entry status to a new scheme from the July 2018 prioritised list (see Appendix 1) following confirmation from Slough Borough Council that, due to complexities of land ownership, scheme 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride cannot be delivered by the required March 2021 timing.
2. You are recommended to grant programme entry status for scheme 2.42 Wokingham: Barkham Bridge for £4,265,431
Other Implications
Financial
3. The LGF programme covers six financial years, 2015-16 to 2020-21, and the expectation is that the funds allocated to Thames Valley Berkshire LEP will be spent in that period, or failing that, fully committed to schemes that have started on site by March 2021 and have a “tail” of funding carried over into financial year 2021-22.
4. In January 2019, Reading Borough Council (RBC), had notified the LEP that they could not achieve a start on site for the East Reading (ER) MRT scheme in the required time limit. Your meeting in January agreed to the reallocation of £14,584,931 to six schemes, and postponed a decision about a seventh scheme, 2.41 Slough SMaRT Phase 3 A4 West Park and Ride.
5. This report recommends that a new seventh scheme, 2.42 Wokingham: Barkham Bridge, replaces the scheme previously indicated.
6. The amount available for reallocation is £5,648,069, as set out in Table 1 below. Table 1: Reallocation amounts Unallocated amount as at November 2018 1,166,000 Add: 2.14 and 2.25 East Reading MRT phases 1 and 2 19,067,000 20,233,000
Item 8 BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Less: 2.35 Reading: Reading West Station Upgrade 3,100,000 2.36 Wokingham: Coppid Beech Park and Ride 2,400,000 2.37 Bracknell: A322 A329 Corridor Improvements 1,200,000 2.38 Theale: Theale Station Park and Rail Upgrade 4,000,000 2.39 Wokingham: Coppid Beech northbound on-slip widening 2,322,431 2.40 Windsor: Town Centre Package 1,562,500 14,584,931 Unallocated amount as at 14 March 2019 5,648,069 Less: if agreed 2.42 Wokingham: Barkham Bridge 4,235,641 Available 1,412,428
7. Although the vast majority of LGF is ringfenced for strategic transport schemes there remains the possibility that the LEP will bring forward skills or enterprise capital projects for consideration, if these offer VfM, make more of a strategic impact and can be delivered swiftly. The LEP Board will be discussing this on 12 March 2019.
8. There remains a risk that the new scheme identified in this report will be unable to mobilise quickly enough to achieve the necessary start on site by March 2021; in that event any LGF not committed would be liable for return the government unspent.
9. This risk has been anticipated and reassurances have been given by Wokingham Borough Council that this scheme is already in development and will be able to start on site in the required time.
Human Rights Act and Other Legal Implications
10. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
11. At your meeting in July 2018, a list of 16 potential LGF schemes was considered and prioritised. They are listed at Appendix 1. See Appendix 2 for short summaries of each scheme and hyperlinks to detailed scheme proformas.
12. Following the delay to the progress of scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2, and the subsequent confirmation from the scheme promoter that it could not be delivered within the current Local Growth Fund (LGF) programme, i.e. by the end of 2020/21, it was agreed at the January 2019 meeting of the BLTB to re-allocate £19,067,000 LGF previously awarded.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revised Local Growth Fund Programme 2015/16 to 2020/21: UpdateReport | 173 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.