Resolved – (a) That the progress be noted on the schemes previously given programme entry status as set out in the report. (b) That the proposed changes to scheme 2.34 Slough MRT Phase 2 be noted and that BLTB receive a full report in November 2022.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) and Growth Deal 3 (Factsheet GD3iii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiv; and on the progress of schemes funded by the Business Rates Retention Pilots (BRRP) of 2018/19 and 2019/20. This report also reports on the transport element of the Getting Building Fund (GBF) released in September 2020.
2. The headline figure for transport scheme grants under the three Local Growth Deals is £135.96m. This includes £24m of “DfT retained” allocation relating to the Wokingham Distributor Roads. This report no longer includes detail for the TVB Smart City Cluster scheme, as this is reported separately to Berkshire’s Digital Infrastructure Group. A further £25m has been released through BRRP1 2018/19 and £11m from BRRP2 2019/20, with £1.1m being allocated to two digital projects. Thames Valley Berkshire has received £7.5m through the GBF, of which £2,093,000 has been allocated to two transport projects.
3. £14.742m LGF was spent on transport schemes in 2015/16, £16.546m in 2016/17, £15.055m in 2017/18, £8.810m in 2018/19 and £12.441m 2019/20; £44.366m in 2020/21. In addition, £25.547m was spent from BRRP and £2.093 from the GBF.
4. To note a change to the current programme of LGF schemes:
Scheme 2.34 Slough MRT Phase 2 – note the change in focus for the park and ride facility.
Recommendations
5. That you note the progress made on the schemes previously given programme entry status, as set out in the accompanying summary report.
6. That you note the proposed changes to scheme 2.34.
Other Implications
Risk management
7. The delegation of programme management responsibilities to the LEP/BLTB brings risks. The well-established scrutiny given by both BST(O)F and BLTB meetings is designed to mitigate that risk.
Item 6 BLTB 14 July 2022 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 - 1 8. There will be an element of risk for scheme promoters who invest in developing their schemes to full business case stage in accordance with the approved Assurance Frameworkv. However, there is also risk involved in not developing the schemes; that risk is that any reluctance to bring the schemes forward will result in any final approval being delayed or refused.
9. The risks associated with each scheme are monitored locally. Table 4 has been adapted to show the current risk rating of each of the schemes. Completed schemes are shown in blue.
Financial
10. Thames Valley Berkshire LEP has been granted freedoms and flexibilities in managing the Local Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the award of LGF to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.
Table 1: Available Finance for Transport Schemes (including digital) in TVB Local Growth Deal, BRRP and GBF
£m 2015/16 – 2022/23 Growth Deal 1 “DfT Major Schemes” 24.0 Local Growth Deal 112.0 BRRP 2018/19 and 2019/20 34.9 Getting Building Fund 2020/21 and 2.1 2021/22 Grand Total 172.9
*Digital infrastructure projects have been removed from the totals above as these are governed by the Digital Infrastructure Group.
11. The profile and status of the available money in each year is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.