RESOLVED – That the Board: i. Note the scale of the investment and timescales associated with the Transforming Cities Fund. ii. Note the ongoing work highlighted in section 2 of the report that would enable SCR to offer appropriate leadership and support to partners to help ensure successful scheme delivery. iii. Recommend to the MCA a new approach to help ensure earlier release of scheme development funds (as set out in section 2.14 of the report), noting that this included changes to the current levels of delegated responsibility. iv. Recommend to the MCA a revised approach to ... view the full minutes text for item 8.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This report sets out how the City Region intends to work with scheme sponsors to deliver the Transforming Cities Fund programme by March 2023.
Thematic Priority
Secure investment in infrastructure where it will do most to support growth.
Recommendations
That members of the Transport Board:
• Note the scale of investment and timescales associated with the Transforming Cities Fund • Note the ongoing work highlighted in Section 2 that would enable SCR to offer appropriate leadership and support to partners to help ensure successful scheme delivery • Recommend to the MCA a new approach to enable earlier release of scheme development funds (as set put in section 2.14), noting that this includes changes to the current levels of delegated responsibility • Recommend to the MCA a revised approach to approving different stages of business case development, noting that this includes changes to delegated responsibility as set out in sections 2.15 and 2.16.
1. Introduction
1.1The Strategic Outline Business Case (SOBC) for the Transforming Cities Fund (TCF) was submitted to the DfT on 27th November 2019. A decision is expected before March 2020.
1.2The development of a large capital programme requires significant early investment to ensure constituent projects deliver robust business cases. This is especially important with this programme given the 3-year delivery timeframe.
1.3This paper proposes that the Transport Board considers recommending to the MCA that TCF scheme development funding should be made available earlier on in a project’s life as well as how TCF scheme development and construction could be delivered differently. The paper also proposes arrangements for the appraisal and approval of TCF schemes. The recommendations only relate to the SCRs TCF programme and no others. 2. Proposal and justification
2.1The TCF programme will be judged a success by Government if SCR delivers a time- limited complex programme to time and budget. Given the size of the programme and the limited period to deliver schemes a ‘business as usual’ approach to delivering the programme is unlikely to succeed. Attention is now focused on proposing the best possible arrangements to deliver efficiently and effectively, ensuring that we have procedures to aid project and programme delivery.
This paper looks at two programme level risks that have been identified that could be constraints on our ability to deliver the programme on time and budget. They relate to the availability of resources to deliver the programme (both internal and external) and funding scheme development costs. It also considers project leads and how projects will be approved.
2.2The final SCR TCF SOBC included three funding scenarios for capital programmes that need to be delivered over the four years to March 2023. The final values were: • Low - £185 million • Medium - £200 million • High - £229 million. These values include 5% inflation across the funding period and an allowance for risk drawn from a quantified assessment of the risks identified in the risk register
Programme Delivery key issues
Project leads 2.3 To be efficient and effective in delivery, an important principle is that schemes should be delivered by those best placed to do so, which has tended to mean those that are solely/predominantly public transport should be led by South Yorkshire Passenger Transport Executive (SYPTE), active travel schemes by District partners and multi-modal schemes (that combine both) by District partners too.
2.4However, there are some individual schemes or groups/packages of schemes that may not be considered as ‘business as usual' because they are cross-boundary, they are more complex/higher risk, or they involve external partners (e.g. Northern Trains or Highways England). Therefore, there needs to be an early decision about who is best to lead each project/package.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SCR - Transport Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.