RESOLVED – That the Board approve: i) Progression of Rotherham Town Centre Active Travel Project Outline Business Case to Full Business Case and the release of up to £1,240,690 business case development cost funding to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary at Appendix A to the report. ii) Progression of Project ‘Sheffield Heart of the City Breathing Spaces’ to MCA for award of £2m grant from the Transforming Cities Fund subject to the conditions set out in the Appraisal panel Summary at Appendix B to the report. iii) The project change request from “Sheffield Package of Cycling Infrastructure” to agree an extension to the completion date. iv) Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into a legal agreement for the early release of business case development funding for the Rotherham Town Centre scheme and the Sheffield Package of Cycling Infrastructure change request
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Report to MCA - Transport and the Environment Board
Purpose of report
This paper seeks:
1. Approval of progression of one Transforming Cities Fund Tranche 2 (TCF2) Outline Business Case to Full Business Case and early release of up to £1.24m business case development cost funding and, 2. Progression of one Transforming Cities Fund Tranche 2 (TCF2) scheme to MCA for approval with a total value of £2m 3. Approval of one change request for an existing Transforming Cities Trance 1 (TCF1) project 4. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the scheme covered at point 1 above.
Freedom of Information and Schedule 12A of the Local Government Act 1972
The paper will be available under the Combined Authority Publication Scheme.
Recommendations
The Board consider and approve: 1. Progression of Rotherham Town Centre Active Travel Project Outline Business Case to Full Business Case and release of up to £1,240,690 business case development cost funding to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix A 2. Progression of Project ‘Sheffield Heart of the City Breathing Spaces’ to MCA for award of £2m grant from the Transforming Cities Fund subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix B 3. Project change request from “Sheffield Package of Cycling Infrastructure” to agree an extension to the completion date, 4. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into a legal agreement for the early release of business case development funding for the Rotherham Town Centre scheme and the Sheffield Package of Cycling Infrastructure change request covered above.
1. Introduction
1.1In March 2020 the MCA was awarded £166.3m funding for the MCA’s TCF aspirations. This grant was allocated from April 2019 to March 2023 resourcing a programme of transformational public transport, active travel and rail initiatives.
1.2In March 2020 the MCA approved the early release of scheme development costs:
• release up to 2% of the total scheme cost (as included in the bid/SOBC) to facilitate the development of the OBC. • release costs (based on a costed fee plan) following approval of the OBC to enable the schemes to progress to FBC
This paper requests approval of progression of one scheme to Full Business Case (FBC) and early release of up to £1.24m development costs subject to any conditions to be set out in the Appraisal Panel Summary Table, with a total scheme value of £10.9m and progression to the MCA for full approval for one scheme subject to any conditions to be set out in the Appraisal Panel Summary Table with a value of £2m.
1.3In recognition of unforeseen circumstances that can arise during the project delivery phase, the approved Assurance Framework establishes a formal process for the acceptance of change requests. These change requests could be financial requiring reprofiling of funds or could be to amend deliverables or timescales.
The Assurance Framework established that some change requests will be presented for approval to the relevant Executive Board, in line with their agreed delegation levels whilst others will require the approval of the MCA Board. In line with the agreed Assurance Framework there is one change requests proposed through this report which require Executive approval. This are detailed in sections 2.7 below.
2. Proposal and justification
2.1Rotherham Town Centre Active Travel
Appendix A provides a summary of the scheme appraisal and the suggested conditions of award.
2.2The Project - This investment is for £9.3m from TCF towards a total scheme cost of £10.9m
Rotherham Town Centre Active Travel is a package of measures to facilitate walking and cycling to, from and within Rotherham Town Centre, comprising three schemes:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.