Elephant and Castle Supplementary Planning Document/Opportunity Area Planning Framework
ApprovedExecutive7 papers
AI summarySouthwark Cabinet approved the draft Elephant and Castle supplementary planning document and opportunity area planning framework for consultation, and noted the supporting documents. [D] No immediate additional council funding is required. [P38] [P39]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSupporting documents were also noted [D]
MoneyNo immediate financial implications [P38]Consultation and finalisation work uses existing team budgets [P38] [P39] [P64]
What happens next6 week formal consultation [P10]27 December to 7 February 2012 [P10]
Who it affectsElephant and Castle opportunity area [P4]122 hectares, with nine character areas [P4] [P12]
What was decided
The draft Elephant and Castle supplementary planning document/opportunity area planning framework was approved for consultation. Report P2, P44
The Consultation Plan, Equalities Impact Assessment, Sustainability Appraisal and Appropriate Assessment were noted. Report P2, P67
The document remained at consultation stage rather than being finally adopted. Report P37, P40, P44
Why
The 2004 SPG and 2008 SPDs were becoming out of date. Their housing and floorspace figures no longer matched the Core Strategy or London Plan, and some proposed uses were no longer required. Report P5
The refresh was intended to coordinate growth, direct development to appropriate places, protect sensitive areas and reinforce local character. Report P6
The council and the Mayor worked closely on the draft. A joint approach would give developers certainty, give the public and councillors clarity, and provide a basis for assessing forthcoming planning applications. Report P8
What happens next
Publish the draft on 15 November 2011 and consult formally for 6 weeks from 27 December to 7 February 2012. Make it available on the web and in local libraries, with public inspection for 12 weeks, and contact around 3000 consultees. Hold events, exhibitions, walkabouts and workshops, and attend meetings as required. Report P10
Consult separately on the proposed conservation areas at Larcom Street and Elliotts Row. Report P17
Bring any financial implications of final adoption before subsequent reports for consideration and approval. Report P40
The money
around £50m Estimated strategic transport funding over 20 years Report P28
in the region of £20m TfL estimated cost of transport improvements Report P24
up to £85m TfL estimated cost of additional lift access Report P24
£104 per square metre Residential use strategic transport contribution Report P23
£65 per square metre Student housing strategic transport contribution Report P23
£145 per square metre Hotels strategic transport contribution Report P23
£12 per square metre Retail strategic transport contribution Report P23
Options considered
Chosen: Managed Growth: a major new town centre destination. The appraisal found a more balanced mix of uses and stronger long term benefits for jobs, skills, community cohesion, local services, walking, cycling and crime reduction. Report P35
Rejected: Business as usual: no SPD. The appraisal found weaker long term sustainability outcomes than for the major town centre destination option. Report P35
Rejected: Managed Growth: a district centre meeting local needs. The appraisal found fewer long term sustainability benefits than for the major town centre destination option. Report P35
Rejected: Tallest development elements on the shopping centre. Very tall buildings were likely to detract from the world heritage value of the Palace of Westminster in the protected view from the Serpentine Bridge. Report P18
Chosen: Tall buildings as focal points along main roads and gateways. Tall buildings should act as focal points on main routes and at gateways, then reduce in height away from those points. Report P18
Rejected: Further student housing in the northern end of Walworth Road. Northern Walworth Road already has around 460 bedspaces, with another 220 proposed, and the area should remain mixed. Report P16
Chosen: Removal of the northern roundabout subways and replacement with surface crossings. Removal supports the draft's walking, cycling and public realm proposals. Report P20
Chosen: 3 additional lifts at the northern line station. TfL agreed that this would provide a fit for purpose solution. Report P20
Implications
Financial: Consultation and work needed to finalise the report will remain within existing Planning Policy team budgets, with no immediate financial implications. There are no risks to other council budgets. Any financial effects of final adoption will come through later reports. Report P38, P39, P40
Financial: The draft sets strategic transport contributions and prioritises them for transport improvements. TfL estimates that transport work will cost in the region of £20m and lift access up to £85m, with around £50m potentially generated over 20 years. With a 30% increase in land values and 15% increase in construction costs over a 20 year period, the estimate could rise to around £60m. The tariff will be updated every year in line with inflation, construction costs and sales values, and developers claiming unviability must provide an open book financial appraisal. Report P23, P24, P26, P27, P28
Legal: An SPD provides detailed guidance on existing policies but cannot create new policies. It has no development plan status, is not independently examined, and the presumption in favour of the development plan does not apply. Until the new SPD is adopted, the existing SPG continues to apply. After adoption, it will be a material consideration in planning application decisions. Report P7, P45, P46
Legal: The SPD was prepared under the statutory process and is likely to conform with the Human Rights Act 1998. Human rights effects will be considered when its policies are applied through development control. Report P62
Equalities: Displacement of local businesses may disproportionately affect black and ethnic minority workers and older people. Affordable business space will give priority to businesses displaced from the opportunity area. Report P30
Equalities: Transport and public realm changes need safe, accessible routes and spaces for disabled people, young families and older people. Walking, cycling and open space may benefit people on lower incomes, young people and women. Report P31, P32
Climate: All new development must meet Code for Sustainable Homes level 4 or BREEAM excellent as a minimum. The draft addresses energy, water, waste and traffic through design guidance, while promoting green routes, living walls, green roofs and new public park provision. Report P15, P19, P35
Other: The planning target is at least 4,000 new homes and around 5,000 new jobs by 2026. The draft indicates capacity for around 6000 new homes between 2011 and 2026, with at least 35% affordable, at least 35% private, and at least 10% having 3 or more bedrooms. All homes should provide good quality living environments with generous space standards. Report P4, P14
Who and where
Existing traders and local small and medium sized businesses in the shopping centre and surrounding area Report P30
Black and ethnic minority workers and older people working in existing businesses Report P30
Residents and future residents of the opportunity area Report P14, P19
Disabled people, young families and older people using routes and public spaces Report P31, P32
People on lower incomes, young people and women Report P31, P32
Developers seeking planning permission in the opportunity area Report P8, P22, P26
London South Bank University and the London College of Communications Report P16
People using local schools, health facilities, community facilities, arts, leisure and entertainment venues Report P21
Timeline
2004: The council adopted the supplementary planning guidance for the core opportunity area. Report P5
2008: The council adopted SPDs for the Enterprise Quarter and Walworth Road. Report P5
14 November 2011: The report was marked final. Report P69
15 November 2011: The draft SPD was due to be published. Report P10
27 December to 7 February 2012: The formal consultation was due to run for 6 weeks. Report P10
by 2026: At least 4,000 new homes and around 5,000 new jobs were targeted. Report P4
between 2011 and 2026: The draft indicated capacity for around 6000 new homes. Report P14
over 20 years: Around £50m in strategic transport funding was estimated. Report P28
Plain English for the jargon
SPD: Detailed planning guidance that supplements existing policies. It cannot create new policies. [P7]
OAPF: An opportunity area planning framework covering the whole Elephant and Castle opportunity area. [P8]
SPG: The 2004 supplementary planning guidance for the core opportunity area. [P5]
s106: Planning obligation funding used for infrastructure such as open space, school places and community facilities. [P22]
EQIA: An assessment of effects on groups with protected characteristics. [P30]
material consideration: A factor that must be taken into account when determining a planning application. [P7]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That th e draft Elephant and Castle supplementary planning document/opportunity area planning framework (Appendix A of the report) be approved for consultation and the consultation plan (Appendix B of the report), the equalities impact assessment (Appendix C), the sustainability appraisal (Appendix D) and the appropriate assessment carried out under the EU Habitats Directive (Appendix E) of the report be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Recommendations
That cabinet approves:
1. For consultation the draft Elephant and Castle Supplementary planning document/opportunity area planning framework (appendix A) and note the Consultation Plan (appendix B), the Equalities Impact Assessment (appendix C), the Sustainability Appraisal (appendix D) and the Appropriate Assessment carried out under the EU Habitats Directive (appendix E).
BACKGROUND INFORMATION
2. The Elephant and Castle opportunity area is identified in the London Plan (2011) and the council’s recently adopted Core Strategy (2011). It covers an area of 122 hectares. In addition to the shopping centre and Heygate Estate, the opportunity area also incorporates Walworth Road, London South Bank University campus, St George’s Circus, West Square and the Imperial War Museum and Newington Causeway. Both the London Plan and the Core Strategy recognise its potential for change and growth and set a target of providing at least 4,000 new homes by 2026 and around 5,000 new jobs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.