Gateway 2: Contract Award Approval - Supply of Gas to Sites Consuming less than 25,000 Therms

Agreed Executive 1 paper

AI summarySouthwark Cabinet approved a four year gas supply framework for 132 sites, awarded to LASER with Total Gas and Power, with an estimated value of £4,074,160. The Leader delegated later purchasing and management choices to the cabinet member for transport, environment and recycling. [D][P16]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTripartite POSO agreement covers sites under 25,000 therms. [D]
Money£4,074,160 estimated contract value [D]Actual costs depend on market conditions and purchasing decisions. [P7][P91]
What happens nextPurchasing and management decisions delegated [D]Cabinet member for transport, environment and recycling. [D]
Who it affects132 sites and service users [P16][P77]Includes housing estates, schools and municipal offices. [P16]

What was decided

Cabinet approved the gas supply award to LASER through a tripartite agreement with Total Gas and Power using POSO, for all sites consuming less than 25,000 therms. [D][P2] Report P2

The report estimates £1,018,540 for current annual costs and £4,074,160 over four years, including LASER service charges. [P92][P94] Report P92, P94

The Leader delegated authority to the cabinet member for transport, environment and recycling to approve and change the management option and amend the purchasing solution before and during the contract. [D][P4][P5] Report P4, P5

Why

LASER lets the Council access wholesale rather than retail prices for gas at 132 sites, including smaller centrally heated housing estates, schools and municipal offices. [P16] Report P16

Using LASER avoids another OJEU tender process, saving time and money. [P16] Report P16

Because gas prices are volatile, the authority wanted the purchasing choice made nearer the contract start, with changes allowed during the contract. [P7][P17][P18][P19] Report P7, P17, P18, P19

What happens next

The cabinet member for transport, environment and recycling is to choose between Purchase in Advance and Purchase Within Period by 31 March 2012. The choice may be amended during the contract. [P18][P19] Report P18, P19

The energy management team will evaluate the management option before 31 March 2012 and monitor contract performance at 6 monthly reviews. [P31][P57][P62] Report P31, P57, P62

Housing inclusion remains subject to leaseholder consultation observations. The energy team will transfer gas accounts and supply details to Total Gas and Power before the supply date in October 2012. [P80][P60] Report P80, P60

The money

  • £4,074,160 Estimated four year contract value Report P2, P94
  • £1,018,540 Estimated current annual cost, including service charges Report P92, P94
  • £14,040 Estimated annual POSO charge for 205 meters Report P54
  • £32,969 Estimated annual charge for fully managed service Report P52

Options considered

  • Chosen: Procurement Only Service Option (POSO). LASER secures wholesale prices and Total Gas and Power directly invoices sites. [D][P53] Report P53
  • Rejected: Fully managed LASER service at contract start. POSO was recommended initially, while the Council retained the option to switch during the contract. [P53][P55] Report P53, P55
  • Rejected: Government Procurement Services framework. GPS could not provide the managed solution the Council might require and scored lower than LASER. [P47][P125] Report P47, P125
  • Rejected: A further Council OJEU tender. Using LASER avoids an OJEU tender, saving time and money. [P16][P106] Report P16, P106

Implications

  • Financial: This is a buying method, not a fixed gas price tender. Actual billed costs depend on gas use, the purchasing option and wholesale market prices. [P54][P89][P91] Report P54, P89, P91
  • Risk: Purchasing can change based on performance, markets, forecasts and authority risk. No performance bond is needed, and OFGEM would appoint a supplier if Total Gas and Power ceased trading. [P19][P20][P74][P75] Report P19, P20, P74, P75
  • Legal: LASER's appointment of Total Gas and Power followed EU procurement regulations, allowing use of the framework without another tender. The Leader may delegate contract decisions under Section 14 of the Local Government Act 2000, as amended. [P106][P107] Report P106, P107
  • Legal: Leaseholder consultation had not ended when the report was written. Housing blocks could be included or removed depending on consultation observations. [P80][P120] Report P80, P120
  • Equalities: Rising energy prices affect all sections of the community, whether they use communal systems or have their own boilers. [P77] Report P77
  • Climate: No sustainable alternative was available for the natural gas heating systems covered by the contract. [P83] Report P83
  • Staffing: Client departments pay and monitor their own invoices. The energy team acts as the single contact with the supplier and manages the transition. [P88] Report P88
  • Other: Schools and leisure centres will be notified and may opt out before the start in September 2012. The energy team will transfer gas accounts before the supply date in October 2012. [P100][P60] Report P100, P60

Who and where

  • Southwark Council Report P2, P105
  • 132 sites consuming less than 25,000 therms Report P16, P66
  • Leaseholders in housing blocks Report P80, P118
  • Tenants and consumers using communal heating Report P43, P77
  • Schools and leisure centres Report P100
  • Municipal offices Report P16
  • Client departments and facilities managers Report P88, P93
  • Sites affected by council estate disposals and rationalisation Report P90

Timeline

  • 13th June 2011 to 2nd August 2011: Notice of Intention was served on affected leaseholders and then expired. Report P118
  • 22 August 2011: Leasehold Valuation Tribunal dispensation was granted. Report P78, P117
  • by the 30 August 2011: Notice of Proposal was to advise leaseholders of estimated LASER overhead costs. Report P79, P119
  • 31 March 2012: Deadline for the purchasing option and management solution decision. Report P18, P31
  • prior to the supply date in October 2012: Gas accounts and supply details transfer to Total Gas and Power. Report P60
  • 1 October 2012: Southwark's participation in the contract starts. Report P110
  • 30 September 2016: The four year framework contract expires. Report P7
  • throughout the duration of the contract: Management options are reviewed and the purchasing solution may change. Report P55, P57, P59

Plain English for the jargon

  • LASER: A local government purchasing consortium and part of Kent County Council. [P85]
  • GPS: Government Procurement Services, formerly Buying Solutions. [P15]
  • Procurement Only Service Option (POSO): LASER's unmanaged service, where Total Gas and Power invoices sites directly. [P53]
  • Purchase in Advance (PIA): One of two purchasing solutions for the gas contract. [P17][P18]
  • Purchase Within Period (PWP): One of two purchasing solutions for the gas contract. [P17][P18]
  • OJEU: Official Journal of the European Union, where an award notice was to be placed. [P13][P106]
  • Framework contract: The four year agreement used to secure the Council's gas requirements. [P7]
  • Managed service: LASER's fully managed option, with a fixed charge added to the unit energy cost. [P50]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Decision of the Cabinet 1. That the award of the supply of gas to all sites consuming less than 25,000 therms to LASER in the form of a tripartite agreement with Total Gas and Power using the Procurement Only Service Option (POSO) be approved. The estimated sum, of £ 1,018,540 for a period of four years (with effect from 1 October 2012) making a total contract value of £ 4,074,160 . This includes management fees from LASER. Decisions of the Leader of the Council 2. That authority be delegated to the cabinet member for transport, environment and recycling, prior to, and throughout the duration of the contract (as detailed in the procurement project plan and timeline, paragraph 4 of the report) to; · approve the management option selected for the contract, and consider the flexibility to change the management option (detailed in paragraphs 25 – 32 of the report ), and; · amend the purchasing solution (Purchase in Advance or Purchase within Period detailed in paragraph 8 of the report).
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

Recommendation for the Cabinet

1. That the cabinet approve the award of the supply of gas to all sites consuming less than 25,000 therms to LASER in the form of a tripartite agreement with Total Gas and Power using the Procurement Only Service Option (POSO). The estimated sum, of £1,018,540 for a period of four years (with effect from 1 October 2012) making a total contract value of £4,074,160. This includes management fees from LASER.

Recommendation for the Leader of the Council

2. That the leader delegates authority to the cabinet member for transport, environment and recycling, prior to, and throughout the duration of the contract (as detailed in the procurement project plan and timeline, paragraph 4) to;

• approve the management option selected for the contract, and consider the flexibility to change the management option (detailed in paragraphs 25 - 32), and; • amend the purchasing solution (Purchase in Advance or Purchase within Period detailed in paragraph 8).

BACKGROUND INFORMATION

3. The recommendation of this report is that the gas requirements of this existing contract are secured via a four year framework contract which expires 30 September 2016. As gas is a volatile traded commodity, the ‘wholesale’ cost of gas has been excluded from the tender (gas will be purchased from the wholesale market at different times both before and during the contract term). This contract has therefore not been awarded on the basis of gas price. The contract costs set out above are therefore estimates, and actual costs will depend upon market conditions and purchasing decisions taken during the contract.

4. This contract has no extension duration built into the contract.

Procurement project plan

Date Activity completed Forward Plan (if Strategic Procurement) 01/06/2011

DCRB/CCRB/CMT Review Gateway 1: Procurement Strategy Approval DCRB 01/06/2011 CCRB 02/06/2011 Issue Notice of Intention Note: this is for contracts that only affect Leaseholders. This period is 13/06/2011 for 8 weeks Gateway 1: Procurement strategy for approval report 21/06/2011 Scrutiny Call-in period and notification of implementation of Gateway 1 decision 30/06/2011

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 2: Contract Award Approval: Supply of gas to sites consuming less than 25,000 thermsReport 15 pages DownloadRead as text

At this meeting

Whole meeting
5MinutesApproved 7School Admissions Review - Report of the Education and Children's Services Scrutiny Sub-CommitteeNoted 8Reporting the Outcome of Statutory Consultation on the Proposed Enlargement of St. Anthony's Catholic Primary School from 1.5 to a 2 Form Entry Primary School from 1 September 2012Agreed 9Quarterly Revenue Monitoring Report Quarter 1, 2011/12, including Treasury ManagementNoted 10Quarterly Capital Monitoring Report Quarter 1Approved 11Approval of the Council's Transport for London funded work programme for 2012/13 and indicative programme to 2013/14 for submission to Transport for LondonAgreed
12Gateway 2: Contract Award Approval - Supply of Gas to Sites Consuming less than 25,000 ThermsThis decision
13Motions Referred from Council AssemblyNoted 14Gateway 2: Contract Award Approval - Supply of Gas to Sites Consuming more than 25,000 ThermsAgreed 15Energy and Carbon Reduction StrategyNoted 16Overview and Scrutiny Committee Call-In Decision: Procurement Strategy and Procurement Award of Local Education Partnership to deliver design work for the Elephant and Council Leisure CentreDecided 17Authorisation of Debt Write-off over £50,000 for Health and Community ServicesAgreed 1822 Champion Grove, SE5 and 11 Desenfans Road, London SE21 - Disposal of Freehold InterestApproved 19Disposal of 4 Heaton Road, London SE15 3THApproved 20Authorisation of Debt Write-Offs over £50,000 for National Non Domestic Rates - Revenues and BenefitsApproved 21Exclusion of Press and PublicDecided

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
DC
Deborah CollinsOfficer, expected
AS
Annie ShepperdOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 2: Contract Award Approval - Supply of Gas to Sites Consuming less than 25,000 ThermsThis decision
  2. Gateway 1 - Highway works contractApproved
  3. Gateway 3 - Variation Decision - Parking and Traffic enforcement and associated services contractApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies