Quarterly Revenue Monitoring Report Quarter 1, 2011/12, including Treasury Management
NotedExecutive3 papers
AI summarySouthwark Cabinet noted 2011/12 revenue and treasury forecasts and approved general fund budget movements exceeding £250,000. The forecast was £1.883m favourable overall, and a future collection service report is required.
Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral fund movements exceeding £250,000 were approved. [D]
Money£1.883m favourable variance [P29]Overall general fund forecast, assuming full contingency use. [P29]
What happens nextCollection service report required [P3]It must go to Cabinet and the forward plan. [P3]
Who it affectsServices and tax payers [P111]Revenue monitoring covers spending and collection performance. [P105] [P111]
What was decided
Cabinet noted the 2011/12 general fund outturn forecast and forecast net movement in reserves. [P2] It also noted the housing revenue account forecast, resulting reserve movement and first quarter treasury management activity. [P2] Report P2
Cabinet noted forecast performance for the Council Tax and Business Rates collection fund. [P3] A report on service performance since the move in house must go to Cabinet and be placed on the forward plan. [P3] Report P3
Cabinet approved general fund budget movements exceeding £250,000, as set out in Appendix A. [D] [P4] Report P4
Why
The forecast used experience to date and knowledge as at the end of Quarter 1 (June 2011). [P7] Work continued to ensure a balanced position by the year end. [P7] Report P7
The council had agreed a balanced budget of £321m on 22 February 2011, with a nil council tax increase. [P8] The plan included a 25% savings target over three years. [P8] Reserve support required departments to show they could not contain an additional pressure within their existing budget. [P98] Report P8, P98
The effect of bringing the collection service in house could not yet be quantified with certainty. [P105] There was no evidence the fund would miss its year end break even target, but discounts and exemptions created risks to income. [P105] Report P105
What happens next
A report on collection service performance since the in house move will go to Cabinet and be placed on the forward plan. [P3] [P105] Report P3, P105
The health and community services action plan was expected to achieve £385k of savings. [P86] It includes closer control of payments and purchasing, holding vacancies, limiting agency staff, reviewing care packages and maximising income. [P87] Report P86, P87
The council will continue monitoring landlord maintenance and improvement spending pressure and related housing revenue account risks through 2011/12. [P66] Report P66
The money
£250,000 Threshold for approved general fund budget movements Report P4
£1.883m Forecast favourable general fund variance for 2011/12 Report P29
£2.5m Projected savings shortfall at Quarter 1 Report P74
£5.5m Contingency budget, assumed fully used Report P29, P64
£22.4m Housing revenue account budget movements for 2011/12 Report P96
£56.2m Agreed reductions, savings and efficiencies across both funds Report P74
£762m Long term debt held throughout the quarter Report P109
280.4 Total investment counterparty exposure in £m Report P108
Options considered
Chosen: Bring a collection service performance report to Cabinet and the forward plan. The impact of the in house move could not be quantified with certainty and collection risks remained. Report P3, P105
Chosen: Use contingency for cost pressures and any remaining funding gap. The forecast assumed full use of contingency, and unused contingency would first bridge any funding gap. Report P29, P100
Chosen: Contain the £600k garage income shortfall within housing revenue account contingency and address it in 2012/13 rent and budget setting. The variance could be contained within contingency during 2011/12. Report P96
Chosen: Hold staff vacancies and limit agency staff within the health and community services mitigation plan. These measures formed part of the senior management action plan to contain care spending pressures. Report P86, P87
Rejected: Replace unrealised Vangent savings from other housing general fund budgets. Substitution from other budgets was considered unlikely, with a possible call on corporate reserves. Report P46
Rejected: Recover the travellers' site rent shortfall later in 2011/12. There was no scope to recover the rent debit over the remainder of the year. Report P49
Rejected: Deliver parking enforcement savings in 2011/12 and 2012/13. The current contract did not expire until February 2013, so savings were not realised until 2013/14. Report P89
Chosen: Maximise private rented sector supply as an alternative to bed and breakfast. Private rented homes were a more cost effective alternative, and procurement was expected to recover during the next quarter. Report P48
Implications
Financial: The general fund forecast was £1.883m favourable and assumed full use of the £5.5m contingency. [P29] [P64] Quarter 1 savings delivery had a projected shortfall of £2.5m. [P74] Report P29, P64, P74
Financial: The housing revenue account was forecast neutral at month 3, but landlord maintenance and improvement spending remained under pressure. [P66] Report P66
Risk: Unrealised housing customer service centre savings may ultimately require a call on corporate reserves. [P46] Report P46
Risk: Collection fund income and the year end break even target remained exposed to the level of discounts and exemptions awarded. [P105] Report P105
Legal: As billing authority, the council must maintain a collection fund account showing council tax and business rates transactions and their distribution. [P103] [P104] Report P103, P104
Staffing: The forecast excluded estimates of one off reorganisation and redundancy costs. [P27] Health mitigation includes holding vacancies and limiting agency staff. [P87] Report P27, P87
Equalities: Adult social care redesign and reconfiguration were planned for services meeting needs assessed at critical or substantial risk. [P12] Some £7.7m of savings were planned for 2011/12. [P12] Report P12
Other: The report was judged to have no or a very small impact on local people and communities. [P111] Its projected spending reflected plans designed to have an impact on local people and communities. [P111] Report P111
Who and where
Council service users Report P111
Housing tenants and leaseholders Report P15, P96
Children and families using children's services Report P30, P32
People using adult social care Report P12
Council tax and business rates payers Report P103, P105
People using homeless accommodation Report P47, P48
Council staff, Vangent, Southwark Building Services and Just Housing Management Report P17, P18, P27, P45, P46
Small businesses physically affected by the public disorder Report P28
Timeline
15 February 2011: Cabinet agreed a balanced housing revenue account budget. [P15] Report P15
22 February 2011: The council agreed a balanced general fund budget of £321m with a nil council tax increase. [P8] Report P8
1 April 2011: The council brought its revenue and benefits service in house. [P105] Report P105
30 June 2011: Quarter 1 forecasts were based on three months' experience. [P7] [P22] Report P7, P22
1 September 2011: The housing services restructure was fully implemented on target, and Just Housing staff transferred. [P17] [P18] Report P17, P18
1 October 2011: Implementation of the Southwark Building Services restructure was expected to take place. [P18] Report P18
1 January 2012: The Southwark Building Services management restructure was expected to be implemented. [P18] Report P18
2012/13: The £600k garage income variance was to be addressed through rent and budget setting. [P96] Report P96
Plain English for the jargon
General fund: The fund used to forecast spending and outturn across council departments. [P22]
Housing revenue account: The housing services account, including the council's landlord responsibilities. [P66]
Outturn: The forecast final result for the financial year. [P22]
Collection fund: The account showing council tax and business rates transactions and their distribution. [P104]
Billing authority: The council's collection role for council tax and business rates. [P104]
Contingency: Budget held for unforeseen costs that strategic directors cannot contain. [P64]
Savings shortfall: The gap between agreed savings and forecast savings at Quarter 1. [P74] [P75]
Treasury management: Management of the council's cash, debt balances, investments and borrowing. [P107] [P109]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the following be noted: · the general fund outturn forecast for 2011/12 and the forecast net movement in reserves; · the housing revenue account’s (HRA) forecast outturn for 2011/12 and resulting forecast movement in reserves; · the treasury management activity for the first quarter of 2011/12. 2. That the forecast performance for the council tax and business rates collection fund be noted, and that a report be brought to cabinet on the performance of the service since moving it in-house. 3. That the general fund budget movements that exceed £250,000, as shown in Appendix A of the report be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 14 pages
Recommendations
1. That the cabinet notes:
• the general fund outturn forecast for 2011/12 and the forecast net movement in reserves; • the housing revenue account’s (HRA) forecast outturn for 2011/12 and resulting forecast movement in reserves; • the treasury management activity for the first quarter of 2011/12.
2. That the cabinet notes the forecast performance for the Council Tax and Business Rates collection fund, and that a report will be brought to cabinet and put on the forward plan on the performance of the service since moving it in- house.
3. The cabinet approves the general fund budget movements that exceed £250k, as shown in Appendix A.
BACKGROUND INFORMATION
General fund
4. The purpose of this report is to provide a forecast for the end of the financial year 2011/12, using predictions based on the experience to date and knowledge as at the end of Quarter 1 (June 2011). Work continues throughout the council to ensure that a balanced position is achieved by the end of the year.
5. The council agreed a balanced budget of £321m on 22 February 2011 based on a nil council tax increase. This budget was set in the context of significant overall cuts in government funding. It required the identification of some 25% savings proposals over the three years from 2011/12 to 2013/14, to mitigate against the reduction in resources and to continue to fund the Council’s commitments in terms of services provided.
6. The budget plan recognised a number of key commitments and cost pressures. The budget for children’s services included a commitment of £785k over the two years from 2011/12 which is to cover the cost of lost funding for the youth offending services and to support young adults who are in receipt of a special guardianship order. £1.145m was agreed to fund the provision of free healthy school meals for primary aged pupils in maintained schools in Southwark in 2011/12. There will be a phased implementation over the academic years 2011- 14.
7. Core budget savings of some £5.8m in 2011/12 were proposed within children’s services. This target is significantly challenging whilst also bearing a reduction of nearly £6.0m in previous grant funding supporting core children’s services activities.
8. The budget agreed for health and community services in 2011/12 was £114.3m. This budget included a growth proposal of £1.85m to support approximately 45 young people with learning disability care needs in transition to adult social care. For 2012/13 and 2013/14 this pressure is expected to increase by a further £1.96m and £2.17m respectively, and therefore close monitoring and stringent financial control on costs will be required to contain such significant budget pressures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.