Quarterly Revenue Monitoring Report quarter 2, 2011/12, including Treasury Management
NotedExecutive3 papers
AI summarySouthwark Cabinet noted general fund and housing revenue account outturn forecasts, reserve movements and treasury activity, then approved general fund budget movements [D]. General fund services were forecast £2.6m over budget, with £5.5m contingency held for cost pressures [P22] [P70].
Written from the decision and the officer reportPDF Pro
OutcomeNotedForecasts, reserve movements, treasury activity and collection performance noted [D]
Money£2.6m unfavourable variance [P22]£5.5m contingency may cover year end pressure [P26] [P70]
What happens nextCollection service report planned [P3]It will go to Cabinet and the forward plan [P3]
Who it affectsCouncil services and local communities [P124]Spending is compared with the February 2011 budget [P124]
What was decided
Cabinet noted the 2011/12 general fund outturn forecast and the forecast net movement in reserves. Report P2
Cabinet noted the housing revenue account outturn forecast, resulting reserve movement and treasury management activity. Report P2
Cabinet noted council tax and business rates collection fund performance and approved the general fund budget movements in Appendix A. Report P3, P4, P128
Why
The forecast was based on experience to date and knowledge at the end of quarter 2, while work continued to secure a balanced year end position [P6]. Report P6
The general fund variance improved from quarter 1 and the same period in 2010/11, but remained £2.6m unfavourable [P22]. Report P22
The collection fund was forecast to have a £65k surplus, although the effect of moving the service in house could not yet be quantified [P114]. Report P114
What happens next
A report on collection service performance since it moved in house will go to Cabinet and the forward plan [D] [P3]. Report P3
Work will continue to mitigate the projected £2.6m variance, using contingency if it crystallises at year end [P26]. Report P26
Remaining 2011/12 agency workers directive costs will enter quarter 3 forecasts, and further council tax collection information will enter the Q3 revenue monitoring report [P25] [P100]. Report P25, P100
The money
£2.6m Forecast general fund services variance. Report P22
£5.5m Contingency held for unforeseen departmental costs. Report P70
£2.5m Projected savings shortfall at quarter 2. Report P78
£56.2m Agreed budget reductions for 2011/12. Report P78
£65k Forecast collection fund surplus. Report P114
£3.363m Planned release of reserves assumed in full. Report P109
£762m Long term debt held throughout two quarters. Report P121
£274m Proposed reduction in Southwark housing debt. Report P121
Options considered
Chosen: Use contingency if the projected general fund variance crystallises. Contingency was held for unforeseen costs that strategic directors could not contain. Report P26, P70
Chosen: Use any unused contingency before reserves to bridge a remaining funding gap. The report assumes the full planned reserve release, with unused contingency used first for any gap. Report P109
Chosen: Manage the customer services savings shortfall corporatively. The £1.5m savings shortfall was addressed corporately and reflected in the quarter 2 forecast. Report P68, P102
Rejected: Increase court costs this year. Alternative savings will come from a higher housing benefit subsidy and greater efficiencies since the service moved in house on 1 April. Report P100
Chosen: Substitute other savings if finance and resources savings cannot be fully met. Substitution options will ensure the overall target is achieved. Report P67
Chosen: Compensate environment and leisure pressures with one off savings. Most identified pressures are expected to be offset by compensatory one off savings. Report P47
Chosen: Seek reserve support where a department cannot contain an additional pressure. Departments must show they cannot contain the pressure, and Cabinet approval is required at £250k or above. Report P107
Chosen: Mitigate care savings pressure through vacancy holds, agency limits and better procurement. The action plan includes closer care payment review, better procurement, vacancy holds and lower agency use. Report P91, P92
Implications
Financial: The general fund forecast was £2.6m unfavourable, and the £5.5m contingency may be needed if the pressure remains at year end [P22] [P26] [P70]. Report P22, P26, P70
Financial: At quarter 2, agreed savings had a projected £2.5m shortfall against £56.2m of reductions [P78]. Report P78
Financial: The HRA forecast was broadly neutral, but maintenance and improvement of the housing stock created spending pressure [P72]. Report P72
Risk: Unused contingency would bridge any remaining gap first, and a £3.363m reserve release was assumed in full [P109]. Report P109
Legal: Agency workers would gain the same terms and conditions as permanent employees after 12 weeks, with costs to be confirmed and future budgets updated [P24] [P25]. Report P24, P25
Staffing: Restructuring led to redundancies, including at Southwark Building Services, with a management structure review due in quarter 3 [P13]. Report P13
Financial: Proposals to make housing self funding would reduce Southwark housing debt by some £274m, but would require the HRA to meet future interest and running costs from its own resources [P121]. Report P121
Other: The report was judged to have no or very small impact on local people and communities [P124]. Report P124
Who and where
Council tax payers Report P114
Housing tenants and leaseholders Report P11, P104
Pupils with special educational needs using bus and taxi transport Report P35
Unaccompanied asylum seeking children Report P32
Families with no recourse to public funds Report P31
People using Holmhurst Day Centre for Older People Report P44
Council staff and agency workers Report P13, P24
Small businesses physically affected by public disorder Report P23
Timeline
15 February 2011: Cabinet agreed a balanced HRA budget. Report P11
22 February 2011: The council agreed a balanced general fund budget. Report P7
1 April 2011: The revenue and benefits service moved in house. Report P114
1 September 2011: The housing services restructure was implemented, and Southwark Building Services management was brought in house. Report P12, P13
1 October 2011: The European Union agency workers directive took effect. Report P24
10 November 2011: The final report was dated. Report P130
quarter 3: Southwark Building Services management structure was due for review. Report P13
towards the end of March 2012: Housing debt was expected to reduce under government proposals. Report P121
Plain English for the jargon
Outturn: Forecast final spending for the financial year [P6].
Collection fund: Account for rates and council tax transactions and their distribution [P113].
Treasury management: Council cash and debt balances [P116].
Contingency: Budget for unforeseen costs within departments [P70].
Earmarked reserves: Funds for unpredictable spending outside revenue budgets and capital programmes [P106].
Housing revenue account: Council housing account covering services and landlord responsibilities [P72].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the following be noted: · the general fund outturn forecast for 2011/12 and the forecast net movement in reserves; · the housing revenue account’s (HRA) forecast outturn for 2011/12 and resulting forecast movement in reserves; · the treasury management activity for the second quarter of 2011/12. 2. That the forecast performance for the council tax and business rates collection fund be noted, and that it also be noted that a report will be brought to cabinet on the performance of the service since moving it in-house. 3. That the general fund budget movements as shown in Appendix A of the report be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendations
1. That the cabinet notes:
• the general fund outturn forecast for 2011/12 and the forecast net movement in reserves; • the housing revenue account’s (HRA) forecast outturn for 2011/12 and resulting forecast movement in reserves; • the treasury management activity for the first quarter of 2011/12.
2. That the cabinet notes the forecast performance for the Council Tax and Business Rates collection fund, and that a report will be brought to cabinet and put on the forward plan on the performance of the service since moving it in- house.
3. The cabinet approves the general fund budget movements as shown in Appendix A. BACKGROUND INFORMATION
General fund
4. The purpose of this report is to provide a forecast for the end of the financial year 2011/12, using predictions based on the experience to date and knowledge as at the end of quarter 2. Work continues throughout the council to ensure that a balanced position is achieved by the end of the year.
5. The council agreed a balanced budget of £321m on 22 February 2011 based on a nil council tax increase. This budget was set in the context of significant overall cuts in government funding. It required the identification of some 25% of savings proposals over the three years from 2011/12 to 2013/14, to mitigate against the reduction in resources and to continue to fund the council’s commitments in terms of services provided. The budget plan recognised a number of key commitments and cost pressures.
6. When setting the council budget there were a number of budget proposals that would impact across the entire council and are of cross-organisational significance. These included the cost of pension provision, changes in employer national insurance costs (specifically as a result of the government’s emergency budget), and contingency provision to mitigate against future, as yet unknown, budget pressures. In 2011/12 the council proposed to set aside some £9.4m to cover such costs. The indicative allocations for 2012/13 and 2013/14 are £4.7m and £4.8m respectively.
7. The council approved budget decisions including agreed budget reductions of some £33.8m within general fund and a further £22.4m within the housing revenue account for 2011/12. Performance on achieving these savings is closely monitored and details are provided in paragraphs 48 to 55 below.
Housing revenue account
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.