Livesey Museum Update and Options

Decided Executive 2 papers

AI summaryCabinet agrees to negotiate with Treasure House and Igmusic as the two leading bids for the Livesey building, subject to financial and Charity Commission checks, with a further report due in April 2012.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTreasure House CIC and Igmusic Ltd to be negotiated with
Money£250,000+ repairs neededAnnual running cost about £8k currently
What happens nextReport back to Cabinet in April 2012After second round of checks in January 2012
Who it affectsResidents of former Parish of CamberwellIncluding Peckham and Camberwell communities

What was decided

Officers are to progress negotiations with Treasure House (London) CIC and Igmusic Ltd, the two viable bids from the expressions of interest process, provided each meets the trust's educational or cultural objectives and passes a second round of financial and organisational checks. Report P1, P2, P3, P4, P45

The preferred user must enter a full repairing lease and demonstrate secure revenue and capital funding arrangements. Report P3, P47, P68

Officers will report back to Cabinet in April 2012 on the outcome of negotiations and on the Charity Commission discussions. Report P5, P48

Why

The council, as trustee, must find an appropriate use for the building and remedy a long-standing breach of trust, as the building has not been used as a public free library since 1966. Report P7, P8, P12, P55

Three expressions of interest were assessed, with Treasure House scoring 56% and Igmusic 55%, both considered able to meet the trust's objects, while People Empowering People scored 28% and did not meet the criteria. Report P25, P26, P27, P35, P40, P44, P45

The Charity Commission has indicated that widening the trust's objects to include broader educational benefit would be acceptable, but a cy-pres scheme and its consent are still required. Report P9, P55, P56, P57

What happens next

Detailed financial and organisational checks on the two bidders in January 2012. Report P4, P5

Re-start negotiations with the Charity Commission on the cy-pres scheme to amend the trust's objects. Report P56, P58, P62

Cabinet to receive a further report in April 2012 covering negotiations, financial risk assessment and any council implications. Report P5, P21, P48

The money

  • about £8k Annual running cost on the building currently borne by Environment and Leisure Department Report P47
  • over £250,000 Cost of works identified in 2008 condition report to maintain the grade II listed building Report P68

Options considered

  • Chosen: Treasure House (London) CIC. Scored 56% overall, judged to meet the trust's educational objects and presented the strongest financial offer, though reliant on grant funding Report P31, P32, P33, P34, P35, P36, P45
  • Chosen: Igmusic Ltd. Scored 55% overall with the strongest educational and cultural offer at 59%, though business planning and capital funding risks were identified Report P37, P38, P39, P40, P45
  • Rejected: People Empowering People Ltd. Scored 28% overall with weak business plan and a proposal that did not meet the library, educational or cultural objects of the trust Report P41, P42, P43, P44

Implications

  • Legal: The council has been in breach of the trust since 1966 when it stopped using the building as a library; a cy-pres scheme and Charity Commission consent are required before any transfer or change of use. Report P12, P55, P56, P57, P58
  • Financial: The division holds no capital or revenue budget for the Livesey; the preferred user must fund capital works via a full repairing lease, and any resulting budget pressures must be contained within Environment and Leisure. Report P47, P65, P68
  • Risk: Both shortlisted bidders carry financial risk; neither has capital funding immediately in place and both depend on grant income during a recession. Report P36, P40, P45
  • Governance: If the building reopens, a management committee with non-conflicted members is likely to be required to address conflicts of interest of the council as trustee. Report P59, P60, P61
  • Staffing: Officer time to deliver the recommendations will be contained within existing budgeted revenue resources. Report P65
  • Other: Significant capital expenditure is likely needed on a grade II listed building to make it secure and compliant before reopening. Report P68

Who and where

  • Residents of the former Parish of Camberwell, including Peckham and Camberwell communities Report P8, P22, P50, P51
  • Treasure House (London) CIC Report P31, P32, P45
  • Igmusic Ltd Report P37, P45
  • People Empowering People Ltd Report P41, P44
  • Live-in guardians currently occupying the building under the Guardian scheme Report P20, P67
  • Schools and community groups that work with the two shortlisted bidders Report P33, P34, P38, P39

Timeline

  • 1890: George Livesey bequeathed the building as a free public library for the Parish of Camberwell Report P7, P8
  • 1966: Council relocated library provision; the building ceased to be used as a library Report P12
  • 1974: Building reopened as a Museum for Children, putting the council in breach of the trust Report P12
  • February 2008: Council decided to close the Livesey Museum alongside other service reductions Report P10
  • September 2008: Consultation plan approved for finding potential users Report P14
  • May 2010: Theatre Peckham withdrew its proposal after raising funding concerns Report P15, P16, P17
  • June 2011: Officers instructed to open a formal call for expressions of interest for a long-term user Report P21
  • 30th September 2011: Deadline for expressions of interest; three eligible proposals received Report P21, P24, P25
  • October 2011: Proposals assessed and Treasure House and Igmusic identified as the two leading bids Report P27, P45
  • January 2012: Second round of financial and organisational checks on the two bidders Report P4, P5
  • 27 January 2012: Final report version dated Report P72
  • April 2012: Officers to report back to Cabinet on negotiations and Charity Commission discussions Report P5, P21, P48

Plain English for the jargon

  • Cy-pres scheme: A scheme approved by the Charity Commission or High Court to alter a charity's objectives so they remain as close as possible to the original purposes.
  • Objects of the Trust: The original purposes of the Livesey trust, principally the provision of a free public library for the Parish of Camberwell.
  • Expression of Interest (EOI): A formal invitation for organisations to submit proposals for a long-term use of the building.
  • Community Interest Company (CIC): A type of limited company set up to deliver community benefit, used by Treasure House (London).
  • Full repairing and insuring lease: A lease where the tenant is responsible for all repairs, maintenance and insurance of the building.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That officers be instructed to progress negotiations with the two leading bids for the Livesey building within the Objects of the Trust, as identified by the call for expressions of interest and subsequent assessment in October 2011, to ensure that bids meet with the requirements set out below: · Meet the original objectives of the trust, i.e. a free public library, or any other objectives of an educational or cultural nature, in keeping with the proposed amended charitable objectives · Are financially viable with secure and robust revenue arrangements as well as funding for any associated capital works that schemes may require · Are proven robust in the second round of financial assessment and organisation checks in March 2012. 2. That subject to a satisfactory outcome of detailed checks in January 2012, officers report back to cabinet on the outcomes of the negotiations with the preferred user and Charity Commission in April 2012.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 9 pages

Recommendations

1. That officers be instructed to progress negotiations with an end user for the Livesey building within the Objects of the Trust, as identified by the call for expressions of interest and subsequent assessment in October 2011, with the requirements that:

• The end user’s proposal must meet the original objectives of the trust, i.e. a free public library, or any other objectives of an educational or cultural nature, in keeping with the proposed amended charitable objectives.

• The end user’s proposals must be financially viable with secure and robust revenue arrangements as well as funding for any associated capital works that schemes may require.

• The end user’s proposal is subject to second round of financial assessment and organisation checks in January 2012.

2. That, subject to a satisfactory outcome of detailed checks in January 2012, officers report back to Cabinet on the outcomes of the negotiations with the preferred user and Charity Commission in April 2012.

BACKGROUND INFORMATION

3. The London Borough of Southwark is the trustee of the building on the Old Kent Road now known as the Livesey Museum for Children. The museum was bequeathed by George Livesey, a local benefactor, to the Commissioners for

1 Public Libraries and Museums for the Parish of Camberwell in 1890 as a free public library for the beneficiaries of the trust. The conveyance states that “the said commissioners shall hold the said hereditaments and premises upon trust to permit the same to be used for the purposes of a Public Free Library for the benefit of and by the ratepayers, inhabitants and residents of the Parish of Camberwell”. Southwark became the legal owner and trustee of the building by means of statutory devolution. The trust did not provide any revenue support for the running of the library. The beneficiaries are within the original geographical boundary of the Parish of Camberwell which includes the area known both now and at the time as Peckham, and is considerably larger than the area now known as Camberwell.

4. The Charity Commission has indicated that it is acceptable to extend the Objects of the Trust to include a broader educational benefit.

5. During budget setting in February 2008, the Council took the decision to close the Livesey Museum for children alongside a series of other service reductions.

6. The Council, as trustee of the building is obliged to find an appropriate use for the assets of the trust, which are the land and the buildings of the “Livesey” site at 682 Old Kent Road.

7. The Council relocated its library provision to a nearby site in 1966 and the building closed to the public. The use of the building then changed from a public library to a Museum for Children when it reopened in 1974. At this stage, the Council became in breach of the trust conditions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Livesey Museum Update and OptionsReport 9 pages DownloadRead as text
PDF
Revised recommendationReport 2 pages Download

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Livesey Museum Update and OptionsThis decision
  2. Livesey Museum update and optionsDecided
  3. Future of Livesey MuseumAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies