Combined Gateway 1 Procurement Strategy Approval and Gateway 2 Contract Award for Integrated Highways Term Contract
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approves nine month extension of highways maintenance contract with FM Conway from 1 July 2012 to 31 March 2013, awarded by single supplier negotiation.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSingle supplier award to FM Conway Ltd
MoneyNot disclosed in open reportCost given in separate closed report
What happens nextNew long-term contract procurementTo be completed before 31 March 2013
Who it affectsAll borough road usersBorough-wide highways maintenance service
What was decided
Cabinet approved the procurement strategy of single supplier negotiation with the current contractor under Contract Standing Orders 4.4.3. Report P1
Cabinet approved the award of a nine month contract to FM Conway Ltd, taking effect as a variation to the existing contract and running from 1 July 2012 to 31 March 2013. Report P2
Why
The current highways maintenance contract expires on 30 June 2012 and a longer term procurement is in progress elsewhere on the agenda, so end dates need to be realigned to 31 March 2013 to allow consolidation. Report P9, P11
Officers considered tendering a short term contract, using an existing framework, or bringing the service in-house, but found all alternatives impractical; only the incumbent can deliver at acceptable cost and standards for such a short period. Report P13, P16, P17, P32
What happens next
Run a full procurement for a new long-term integrated highways contract, to be awarded before 31 March 2013, in parallel with a similar London-wide LoHAC procurement. Report P11, P56, P78
Continue monitoring FM Conway against seven KPIs through weekly operational meetings, monthly strategic meetings and an annual contract review. Report P42, P43, P46
Options considered
Rejected: Tender a short term contract. Still subject to OJEU process, high officer costs, unlikely to attract a proven contractor, and would produce high unit rates over nine months Report P16
Rejected: Use an existing framework arrangement. Market research found no viable frameworks operated by local authorities Report P16
Rejected: Bring the service in-house. Would require short term plant hire, skilled labour and professionals Report P17
Chosen: Extend the current contract with FM Conway by nine months. Most economically advantageous; specialist service cannot be provided by another provider at lower cost for such a short period while maintaining standards Report P13, P19, P34
Implications
Legal: Award is given legal effect by formal variation of the existing contract with FM Conway Ltd; required to meet Highway Authority duty to keep the network safe under Highways Act 1980 Section 41. Report P2, P63, P71
Financial: Capital and revenue budgetary provision exists to support the contract variation; the variation does not commit the council to a minimum level of expenditure. Report P62, P73
Equalities: The borough-wide service affects all communities, groups, residents and visitors, with direct benefits to quality of life and safety of all highway users. Report P49, P50
Climate: FM Conway recycles all highway arisings and gully waste through its Dartford plant and has used over 32,000 tonnes of recycled materials on Southwark works since July 2010. Report P53, P54
Risk: Urgency: any slippage in approving this report would delay the OJEU notice for the long-term procurement and put the new contract start date of 1 April 2013 at risk, with no alternative provision for emergency reactive maintenance. Report P83
Staffing: No additional staffing implications as it is a supply contract within current working arrangements; TUPE not applicable. Report P38, P60
Who and where
All borough residents, groups, communities and visitors using the road network Report P49
Highway users benefitting from inspections, maintenance, drainage, structures and winter service Report P5
FM Conway Ltd as the continuing contractor Report P2, P23
Timeline
May 2005: Executive approved original award of Integrated Highway Maintenance Term Contract to FM Conway for five years from 1 July 2005 Report P6
June 2010: Finance Director approved two year extension to 30 June 2012 Report P7
1 July 2012: New nine month contract period begins Report P2, P21
31 March 2013: Interim contract ends; new long-term contract expected to commence 1 April 2013 Report P11, P21
Plain English for the jargon
Gateway 1: Procurement strategy approval stage in the council's project review process
Gateway 2: Contract award approval stage in the council's project review process
CSO 4.4.3: Contract Standing Order rule permitting single supplier negotiation with the current contractor
OJEU: Official Journal of the European Union, used to advertise public sector tenders above threshold values
LoHAC: London Highways Alliance of Contractors, a pan-London highways procurement arrangement
KPI: Key Performance Indicator, used to measure contractor performance
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
That the procurement strategy outlined in the report for the integrated highways term maintenance contract of entering into a single supplier negotiation with the current contractor in line with contract standing orders (CSO 4.4.3) be approved. 2. That the award of a contract to FM Conway Ltd (“FM Conway”) for a period of nine months at an estimated cost as reported in the separate closed version of this gateway report be approved. The award will be effected by way of a variation to the existing contract. The new contract period will therefore run from 1 July 2012 to 31 March 2013.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 9 pages
Recommendations
1. That the Cabinet approves the procurement strategy outlined in this report for the Integrated Highways Term Maintenance Contract of entering into a single supplier negotiation with the current contractor in line with Contract Standing Orders (CSO 4.4.3).
2. That the Cabinet approves the award of a contract to FM Conway Ltd (“FM Conway”) for a period of nine months at an estimated cost as reported in the separate closed version of this gateway report. The award will be effected by way of a variation to the existing contract. The new contract period will therefore run from 1 July 2012 to 31 March 2013.
BACKGROUND INFORMATION
3. Currently the Council procures repairs and alterations to the Borough road network through its highways maintenance contract with FM Conway as the contractor. The contract provides the following services:
a) Integrated Highways maintenance: Programmed highway inspections and fault reporting Reactive and planned maintenance Highway capital schemes (projects) Programmed gulley inspections, fault reporting and gulley cleansing Reactive and planned drainage works Programmed inspections of structures and fault reporting Reactive and planned maintenance of structures Winter service
1 4. In May 2005 the Executive approved the award of the Integrated Highway Maintenance Term Contract to FM Conway, for a period of five years from 1 July 2005 with an option to extend the contract term for up to two further years subject to reaching performance criteria.
5. In June 2010 the Finance Director approved the contract extension of the Integrated Highways Maintenance Term Contract for a period of two years from 1 July 2010 to 30 June 2012.
Summary of business case/ justifications for the procurement
6. Southwark’s current contractual arrangements for Highways Maintenance will expire in June 2012. Elsewhere on this meeting’s agenda cabinet are being asked to approve the procurement strategy for both its highway’s term maintenance and highway design and professional services and project construction and delivery which provides for a potential consolidation of the current contract areas. In order to achieve this it is necessary to realign the end dates of the existing contacts to 31 March 2013
7. The value of the single supplier negotiation and extension which is reported in the separate closed version of this gateway report is based on the current contract pricing, the current contract price variation mechanism and the expected volume of work based on the average of the last 5 years including in the case of highways maintenance a previously agreed budget reduction.
8. The proposed interim arrangement (9 month award) will allow officers to undertake a full procurement process for a new contract commencing April 2013 which has been detailed elsewhere on this agenda and is the subject of a separate Gateway 1 report elsewhere on this meeting’s agenda.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.