Disposal of Land at Coopers Road, London SE1 (Phase 4)
AgreedExecutive2 papers
AI summarySouthwark Cabinet authorises disposal of the freehold of Coopers Road estate Phase 4 land to Peabody Trust for a 46 home mixed tenure scheme.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFreehold of Phase 4 site to Peabody or associated company
MoneyNot stated in open reportPrice and terms in closed version of report
What happens nextPeabody to seek planning and HCA funding. Planning application expected shortly
Who it affectsCoopers Road estate area in SE1Last phase of estate regeneration begun in 2005
What was decided
Cabinet authorised the head of property to dispose of the council's freehold interest in the Coopers Road estate SE1 (Phase 4) to the Peabody Trust or one of its associated companies on the terms in the closed report. Report P1, P2
The head of property was also authorised to agree any minor variations to the sale terms with Peabody before completion. Report P3
Why
The site has been vacant and hoarded since the former 1960s block of 12 three bedroom maisonettes was demolished in 2008, and earlier disposal attempts, including a 2009 scheme with Wandle housing association, did not proceed. Report P6, P7
Peabody proposes 46 units (154 habitable rooms) over five storeys, made up of 11 affordable rent, 19 shared ownership and 16 private sale homes, with five units for wheelchair users, completing the regeneration of the estate. Report P8, P9, P10
The disposal will deliver affordable housing, remove a visual eyesore and cut anti social behaviour, supporting the council's housing strategy and cleaner, greener, safer agenda. Report P23, P24, P25
What happens next
Peabody to submit a planning application, following further consultation on the detailed design. Report P10, P36
Completion of the sale is subject to planning permission, Homes and Communities Agency grant funding, site and soil surveys, deduction for abnormal costs, and an overage or underage adjustment based on habitable rooms. Report P14, P15, P17
Any planning application arising will go through the usual statutory consultation process. Report P37
The money
£325 Weekly market rent for a 2 bed unit in Peabody's assumed rent table Report P19
£380 Weekly market rent for a 3 bed unit in Peabody's assumed rent table Report P19
£445 Weekly market rent for a 4 bed unit in Peabody's assumed rent table Report P19
Options considered
Chosen: Dispose the site to Peabody Trust on the terms in the closed report. Peabody's offer is considered best consideration reasonably obtainable, supported by a third party valuation, and the scheme delivers affordable housing that previous partner attempts failed to achieve. Report P7, P13, P49
Implications
Financial: A substantial capital receipt will go to the council's housing investment programme; the council will be freed from ongoing management and maintenance costs such as security and flytipping on the cleared site. Report P33, P34, P50, P51
Legal: The site is held in the housing revenue account and is being disposed under Section 32 of the Housing Act 1985, relying on the General Housing Consents 2005, with the Secretary of State's consent obtained where required. Report P13, P40, P41, P42, P43, P44, P45, P46
Equalities: The scheme includes five units for wheelchair users and 23 larger family units, including three bedroom shared ownership homes that are rarely provided. Report P10, P23
Climate: Homes will be designed and built to Code for Sustainable Homes level 4, with investigations continuing into linking to the estate's combined heat and power plant. Report P26
Staffing: Officer time to complete the disposal will be met from existing budgeted revenue resources. Report P51
Who and where
Households in high priority housing need, including those affected by regeneration programmes Report P25
Existing and former residents of the wider Coopers Road estate Report P35
Future residents of the 46 new homes on Phase 4 Report P8, P9
The council, as freeholder and housing revenue account holder Report P13
Timeline
2005: Regeneration of the Coopers Road estate began under the Southwark Estates Initiative Report P5
2008: Former 1960s block on the Phase 4 site demolished Report P6
October 2009: Council's then executive approved disposal terms for the site Report P7
March 2011: Wandle housing association withdrew from its proposed scheme Report P7
Shortly after the decision: Peabody expected to submit a planning application for the 46 home scheme Report P10
Plain English for the jargon
Affordable rent: Rented housing let at up to 80 percent of market rent, replacing social rent in many new developments
HCA: Homes and Communities Agency, the national housing and regeneration agency providing grant funding
Code for Sustainable Homes: National environmental performance rating for new homes, with level 4 indicating a high standard
Section 32, Housing Act 1985: Legal power for a local authority to dispose of land held for housing purposes, with Secretary of State consent where required
Section 106 agreement: A planning obligation under which a developer agrees measures, such as capped rents, as part of a planning consent
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15
Resolved
The head of property be authorised to dispose of the council’s freehold interest in the land at the Coopers Road estate SE1 (the “Site”), as shown and highlighted in bold on the plan at Appendix 1 to the report to the Peabody Trust, or one of their associated companies, on the terms outlined in the closed version of the report. 2. The head of property be authorised to agree any minor variation to the terms of the sale, with the Peabody Trust, which may arise prior to the completion of the transaction.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendations
That Cabinet authorises:
1. The head of property to dispose of the council’s freehold interest in the land at the Coopers Road estate SE1 (the “Site”), as shown and highlighted in bold on the attached plan at Appendix 1 to the Peabody Trust, or one of their associated companies, on the terms outlined in the closed version of this report.
2. The head of property to agree any minor variation to the terms of the sale, with the Peabody Trust, which may arise prior to the completion of the transaction.
BACKGROUND INFORMATION
3. Regeneration of the Coopers Road estate first began in 2005 as part of the Southwark Estates Initiative. It has to date involved the phased replacement of four 1960s blocks with 154 new flats and houses for rent and shared ownership for both Peabody and the council, which retains forty units. The Site, also known as phase 4, remains the last part of the project to be completed. It was originally designated as the private housing for sale site in the original project masterplan.
4. The Site is currently hoarded and cleared. It was formerly occupied by a 1960’s built four storey block containing 12 three bedroom maisonettes. This block was
1 demolished in 2008. Previous attempts to develop this site in conjunction with partner registered providers (RPs) have so far proved unsuccessful. The last and most recent work by Wandle housing association failed to move forward for a number of reasons, not least inadequate funding. The council’s then executive approved the terms for a disposal of the Site in October 2009 but Wandle withdrew from their proposed scheme in March 2011.
5. Peabody have adopted the former proposals first formulated by Wandle and plan to develop a scheme of forty six units comprising one hundred and fifty four habitable rooms arranged over five storeys across a variety of unit types;
1 bed 2 bed 3 bed 4 bed total Affordable Rent 0 3 (3W) 4 (2W) 4 11 Shared Ownership 3 6 10 0 19 Private Sale 8 3 5 0 16
6. The proposal also includes the provision of five units for wheelchair users. The unit mix is for 11 affordable rented units for general needs and 19 units for shared ownership. The private ‘for sale’ units are necessary so that the proposal will comply with the local planning authorities adopted policies found in the core strategy. Wandle had a number of pre application discussions with the planning authority prior to releasing this opportunity for Peabody to pursue. Peabody are confident of submitting an application shortly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.