Gateway 1 - Procurement Strategy Approval: Integrated Highways Maintenance, Project Delivery and Professional Services Contract

Approved Executive 3 papers

AI summarySouthwark Cabinet approves procurement strategy for a new integrated highways contract worth an estimated £11.588m a year, with awards delegated to a Cabinet Member and a twin-track comparison with the London Highways Alliance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStrategy for highways maintenance, project delivery, professional services
Money£11.588m per year, £66.528m over 6 yearsUp to £87.704m with two-year extension; no minimum spend
What happens nextAdvertise contract from 14/03/2012Contract award expected February 2013, start 1 April 2013
Who it affectsHighways service users and contractorsBorough-wide; TUPE may apply to incumbent staff

What was decided

Cabinet approved the procurement strategy covering highway maintenance, design and professional services, project construction and delivery, packaged as three contract elements. Report P2, P62

Cabinet noted the council will simultaneously run its own tender and continue participating in the London Highways Alliance Contract (LoHAC) to identify the most economically advantageous option. Report P3, P51, P138

Cabinet agreed the Gateway 2 award decision will be delegated to the Cabinet Member for Transport, Environment and Recycling, with the Leader asked to formalise the delegation. Report P5

Why

The current contracts with FM Conway and Mouchel need replacing so the council can meet its Highways Act 1980 duty to keep the network safe, manage workload peaks, and access specialist skills. Report P7, P25, P26, P28

Combining the three services into one procurement is expected to reduce overheads and provide better value, while running a parallel comparison with LoHAC preserves flexibility. Report P40, P41, P61, P138

In-house delivery and a shared service with Lambeth and Lewisham were considered and ruled out as premature or cost-prohibitive. Report P33, P37, P38

What happens next

Officers will extend the current FM Conway and Mouchel contracts to 31 March 2013 through separate Gateway decisions to maintain service continuity. Report P29, P42, P43

An OJEU notice will be published on 14 March 2012, with a Pre-Qualifying Questionnaire and a minimum of five bidders invited to tender for each of the three contract elements. Report P50, P82, P109, P123

Tender evaluation will use a 70% price, 30% quality split, with final award recommended at Gateway 2 in early 2013 after comparison with the LoHAC result. Report P122, P138, P85

The money

  • £11.588 million per annum Estimated total annual value of the new contract Report P54, P172
  • £66.528 million Total indicative spend over six years Report P54, P172
  • £87.704 million Total indicative spend over six years plus two-year extension Report P54, P172, P199
  • £350 million Annual value of around 100 London-wide highway contracts Report P21
  • 5% to 15% Potential London-wide savings from collaborative LoHAC procurement Report P21, P81, P135

Options considered

  • Rejected: Procure independently from the market (Option 1). Lacks comparison with LoHAC pricing Report P56, P61
  • Rejected: Join the emerging LoHAC initiative (Option 2). LoHAC outcome and savings cannot be guaranteed in advance Report P57, P61
  • Chosen: Twin-track: tender independently and compare with LoHAC (Option 3). Allows market testing while keeping flexibility to adopt LoHAC if advantageous Report P58, P61, P138
  • Rejected: Joint procurement with another borough (Option 4). Premature while boroughs have differing specifications and funding Report P59, P37
  • Rejected: Internalise the contract (Option 5). Capital and start-up costs, depot, plant and vehicles would be prohibitive Report P60, P33
  • Rejected: Separate function contracts. Higher overheads compared with combined approach Report P65, P66
  • Rejected: One large works contract with separate professional services contract. Misses savings from combining elements Report P65, P66
  • Chosen: Combination of lots across the three elements (Option 3). Allows multi-skilled suppliers and discount mechanism for combined bids Report P65, P66, P68
  • Rejected: Private Finance Initiative. Not appropriate for this scale and type of work Report P65
  • Rejected: Contracts split on a geographical basis. Does not align with proposed service integration Report P65

Implications

  • Financial: The contract will not commit the council to any minimum level of expenditure; indicative annual spend of £11.588m is contained within existing revenue and capital budgets. Report P171, P188
  • Legal: The procurement falls within Strategic Procurement under the council's Contract Standing Orders and must follow the EU procurement regime, with an OJEU notice required. Report P114, P182
  • Legal: TUPE may apply if incumbent contractors are unsuccessful; incumbent will be required to supply TUPE information before tender invitation. Report P87, P88
  • Equalities: Particular attention will be paid to equalities responses at PQQ and tender stage; benefits expected for the elderly, disabled and young children through safer footways. Report P144, P146
  • Climate: The contract will follow the council's Sustainability Policy, recycle highway maintenance debris, and require Environmental Management System certification. Report P148, P149
  • Climate: Contractor equipment must comply with mayoral vehicle emissions policies. Report P159
  • Risk: Fifteen risks identified, including delays to Gateway 1, procurement timetable slippage, contractor failure, and the risk that LoHAC tender results are not disclosed. Report P71, P72, P73, P74
  • Staffing: No additional staffing resources required; training needed for NEC3 contract form for staff supervising and administering the contract. Report P168, P170
  • Other: Compliance with the London Minimum Living Wage will be a contractual requirement. Report P158

Who and where

  • Highway users across the borough, including residents, businesses and visitors Report P146
  • Incumbent contractors FM Conway and Mouchel, whose contracts are being extended to 31 March 2013 Report P7, P29, P42
  • Staff of incumbent contractors, potentially subject to TUPE transfer Report P87, P88
  • Southwark council staff in the Public Realm Division preparing tender documents Report P30, P63
  • Other London boroughs grouped with Southwark in LoHAC Central Area Report P22
  • Local companies and small or medium enterprises, encouraged to bid and use local supply chains Report P95, P96, P152
  • Unemployed residents targeted through Southwark Works and Building London Creating Futures Report P152

Timeline

  • 1 July 2005: FM Conway integrated highway maintenance term contract began Report P9
  • December 2005: Mouchel transport planning and streetscene services contract awarded Report P14
  • July 2009: TfL commissioned project to consider Pan-London collaborative highways procurement Report P18
  • 7 February 2012: Cabinet approval of Gateway 1 procurement strategy report Report P82
  • 14 March 2012: Southwark to advertise the contract via OJEU notice Report P82, P109
  • 20 July 2012: Closing date for return of Southwark tenders Report P85
  • November 2012: LoHAC contract award anticipated Report P85, P139
  • December 2012: DCRB/CCRB/CMT review of Gateway 2 contract award report Report P85
  • January 2013: Approval of Gateway 2 contract award report Report P85
  • February 2013: Contract award following Alcatel standstill period Report P85
  • 31 March 2013: End of current FM Conway and Mouchel contracts (after realignment) Report P29, P42, P85
  • 1 April 2013: New contract start date Report P29, P85
  • 31 March 2019: Initial six-year contract completion date Report P85
  • 31 March 2021: Contract completion date after possible two-year extension Report P85

Plain English for the jargon

  • LoHAC: London Highway Alliance Contract, a pan-London collaborative procurement of highways maintenance and improvement works led by Transport for London.
  • OJEU: Official Journal of the European Union, where public contracts above certain thresholds must be advertised.
  • NEC3: New Engineering Contract, third edition, the form of contract chosen for the integrated highways contract.
  • Gateway 1 / Gateway 2 / Gateway 3: Stages of Southwark's procurement approval process covering strategy, contract award and contract variation.
  • PQQ: Pre-Qualifying Questionnaire, used to assess suitability of bidders before invitation to tender.
  • KPI: Key Performance Indicator, used to measure and manage contract performance.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, which may transfer staff to a new contractor.
  • TfL: Transport for London.
  • LoTAG: London Technical Advisers Group.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

That the procurement strategy outlined in the report for highway maintenance, design and professional services, project construction and delivery be approved. 2. That it be noted that at the same time as seeking tenders for services, the council continues to participate in the London Highway Alliance Contract (LoHAC) procurement process in order to identify the most economically advantageous option. 3. That the Gateway 2 decision for award of contract be agreed by cabinet.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 20 pages

Recommendations

Recommendations for the Cabinet

1. That Cabinet approve the procurement strategy outlined in this report for highway maintenance; design and professional services, project construction and delivery.

2. That Cabinet notes that at the same time as seeking tenders for services the Council continues to participate in the London Highway Alliance Contract (LoHAC) procurement process in order to identify the most economically advantageous option.

Recommendation for the Leader of the Council:

3. That the Leader of the Council delegates authority to the Cabinet Member for Transport, Environment and Recycling to approve the Gateway 2 decision for award of contract.

BACKGROUND INFORMATION

4. The Council currently procures services for the maintenance, improvement design and construction of highways through two contracts, namely; the integrated highway maintenance contract with FM Conway as the term contractor and Transport Planning and Streetscene Services contract with Mouchel plc as the service provider.

1 Integrated highways term maintenance contract

5. In May 2005 the Executive approved the award of the Integrated Highway Maintenance Term Contract to FM Conway, for a period of five years from 1 July 2005 with an option to extend the contract term for up to two further years subject to reaching performance criteria.

6. In June 2010 the Finance Director approved the contract extension of the Integrated Highways Maintenance Term Contract for a period of two years from 1 July 2010 to 30 June 2012.

7. The scope of the services included within this contract include;-

• Programmed highway inspections and fault reporting • Reactive and planned maintenance • Highway capital schemes (projects) • Programmed gulley inspections, fault reporting and gulley cleansing • Reactive and planned drainage works • Programmed inspections of structures and fault reporting • Reactive and planned maintenance of structures • Winter service

Transport planning and streetscene services contract

8. In December 2005 the Executive approved the award of the Transport Planning and Streetscene Services contract to Mouchel Parkman Ltd (now the Mouchel Group plc) for an initial period of 5 years 3 months expiring on 2 April 2011. The contract was extended by Gateway 3 approved in January 2011, for a further period to 30 June 2012.

9. The contract delivers professional services to the Environment & Leisure and Deputy Chief Executive’s [formerly Regeneration and Neighbourhoods] departments. The work is substantially in transport planning, traffic and highway engineering and related services.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Evaluation summary of procurement optionsAppendix 1 3 pages Download
PDF
Evaluation summary of contract optionsAppendix 2 3 pages Download
PDF
Report: Gateway 1: Procurement Strategy Approval: Integrated Highways: Maintenance, Project and Professional Services ContractReport 20 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval: Integrated Highways Maintenance, Project Delivery and Professional Services ContractThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies