Approval to Enter Grant Agreement with the GLA for the Gateway to Peckham Project
AgreedExecutive1 paper
AI summaryCabinet agrees in principle to a £5.25m GLA grant agreement for the Gateway to Peckham project, a four year regeneration scheme around Peckham Rye Station with a total cost of £10.6m.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTo enter GLA grant agreement
Money£5.25m from GLATotal project cost £10.6m
What happens nextDetailed terms to be approvedBy strategic director of communities, law & governance
Who it affectsPeckham Rye Station and surroundsLocal businesses and residents
What was decided
Cabinet agreed in principle to enter a grant agreement with the Greater London Authority for the Gateway to Peckham project. Report P2
The strategic director of communities, law & governance, in consultation with the deputy chief executive, was authorised to approve the detailed terms and conditions of the grant agreement. Report P2
Why
The GLA bid was successful and the GLA will support the project with a £5.25m grant, forming a four year partnership with Network Rail and the council. Report P12, P25
The project is intended to be the centrepiece of regeneration in Peckham, delivering around 90 new jobs, 280sqm of new and 3,200sqm of improved commercial space, and supporting the 2,000 homes, 8,000sqm of business space and 1,500sqm of retail space identified in the Peckham and Nunhead Area Action Plan. Report P5, P7, P11
The scheme is consistent with the council's economic development strategy and the policies of the Peckham and Nunhead Area Action Plan, and 86% of respondents in earlier consultation supported a new square in front of Peckham Rye Station. Report P19, P26
What happens next
The strategic director of communities, law & governance will review the grant agreement from the GLA to protect the council's interests before final terms are approved. Report P30
The council will provide the GLA with quarterly updates on financial and output data, collecting the information monthly, and produce an annual monitoring report. Report P16, P23
A programme of consultation and relocation will be carried out with affected businesses in the station arcade and the light industrial area to the rear of the station. Report P21, P27
The money
£5.25m GLA grant towards the Gateway to Peckham project Report P12, P17
£10.6m Total project cost, comprising £5.25m GLA, £5.07m council and £0.35m future Lip funding Report P17
£5.07m Council match funding committed by entering the grant agreement Report P17
£0.35m Funding from future Lip funding allocations Report P17
Options considered
Chosen: Enter into the grant agreement with the GLA and deliver the Gateway to Peckham project. The GLA bid was successful and the project is central to delivering the Peckham and Nunhead Area Action Plan and the council's economic development strategy. Report P2, P5, P12, P19
Implications
Financial: The council commits to £5.07m of match funding and £0.35m from future Lip funding, against total project cost of £10.6m, with capital budget already included in the capital programme. Report P17, P34
Legal: The grant agreement will be reviewed by the strategic director of communities, law & governance to ensure the council's interests are protected; the decision is a matter for cabinet under the council's constitution. Report P30, P31
Equalities: The project is expected to have a positive impact on all Southwark residents, with ongoing monitoring to ensure no adverse community implications and to minimise any that arise. Report P22, P23
Risk: The council is committing to deliver the project and its constituent components once the grant agreement is signed, and must meet quarterly monitoring and reporting requirements. Report P14, P16
Other: Local businesses in the station arcade and light industrial area will be affected and a relocation programme is planned, with support from existing council business support programmes. Report P21
Who and where
Local businesses in the station arcade and light industrial area to the rear of Peckham Rye Station, who will need to be relocated Report P21
Southwark residents in Peckham, who are expected to benefit from improved public realm and town centre trade Report P11, P22
Network Rail, working with the council as joint project board partner Report P25
Future users of Peckham Rye Station, including passengers using the planned London Overground service Report P6
Timeline
December 2011: Council sought funding through the Mayor's Regeneration Fund for improvements to and around Peckham Rye Station Report P4
4 April 2012: Final version of the report completed and sent to the Constitutional Team Report P40
December 2012: Planned introduction of London Overground service through Peckham Rye, expanding travel opportunities Report P6
Four year period from agreement: Project to be delivered in three phases, starting with internal station works, then forecourt square, then light industrial relocation Report P8, P9, P10
Plain English for the jargon
GLA: Greater London Authority, the regional government body for London providing the grant.
PNAAP: Peckham and Nunhead Area Action Plan, the council's adopted planning framework for the area.
Lip funding: Local Implementation Plan funding, a transport-related funding stream.
SDCLG: Strategic Director of Communities, Law & Governance, the senior officer authorised to approve the grant agreement terms.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That it be agreed in principle to enter into a grant agreement with the Greater London Authority for the Gateway to Peckham project and the strategic director of communities, law & governance be authorised in consultation with the deputy chief executive to approve the detailed terms and conditions of the grant agreement.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 5 pages
Recommendation
That cabinet
1. Agree in principle to enter into a grant agreement with the Greater London Authority for the Gateway to Peckham project and authorise the strategic director of communities, law & governance, in consultation with the deputy chief executive, to approve the detailed terms and conditions of the grant agreement.
1 BACKGROUND INFORMATION
2. In December 2011, the council sought funding through the Mayor’s Regeneration Fund for improvements to and around Peckham Rye Station. The project will deliver an attractive point of arrival forming an anchor in the middle of the town centre, bringing redundant space back into use, creating new job opportunities.
3. The project will be the centrepiece of the regeneration programme in Peckham and be a catalyst for further investment leading to the achievement of the vision in the Peckham and Nunhead Area Action Plan (PNAAP).
4. Peckham Rye Station is a strategic rail interchange but has historically failed to live up to the opportunity this creates. Being only 10 minutes from London Bridge and 13 minutes to London Victoria, Peckham is one of the best connected transport nodes in the borough. This will be further expanded with the introduction of the London Overground service in December 2012 creating new travel opportunities to services to the growing area of East London and with a change at Canada Water being only 13 minutes from Canary Wharf. Peckham Rye Station being equidistant from key London termini, activity areas and employment zones makes Peckham a key gateway to London.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.