Gateway 1 - Procurement Strategy Approval - Lift Maintenance and Repairs Contract

Approved Executive 1 paper

AI summarySouthwark Cabinet approves procurement strategy to retender lift maintenance and repairs as two geographical contracts, with total estimated value of £8,129,373.00 over five years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo contracts, north and south of borough
Money£8,129,373.00 estimated totalAcross 5 year term and 2 year extension
What happens nextEU tender processContracts to start 1 October 2013
Who it affectsCouncil tenants and leaseholdersResidents in blocks with passenger and disability lifts

What was decided

Cabinet approved the procurement strategy for two lift maintenance contracts, A (north, annual £696,803.40) and B (south, annual £464,535.60), for 5 years from 1 October 2013 with potential 2 twelve-month extensions, total estimated value £8,129,373.00. Report P2

Cabinet noted the geographical split is to ensure efficient service delivery and provide backup if one contractor defaults. Report P3, P16

Procurement will use the EU Restricted Procedure, with tenders evaluated at 70:30 price to quality under the Most Economical Advantageous Tender protocol. Report P29, P30, P33, P73

Why

The current contract with Liftec Lifts Ltd expires on 1 January 2013 and needs replacing to maintain essential lift services in council housing. Report P8, P11, P21

The council has a statutory duty, as landlord and employer, to provide step-free access in residential buildings. Report P22, P34, P56

Retendering to two separate contractors limits the risk exposure that exists under the current single source arrangement. Report P16, P23

What happens next

Following Gateway 1 approval, the council will issue a Notice of Intention by 14 May 2012, complete tender documentation by 26 June 2012, and advertise the contract in OJEU on 12 July 2012. Report P60, P69

Tender returns are due 4 December 2012, evaluation completes 19 February 2013, and a Gateway 2 contract award report goes to Cabinet on 14 June 2013. Report P60, P61

Contracts are scheduled to be awarded on 12 July 2013 and to start on 1 October 2013, running to 30 September 2018. Report P62

The money

  • £696,803.40 Estimated annual cost of Contract A (north of borough) Report P2, P17
  • £464,535.60 Estimated annual cost of Contract B (south of borough) Report P2, P17
  • £1,161,339.00 Current annual budget for the whole lift contract Report P17, P95
  • £5,806,695.00 Total cost for the 5 year term Report P19
  • £2,322,678.00 Total cost of the additional 2 year extension term Report P19
  • £8,129,373.00 Total estimated contract value across both contracts and full term Report P2, P18

Options considered

  • Rejected: Do nothing. Council has a statutory obligation to provide step-free access in residential buildings Report P34
  • Rejected: Use an existing framework agreement. No existing or other suitable framework agreements are available for this work Report P35
  • Rejected: Shared services with Greenwich Council. Greenwich is part way through a 10 year partnering deal and contract scope cannot be extended to other boroughs Report P37, P38, P39
  • Rejected: Shared services with Lewisham Council. Lewisham contract value is more than 50% lower and cannot be varied Report P40, P41
  • Rejected: Shared services with Lambeth Council. Lambeth contract is part way through and does not allow other boroughs to join Report P42, P43, P44
  • Rejected: Provide the service in-house. The work is highly specialised and the expertise does not exist within the council Report P45
  • Chosen: Tender two separate contracts via EU Restricted Procedure. Specialist work and high value require full EU tendering; two contractors provide backup and limit single-source risk Report P16, P23, P46

Implications

  • Legal: Council must continue to provide step-free access in residential buildings, in line with statutory duties as landlord and employer. Report P56
  • Financial: The current housing management budget is sufficient to cover the £1,161,339 proposed annual cost for the foreseeable future; officer time will be contained within existing budgeted revenue resources. Report P95, P109
  • Risk: Using two separate contractors reduces the risk if one contractor defaults or fails to perform; identified procurement risks include delays, OJEU challenges, and security for due performance. Report P16, P48, P49, P50, P51, P111
  • Staffing: No impact on council staff; the Engineering and Compliance team will continue ordering and monitoring roles. TUPE is likely to apply for incoming contractors. Report P44, P64, P92
  • Equalities: Lift maintenance supports residents with disabilities and provides step-free access. Contractors must operate an Equal Opportunity Policy compliant with the council's policy, and operative pay exceeds the London Living Wage. Report P22, P41, P85, P86
  • Climate: Contracts will encourage low emission vehicles, planned journeys, reuse of materials, and avoidance of environmentally damaging substances; materials must conform to BS and IS standards. Report P79, P80, P81, P88
  • Other: Leathermarket JMB will be excluded from the new contract and will appoint its own lift contractor on expiry of the existing arrangement. Report P14

Who and where

  • Council tenants and leaseholders in residential blocks across the borough with passenger or disability lifts Report P7, P22, P76, P77
  • Leathermarket JMB, which will be excluded from the future contract and will appoint its own lift contractor Report P14
  • Current contractor Liftec Lifts Ltd, whose contract is due to expire and may be extended by 9 months pending a separate Gateway 3 report Report P8, P11
  • Potential tenderers in the lift maintenance market, including medium to large contractors with social housing experience Report P26, P27, P83

Timeline

  • 5 Apr 2012: Notification of forthcoming decision (five clear working days) Report P60
  • 17 Apr 2012: Approval of Gateway 1 procurement strategy report Report P60
  • 30 Apr 2012: End of scrutiny call-in period and notification of implementation Report P60
  • 14 May 2012: Issue Notice of Intention Report P60
  • 26 Jun 2012: Completion of tender documentation Report P60
  • 12 July 2012: Advertise the contract in OJEU Report P60
  • 3 Sept 2012: Closing date for expressions of interest Report P60
  • 17 Sept 2012: Completion of short-listing of applicants Report P60
  • 19 Sept 2012: Invitation to tender Report P60
  • 4 Dec 2012: Closing date for return of tenders Report P60
  • 19 Feb 2013: Completion of evaluation of tenders Report P60
  • 28 Mar 2013: Issue Notice of Proposal Report P60
  • 14 Jun 2013: Approval of Gateway 2 Contract Award Report Report P61
  • 12 Jul 2013: Contract award Report P62
  • 1 Oct 2013: Contract start Report P2, P62
  • 30 Sept 2018: Contract completion date Report P62

Plain English for the jargon

  • DCRB: Departmental Contracts Review Board, which reviews procurement decisions before they go to Cabinet.
  • CCRB: Corporate Contracts Review Board, a higher-level review body for strategic procurements.
  • OJEU: Official Journal of the European Union, where public contract notices above EU thresholds must be advertised.
  • PQQ: Pre-Qualification Questionnaire, used to shortlist contractors before they are invited to tender.
  • MEAT: Most Economical Advantageous Tender, the EU procurement evaluation approach combining price and quality.
  • CSO: Contract Standing Orders, the council's internal rules governing how contracts must be procured.
  • JCT Measured Term Contract 2011: A standard form of building contract used for ongoing maintenance work over a set period.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, which may transfer staff to a new contractor.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the procurement strategy outlined in the report for the lift maintenance and repairs contracts – Contract A – north of the borough at an estimated annual cost of £696,803.40 and Contract B – south of the borough at an estimated annual cost of £464,535.60, for a period of 5 years from 1 October 2013, with the potential for 2 twelve month extensions, subject to performance, making an estimated contract value of £8,129,373.00 be approved. 2. That it be noted that the rationale behind the geographical division of contract areas is based on the need to ensure efficient delivery of the service.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 12 pages

Recommendations

That the Cabinet:

1. Approves the procurement strategy outlined in this report for the Lift Maintenance and Repairs Contracts – Contract A – north of the borough at an estimated annual cost of £696,803.40 and Contract B – south of the borough at an estimated annual cost of £464,535.60, for a period of 5 years from 1st October 2013, with the potential for 2 twelve month extensions, subject to performance, making an estimated contract value of £8,129,373.00.

2. Notes the rationale behind the geographical division of contract areas is based on the need to ensure efficient delivery of the service.

1 BACKGROUND INFORMATION

3. The current contract delivers essential planned maintenance, repairs and refurbishments of passenger and disability lifts across the borough. The contract is split across the following three contract service areas:

• Area 1 - Bermondsey, Leathermarket JMB, Borough & Bankside and Rotherhithe. • Area 2 - Walworth and Peckham • Area 3 - Camberwell, Peckham Rye and Dulwich

4. The provision of the services is essential for the day-to-day maintenance, repairs and refurbishment of passenger and disability lifts at residential properties owned by the council.

5. A contract for the services is currently in place with Liftec Lifts Ltd (“Liftec”) for all of the above areas and is due to expire on 1st January 2013.

6. Originally, Liftec were only awarded a contract for Area 3, with Areas 1 & 2 being awarded to Apex Lift and Escalator Engineers Ltd (“Apex”) for the same term. The contract term (applicable to both contracts) was 5 years from 2nd January 2008 with the option to extend by a further 24 months, in 12 month increments.

7. After the council determined the contract with Apex, Areas 1 & 2 were transferred to Liftec on the 22nd June 2010.

8. With the addition of Areas 1 and 2, Liftec are contracted to provide the Lift Maintenance and Repair works for the whole borough until 1st January 2013. A separate Gateway 3 Report will be submitted in April 2012 seeking approval to extend Liftec’s contract by a further 9 months until 30th September 2013.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1: Procurement Strategy Approval: Lift Maintenance and Repairs ContractReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval - Lift Maintenance and Repairs ContractThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open