AI summarySouthwark Cabinet approves £17m procurement strategy for buildings insurance covering 12,900 leasehold flats, with new contract from April 2013.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedThree years plus two year extension option
Money£17m estimated totalUp to five years at £3.4m per year
What happens nextNew contract from 1 April 2013Advert in OJEU from June 2012
Who it affects12,900 leasehold propertiesSecond largest council flat portfolio
What was decided
Cabinet approved the procurement strategy for the leasehold and ancillary properties buildings insurance contract, with a potential total estimated value of £17m. Report P2
If tender bids are significantly higher than the current contract price, the option to extend the current contract may be exercised, subject to a separate Gateway 3 report. Report P3
Authority to award the contract is delegated to the cabinet member for housing management. Report P4
Why
The council is required by its lease terms to insure 12,900 flats and maisonettes and must have cover from 1 April 2013 to avoid being in breach of those leases. Report P10, P15
The current broker, Acumus, is an intermediary and the council wants direct relationships with insurers; under the existing arrangement it has no control over renewal pricing. Report P21, P22
The portfolio is the second largest local authority flat portfolio in the country, which should attract international insurers, and leaseholder representatives have been involved in shaping the requirements. Report P17, P18, P26
What happens next
A Section 20 Notice of Intention is to be issued to leaseholders with a 30 day consultation period before the contract is advertised. Report P63, P67
Tenders are to be advertised in OJEU by 6 June 2012, with a return date of 3 August 2012 and evaluation by 31 August 2012. Report P69, P73, P75
Contract award is planned for 23 February 2013, with the new contract starting on 1 April 2013 and running to 31 March 2016. Report P79, P80, P81
The money
£17m Estimated total contract value, including two twelve month extensions Report P2, P14
£3.4m per annum Estimated annual cost of the new contract, including 6% Insurance Premium Tax Report P13
£10.2m Estimated three year contract value, including Insurance Premium Tax Report P13
6% Insurance Premium Tax rate applied to the contract Report P13
Options considered
Chosen: Competitive tender through an EU open procedure. Specialist market but the portfolio size should attract international insurers, with evaluation on a 70:30 price/quality basis Report P22, P33, P35
Fallback only: Extend the current Acumus contract for one year. Council has no control over Acumus pricing and wants direct insurer relationships; only used if tender prices are significantly higher Report P21, P22, P50, P51
Rejected: Self insurance backed by a reserve pool. Would need extra specialist staff and loss adjuster contracts, and the older lease form requires full block cover; exposes the council to greater risk Report P36
Rejected: Joint procurement with other local authorities. Other authorities have different lease terms, stock types and contract expiry dates, and could push up Southwark's premiums Report P23
Rejected: Do nothing. Would place the council in breach of 12,900 leases Report P37
Implications
Financial: Contract cost is fully recovered from leaseholders through annual service charges, including a commission to the council, so there is no effect on the Housing Revenue Account. Report P117, P133, P142
Legal: Lease clause 4(6) requires the council to insure or make other appropriate arrangements, and the Landlord and Tenant Act 1985 requires leaseholders to be consulted. Report P10, P63, P118
Risk: The insurer may include a break clause allowing withdrawal if claims experience is higher than expected, and the global insurance market is forecast to harden, raising premiums. Report P13, P29
Staffing: No additional council resources are needed because the home ownership and TMI division already has a buildings insurance officer and supporting staff. Report P114, P115
Equalities: Tenderers will be asked to submit equal opportunities and diversity policies, which will be evaluated against the council's policies. Report P104
Other: TUPE is likely to apply between the incumbent and the new contractor; due diligence is needed before the tender pack is finalised. Report P83
Who and where
Leaseholders of around 12,900 council sold flats and maisonettes Report P6, P15, P17
Mortgaged housing properties, currently 3 premises Report P7
Leaseholder representatives on the Home Owners Council Report P18, P56, P120
Timeline
15 February 2012: Home Owners Council consulted Report P120
12 March 2012: DCRB, CCRB and CMT review of Gateway 1 Report P67
10 April 2012: Notification of forthcoming decision issued Report P67
17 April 2012: Cabinet approval of Gateway 1 procurement strategy Report P67
2 May 2012: Section 20 Notice of Intention to be issued to leaseholders Report P67
6 June 2012: Contract to be advertised in OJEU and trade journals Report P69
3 August 2012: Closing date for return of tenders Report P73
5 November 2012: Issue Notice of Proposal, or start Gateway 3 process if tender prices too high Report P76
23 February 2013: Contract award Report P79
1 April 2013: New contract starts Report P80
31 March 2016: Initial three year contract ends Report P81
Plain English for the jargon
Gateway 1: Procurement strategy approval stage under the council's gateway review process
Gateway 3: Later gateway stage at which a contract extension decision could be considered
MEAT: Most Economically Advantageous Tender, the basis on which the contract will be awarded
Section 20 Notice: Statutory consultation notice under the Landlord and Tenant Act 1985 served on leaseholders before long term contracts are entered into
OJEU: Official Journal of the European Union, used to advertise public sector tenders above EU thresholds
Acumus: Insurance broker that has held the current leasehold buildings insurance contract since 1 April 2010
TUPE: Transfer of Undertakings (Protection of Employment) regulations that may transfer staff between old and new contractors
HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
Decisions of the Cabinet 1. That the procurement strategy outlined in the report for the leasehold and ancillary properties buildings insurance contract for a period of 3 years, with an option to extend for 2 twelve month extensions, making an estimated contract value of £17m be approved. 2. That it be noted that in the event that tender bids are significantly higher than the current contract price, the option to extend the current contract may be exercised and would form the subject of a separate Gateway 3 report. Decision of the Leader 3. That authority be delegated to the cabinet member for housing management to award the contract for the reasons set out in paragraph 10 of the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendations
Recommendations for the Cabinet
1. That the cabinet approves the procurement strategy outlined in this report for the leasehold and ancillary properties buildings insurance contract for a period of 3 years, with an option to extend for 2 twelve month extensions, making an estimated contract value of £17m.
2. That the cabinet notes in the event that tender bids are significantly higher than the current contract price, the option to extend the current contract may be exercised and would form the subject of a separate Gateway 3 report. Recommendation for the Leader
3. That the Leader of the council delegates authority to the cabinet member for housing management to award the contract for the reasons set out in paragraph 10.
BACKGROUND INFORMATION
4. The leaseholders and ancillary properties buildings insurance contract relates to flats and maisonettes sold by the council under long lease terms. There are (3) separate policies within the contract covering;
• The main policy where flats have been sold (under the Right to Buy scheme or through other disposals e.g. auction sales, social home buy) • A policy to insure under-leased blocks on a comprehensive basis (there are currently 3) • A much smaller policy relating to mortgaged housing properties - currently (3) premises - where the council is still providing a mortgage.
In addition, the council may need to nominate buildings insurers, as per the terms of houses sold on leases.
5. The terms of the current lease requires the council as the freeholder:
Clause 4 (6) “To insure the building to the full insurance value thereof against destruction or damage by fire, tempest, flood and other risks against which it is normal practice to insure, or to make other appropriate and adequate arrangements and in the event of destruction or, damage by any such risk as aforesaid to rebuild or reinstate the property and the building”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.