What was decided
Cabinet noted the general fund capital programme for 2013/14 to 2021/22 and the housing investment programme for 2013/14 and future years, both as at 31 December 2013. These positions are detailed in Appendices A and B. Report P2, P3
Cabinet approved the Quarter 3 virements and variations, the new general fund bids for 2013/14 to 2023/24, and the new housing investment bids for 2013/14 to 2021/22. The changes are set out in Appendices C, D and E. Report P4, P5, P6
Cabinet approved the refreshed programme, set out in Appendices F and H for the general fund and Appendix G for the housing investment programme. Further reprofiling is required as more up to date information becomes available. The Strategic Director must monitor the financial position, coordinate expenditure profiling and explore other funding options if required. Report P7, P8, P9
Why
The programme is large and complex, so unforeseen delays and variations are inevitable. Budgets therefore need to be reprofiled as project timing changes. Report P18, P19, P20, P21, P170, P171
The programme depends on the timing and availability of grants, property disposal income, reserves, contributions and borrowing. Regular monitoring is intended to reduce cash flow and funding risks. Report P28, P29, P30, P31, P32
New bids address identified service and asset needs, including a primary school place shortfall, a gap in adult autism provision, and maintenance of council buildings and IT systems. Report P176, P178, P180, P184, P187, P189
What happens next
The Strategic Director of Finance and Corporate Services will monitor the projected financial position closely and work with strategic directors on capital expenditure profiling. Report P9
The programme will be reviewed for the rest of 2013/14, and the final outturn will be reported to Cabinet. Expenditure and resources will be reprofiled as up to date information becomes available. Report P8, P59, P170, P171
Other funding options will be explored if required so that the capital programme can be sustained over the long term. Report P9
The money
- over £2b Total council capital programme value for 2013/14 to 2023/24 if the new bids are approved Report P18
- £339.6m General fund expenditure budget for 2013/14 to 2021/22 Report P54
- £502.3m Housing investment expenditure budget for 2013/14 and future years Report P55
- £32.48m Housing capital budget increase for sprinkler systems and smoke and heat detection Report P166
- £16m Primary Investment Programme for permanent school places and condition investment Report P175, P178
- £12m Adult Autism Provision education and day services resource Report P179, P184
- £27.5m Preventative Planned Maintenance Programme for the council operational estate Report P186, P187
- £10m IT Planned Maintenance Programme for infrastructure and networking Report P188, P189
Options considered
- Chosen: Approve the refreshed capital programme including the new bids. It combines the updated programme positions with the new capital bids. Report P57, P58
- Chosen: Approve the Quarter 3 virements and variations. Appendix C sets out the budget changes arising in Quarter 3. Report P4, P56
- Chosen: Monitor the projected position and explore other funding options if required. The projected position over the 10 year capital programme needs close management to sustain it over the long term. Report P9
- Chosen: Reprofile expenditure and resources as updated information becomes available. Forecast variations and project delays require changes between financial years. Report P8, P20, P170, P171
Implications
- Financial: The approved programme is valued at over £2b and forms a major part of the council's financial activity. Report P18
- Financial: The 2013/14 forecasts were £74m for general fund spend against a reprofiled £96.8m budget, and £117.9m for housing investment spend against a reprofiled £121.2m budget. Report P24, P26
- Risk: If funding generated by property disposals is insufficient during a year, alternative short term funding may be needed, or projects may be deferred or reprofiled. Report P48
- Risk: Unforeseen delays are likely across the programme, so continued reprofiling is needed. Report P19, P20, P21, P170, P171
- Risk: Warm, Dry and Safe works generally need more resources than survey estimates, and accurate long term forecasting has proved challenging. Report P143, P149
- Equalities: The adult autism bid seeks to close a local gap in education and support for adults with high support needs. Report P180, P181, P183, P184
- Climate: The flood prevention bid is intended to reduce surface water flooding and standing water on highways. Report P201
- Legal: Travellers' Sites spending is difficult to predict while the legal dispute with Network Rail over responsibility continues. Report P138
Who and where
- People who live, learn, visit or do business in Southwark Report P18
- Children needing permanent primary school places Report P176, P177, P178
- Adults aged 19 to 25 with autism and learning difficulties Report P180, P181, P183
- Users of council operational buildings and IT systems Report P187, P189
- Cyclists and pedestrians using roads across the borough Report P194, P195, P199
- Properties at risk of surface water flooding Report P201
- Housing estates included in Warm, Dry and Safe works Report P143, P147, P149
- People using parks and open spaces Report P211, P213, P215
Timeline
- 25 September 2012: Cabinet approved additional general fund bids of £59.9m and a general fund programme of £387.2m for the period up to 2021/22. It also noted housing investment of £397.5m for the period up to 2015/16. Report P16
- 31 December 2013: The report set out reprofiled budgets and forecast outturn positions for 2013/14 and future years. General fund spend was forecast at £74m and housing investment spend at £117.9m. Report P14, P21, P24, P26
- early 2014: An updated capital programme refresh was due to be presented. Report P17
- 2014: The council was working towards a CIL adoption date in this year. Report P36
- mid 2014: The 20mph programme was expected to give all roads under council control a 20mph limit. Report P195
- 2014/15: IT planned maintenance was due to start, and Warm, Dry and Safe work at Aylesbury and Tustin was due to start. Report P147, P189
- 2021/22: The general fund programme and new housing investment bids end in this year. Report P2, P5
- 2023/24: The refreshed general fund programme and the council capital programme period end in this year. Report P5, P18
Plain English for the jargon
- Capital programme: The council's planned capital expenditure, funded from grants, receipts, reserves, contributions and borrowing. [P28][P29][P30][P31][P32][P33]
- Housing Investment Programme (HIP): The housing capital programme, which includes Warm, Dry and Safe works. [P26][P141][P142][P143]
- Capital receipts: Money received from property disposals and used to finance capital expenditure. [P47]
- Reprofiling: Changing the timing of budgets or spending between financial years. [P32][P170]
- Section 106: Planning obligations that can provide funding for the capital programme. [P35]
- Community Infrastructure Levy (CIL): A funding source that may support only qualifying schemes. [P35][P36]
- New Homes Bonus: Uncommitted resources allocated to corporate resources for future capital expenditure. [P38]
- Warm, Dry and Safe: Housing works programme aimed at meeting the WDS standard. [P143]