Gateway 1: Procurement Strategy Approval - Consolidated Repairs and Maintenance Contract for the Council's Operational Estate
ApprovedExecutive3 papers
AI summaryCabinet approved a Crown Commercial Service competition for repairs and maintenance across Southwark's operational estate. [D] The estimated value is £11M initially and £18M with two 12 month extensions, and gateway two award approval is delegated to the strategic director. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFurther competition will use the Crown Commercial Service framework. [P1]
MoneyEstimated value £18M with extensions [D]£3.5M annually, £11M initially, £18M if extensions are used. [D]
What happens nextGateway two award delegated [D]Strategic director of finance and corporate services decides the award. [D]
Who it affectsOperational estate buildings [P12]Circa 217 buildings need the new service. [P12]
What was decided
Cabinet approved further competition using the Crown Commercial Service facilities management framework for the consolidated repairs and maintenance contract. [D] Report P1
Cabinet noted an estimated annual cost of £3.5M and an initial total of £11M over approximately 38 months. The total would be £18M with two 12 month extensions and could rise as more buildings are added. [D] Report P2
The gateway two contract award decision was delegated to the strategic director of finance and corporate services, so the contract can be awarded before the current framework expires. [D] Report P3
Why
The council needed a long term strategy to replace multiple, disparate and outmoded contracts with aligned facilities management contracts as accommodation requirements changed. [P6] Report P6
Buildings differ in age and condition and need maintenance strategies that cannot be accommodated within the existing consolidated facilities management contract pricing. [P18] Report P18
The service aims to provide safe and comfortable working environments, use assets efficiently, extend building and equipment lifespans, and meet statutory health and safety requirements. [P20] Report P20
What happens next
Corporate Facilities Management will contact all eight CCS suppliers for a capability assessment. Suppliers that remain will be invited to tender. [P40] Report P40
Corporate Facilities Management will develop the tender documents with input from corporate procurement, legal and finance. No additional advertising is required for the proposed route. [P56] [P61] Report P56, P61
Corporate Facilities Management will develop the evaluation method with the project board, using a 70/30 price and quality ratio. Before award, the gateway two report will update scope, governance, building budgets and inflation effects. [P30] [P64] [P103] [P104] Report P30, P64, P103, P104
The money
£3.5M Estimated annual cost at award. Report P13
£11M Estimated initial value for approximately 38 months. Report P2
£18M Estimated value if the two 12 month extensions are used. Report P2, P16
£1,000 excluding VAT Reactive repairs and maintenance limit within cost stream one for maintenance strategies A and B. Report P28
approximately 40% Estimated increase in total contract value from adding buildings in other sectors. Report P30
£1m Annual contract expenditure target for one apprentice. Report P78
Options considered
Rejected: Do nothing. Repairs and maintenance would not be provided, building fabric and services could degrade, and buildings could close. Report P36
Rejected: Continue with existing arrangements. The council could not deliver its long term consolidation strategy or replicate the efficiencies achieved through the existing contract. Report P36
Rejected: Undertake EU procurement. It would take longer, require more resources and could reduce the number of bids or increase costs. Report P36
Rejected: Undertake single supplier negotiations with the existing consolidated contract's contractor. It would not demonstrate best value and would create a risk of legal challenge because the estimated value is above the EU threshold. Report P36
Rejected: Join the framework set up by Hammersmith & Fulham, Westminster and the Royal Borough of Kensington & Chelsea. It was still in mobilisation, the market had recently been tested, and it would create two contract management protocols. Report P36
Chosen: Further competition from the CCS facilities management framework. It is the recommended route and offers competition with less time needed to produce tender documentation. Report P36, P38
Implications
Financial: The contract will be funded from existing departmental budgets that transfer as buildings are added. Savings are expected against the current £3.5M annual cost, and CPIX is proposed for annual price reviews. [P85] [P86] Report P85, P86
Legal: Public Contract Regulations 2006, as amended, apply. The report says the CCS route meets EU procurement requirements. Secondary TUPE is expected, with legal support planned. [P54] [P100] Report P54, P100
Equalities: The contract should avoid negatively affecting the six equality strands in publicly accessible buildings. Local employment and supply chain use will be encouraged where possible. [P66] Report P66
Climate: Applicants must show how they will reduce energy use and emissions, meet energy and water targets, and capture data for annual emissions reporting. [P70] [P71] [P72] Report P70, P71, P72
Other: The contract requires the London Living Wage for all contractor staff working on it, including subcontracting arrangements. A delivery plan will be assessed. [P75] Report P75
Risk: The CCS framework was due to expire at the end of September 2014, so a significant delay could affect the council's ability to meet the requirement. The report says the project plan was achievable and resourced. [P42] [P43] Report P42, P43
Other: Buildings can be added or moved between maintenance strategies as the estate changes. This may increase contract value, and the gateway two report will set out governance for added buildings. [P25] [P30] Report P25, P30
Staffing: Corporate Facilities Management will manage procurement with existing resources and specialist external support. Corporate Facilities Management and the contractor will carry defined monitoring duties. [P80] [P81] [P82] [P84] Report P80, P81, P82, P84
Who and where
Council operational estate and circa 217 buildings needing the service Report P6, P12
Staff and visitors using operational buildings Report P5, P20
People using buildings open to the public Report P66
Voluntary and community schools and academies Report P30
Voluntary and community sector estate Report P30
Tenant and resident's association estate Report P30
Contractor staff and staff transferring under secondary TUPE Report P54, P75
The eight CCS framework suppliers Report P38, P40
Timeline
18 March 2014: Planned approval of Gateway 1: procurement strategy. Report P52
6 May 2014: Planned invitation to tender. Report P52
2 June 2014: Planned closing date for the return of tenders. Report P52
7 July 2014: Planned completion of tender evaluation. Report P52
13 August 2014: Planned approval of Gateway 2: contract award report. Report P52
1 September 2014: Planned contract award. Report P52
24 November 2014: Planned contract start. Report P52
31 January 2018: Initial contract completion date, with the extension completion date given as 31 January 2020. Report P52
Plain English for the jargon
Facilities management: Cleaning, security, catering, mail between sites, building maintenance, compliance and works projects. [P5]
CCS framework: The Crown Commercial Service facilities management framework, used for a further competition. [P1] [P38]
TSFM contract: The existing consolidated facilities management contract, first awarded for 160 Tooley Street. [P7]
EU procurement rules: The tendering requirements that the report says apply to this contract and are met through the CCS framework. [P95] [P100]
Cost streams: Cost stream one uses fixed pricing for defined work, while cost stream two charges for reactive work under a list of rates. [P28]
London Living Wage: A required wage for all contractor staff working on the contract, including subcontracting arrangements. [P75]
CPIX: The index proposed for annual contract price reviews. [P86]
Secondary TUPE: Expected to apply when services transfer to the new contractor, with information gathering and legal advice planned. [P54]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
That the procurement strategy outlined in the report for the consolidated repairs and maintenance service contract for the council’s operational estate, namely to undertake a further competition using the crown commercial service (CCS) framework for facilities management as allowed for under CSO 3.4 be approved. 2. That based on the minimum number of buildings expected to be included in the contract it be noted that the estimated annual cost is £3.5M for a period of approximately 38 months making a total estimated contract value of £11M, with the option to extend for two 12 month periods giving a total contract value of £18M, which is expected to increase in line with plans to include other buildings during the life of the contract. 3. That the decision of the gateway two contract award report be delegated to the strategic director of finance and corporate services so as to facilitate awarding the contract before the expiry of the current framework.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 13 pages
Recommendations
1. That the cabinet approve the procurement strategy outlined in this report for the consolidated repairs and maintenance service contract for the council’s operational estate, namely to undertake a further competition using the crown commercial service (CCS) framework for facilities management as allowed for under CSO 3.4.
2. That the cabinet note that based on the minimum number of buildings expected to be included in the contract the estimated annual cost is £3.5M for a period of approximately 38 months making a total estimated contract value of £11M, with the option to extend for two 12 month periods giving a total contract value of £18M, which is expected to increase in line with plans to include other buildings during the life of the contract.
3. That the cabinet approve the delegation of the decision regarding the gateway two contract award report to the strategic director of finance and corporate services so as to facilitate awarding the contract before the expiry of the current framework.
BACKGROUND INFORMATION
4. Facilities Management (FM) is an integral business support service that provides the wide range of fundamental soft FM services e.g. cleaning, security, catering, inter-site mail, and hard facilities management e.g. planned, preventative and reactive building maintenance, compliance and works projects which make up the building related services required to provide safe and compliant environments for staff and visitors.
5. In order to meet the changing requirements in the council’s accommodation strategy a new long term procurement strategy for FM services was agreed for the operational estate, namely to move from a situation in which the council has multiple, disparate, outmoded contract arrangements to a consolidated FM service provision through the procurement of a suite of aligned FM contracts.
6. In October 2012 the council awarded the first of these contracts in the form of a consolidated soft and hard facilities management services contract for 160 Tooley Street to Interserve Plc for a period of five years, with an option to extend for an additional two years, hereafter referred to as the TSFM contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.