Gateway to Peckham Project Update and Approval of the making of an application to the Secretary of State for a compulsory purchase order to acquire the property interests within the revised project boundary

Agreed Executive 5 papers

AI summarySouthwark Council decided to make a compulsory purchase order for Peckham Rye Station to secure a public square and commercial space. [D] The £15.2M programme combines council capital and Greater London Authority grant funding. [P66]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedArea 1 acquisition for a public square and commercial space. [P2]
Money£15.2M [P66]Combined council capital and Greater London Authority funding. [P66]
What happens nextNot stated
Who it affectsArea 1 leaseholders and businesses [P47]Some interests will be compulsorily acquired and compensated. [P50] [P51] [P56]

What was decided

Southwark Council will make the CPO under section 226(1) of the Town and Country Planning Act 1990 and section 13 of the Local Government (Miscellaneous Provisions) Act 1976. It covers land and new rights in Area 1 on plan LBS_3175(Layout3), for a public square and new or refurbished commercial space. Report P2

The Director of Regeneration is authorised to progress the CPO, including notices and any public inquiry, and to acquire interests by agreement or compulsorily. They may approve agreements ending objections, amend boundaries, use vesting powers and approve compensation within the closed report budget. Report P4, P5, P6, P7, P8, P9, P10, P11

Cabinet is to note the change in project delivery, the community co design results, other completed work and the renewed Greater London Authority funding agreement. Report P12, P13, P14, P15, P16

Why

Officers said compulsory purchase should be used only where a compelling public interest case exists, and considered the scheme's regeneration benefits to outweigh disadvantages to dispossessed interests. Report P45, P50, P51

The first phase was expected to secure investment, create premises and employment opportunities, improve the station setting, increase footfall and support later redevelopment phases. Report P46

The order was recommended to provide certainty of acquiring all interests within the envisaged timescale and reduce project risk because the legal arrangements were complex. Report P48

What happens next

The Director of Regeneration will take steps to secure the making, confirmation and implementation of the CPO, including publication and service of notices and any public inquiry case. Report P4, P9

Negotiations will continue with leaseholders and businesses, with interests acquired by agreement where possible and compensation approved within the closed report limits. Businesses will be relocated within the scheme or elsewhere where possible. Report P11, P47, P48, P59

If Network Rail and Bywater Properties do not conclude negotiations, the Director may amend Area 1 to include Area 2 or seek a separate compulsory purchase order. Report P8, P46

The money

  • £15.2M Combined total from council capital and Greater London Authority grant funding. Report P66
  • £10.0M Council capital programme commitment. Report P66
  • £5.2M Greater London Authority grant funding for the scheme. Report P66
  • £5.073M Approximate renewed Greater London Authority agreement funding. Report P45
  • £5.093M Capital funding under the earlier Greater London Authority agreement. Report P45
  • £5.07 million Funding secured through the April 2012 grant agreement. Report P19
  • 7.5% of the market value Basic loss payment calculation, capped at £75,000. Report P56
  • £25 per square metre, minimum of £2,500, maximum of £25,000 Occupier's loss payment limits. Report P56

Options considered

  • Chosen: Acquire interests by agreement where possible. Voluntary negotiations will continue and agreement remains the preferred route for many interests. Report P5, P47, P48
  • Chosen: Use a CPO for residual interests. The order is likely to be required to secure interests that cannot be acquired by agreement. Report P47, P48
  • Chosen: Exclude Area 2 from the current CPO. Area 2 is currently excluded while the proposed transaction with Network Rail is pursued. Report P46
  • Chosen: Amend Area 1 to include Area 2 if negotiations fail. This is expressly authorised if Network Rail and Bywater Properties do not conclude negotiations. Report P8
  • Chosen: Seek a separate CPO for Area 2 if negotiations fail. This is expressly authorised as an alternative if negotiations do not conclude. Report P8

Implications

  • Legal: The CPO may dispossess some people of rights in land. The report considers interference with human rights justified and proportionate in the wider public interest. Report P50, P53
  • Financial: All interests within the CPO boundary are commercial. Compensation may include market value, basic loss, disturbance, occupier loss, reinvestment and relocation or extinguishment payments. Report P55, P56, P57, P58
  • Equalities: Potential negative equality effects include lost jobs, business premises and access to culturally specific goods and services. BME owned businesses and employees, particularly people of Black African and Black Caribbean origin, are especially vulnerable. Report P52
  • Equalities: Possible mitigation includes relocation in new units, financial and business support, fair treatment, future letting and site management measures, and continued equality review. Report P49, P51, P52, P53
  • Other: The public square and opened station frontage are expected to improve environmental wellbeing and the public realm. Report P46, P52
  • Other: The scheme is expected to support investment, employment, footfall, public safety and later redevelopment phases. Report P46
  • Risk: The order reduces risk and gives certainty over acquisition, but Area 2 remains dependent on negotiations. Report P48
  • Staffing: Provision is included for staff costs on the order, project completion, tenant relocation and leasehold acquisition. Report P70

Who and where

  • Area 1 leaseholders, covering 10 registered leasehold interests Report P47
  • Approximately 25 businesses in Area 1, including owner occupiers Report P47
  • Four leasehold interests in Area 2 Report P48
  • Network Rail as freeholder and Bywater Properties as tenant Report P8
  • Employees, particularly people in BME groups Report P52
  • Customers from African, Afro Caribbean and Asian backgrounds Report P52
  • People sharing protected characteristics Report P49, P52
  • Peckham residents and communities across Southwark Report P46, P49

Timeline

  • April 2012: Cabinet authorised a Greater London Authority grant agreement securing £5.07 million of funding. Report P19
  • April 2013: Cabinet instructed officers to commence negotiations with interested parties. Report P20, P21
  • 26 June 2013: Cabinet directed work on partnership models and the recording of engagement outcomes. Report P29, P30, P33
  • November 2014: The community atlas was published and the Peckham and Nunhead Area Action Plan was adopted. Report P38, P43
  • Dec 2014: First financial offers were made to head lessees and leasehold negotiations began. Report P46
  • 5 March 2015: The final report was dated. Greater London Authority Investment Board approval was due in March 2015. Report P45, P87
  • late spring 2015: The valuation and condition survey programme was due to be completed. Report P46
  • Summer 2015; Summer 2016 to Spring 2017; Spring 2017: The indicative programme covered the planning application and CPO, construction, and completion. Report P39

Plain English for the jargon

  • Compulsory Purchase Order: A council power to acquire land or rights to support development, redevelopment or improvement. [P45]
  • Area 1: The first redevelopment phase at the station frontage, edged and hatched black on plan LBS_3175(Layout3). [P2] [P38]
  • Area 2: The Iceland site, currently excluded from the CPO pending negotiations. [P46]
  • GLA: The Greater London Authority, which provided capital funding for the project. [P45]
  • Peckham and Nunhead Area Action Plan: The local planning policy framework for redevelopment in the area. [P43]
  • EQIA: An assessment of equality effects on leaseholders, occupiers and businesses, including possible mitigation. [P52]
  • Compensation Code: The statutes and case law used to assess compensation, principally the Land Compensation Act 1961 (as amended). [P60]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

That the council makes a Compulsory Purchase Order (CPO) under section 226 (1) of the Town & Country Planning Act 1990 and section 13 of the Local Government (Miscellaneous Provisions) Act 1976 for the acquisition of the land and new rights within the area and hatched edged black on the Ordnance Survey plan LBS_3175(Layout3) at Appendix One for the purpose of securing the creation of a new public square and new or refurbished commercial space to the front of Peckham Rye Station part of proposal site 6 in the Peckham & Nunhead Area Action Plan (PNNAP). 2. The director of regeneration be authorised to: a) take all necessary steps to secure the making, confirmation and implementation of the CPO including the publication and service of all notices and the presentation of the council’s case at Public Inquiry should one be called; b) acquire all interests in land within the CPO boundary either by agreement or compulsorily; c) approve agreements with land owners setting out the terms for the withdrawal of objections to the CPO, including where appropriate seeking exclusion from the CPO; d) amend the boundaries of the Area 1 edged and hatched black on the Ordnance Survey plan LBS_3175(Layout3) at Appendix One; or e) either amend the boundaries of the Area 1 edged black on the Ordnance Survey plans to include Area 2 edged black on plan LBS_3175(Layout4) at Appendix One or seek a separate compulsory purchase order, if negotiations are not concluded between Network Rail (the freeholder) and Bywater Properties (the tenant), should it be required; f) make arrangements for the presentation of the council's case for confirmation of the CPO at any public inquiry; g) exercise the compulsory purchase powers authorised by the CPO by way of general vesting declaration and/or notice to treat. h) to approve the acquisition of all interests, where possible, by negotiation pursuant to the CPO approving payments to interest holders in line with the statutory compensation provisions within the budget and limits per interest set out in the closed report. 3. That the following be noted: a) The change in the delivery of the project b) The results of the community engagement work undertaken as part of the co-design process c) Other work completed as part of the project d) The renewed funding agreement to be entered into with the GLA.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 14 pages

Recommendations

That the cabinet agrees that:

1. The council makes a Compulsory Purchase Order (CPO) under section 226 (1) of the Town & Country Planning Act 1990 and section 13 of the Local Government (Miscellaneous Provisions) Act 1976 for the acquisition of the land and new rights within the area and hatched edged black on the Ordnance Survey plan LBS_3175(Layout3) at Appendix One for the purpose of securing the creation of a new public square and new or refurbished commercial space to the front of Peckham Rye Station part of proposal site 6 in the Peckham & Nunhead Area Action Plan (PNNAP).

1 2. The Director of Regeneration be authorised to:

a) take all necessary steps to secure the making, confirmation and implementation of the CPO including the publication and service of all notices and the presentation of the council’s case at Public Inquiry should one be called;

b) acquire all interests in land within the CPO boundary either by agreement or compulsorily;

c) approve agreements with land owners setting out the terms for the withdrawal of objections to the CPO, including where appropriate seeking exclusion from the CPO;

d) amend the boundaries of the Area 1 edged and hatched black on the Ordnance Survey plan LBS_3175(Layout3) at Appendix One; or

e) either amend the boundaries of the Area 1 edged black on the Ordnance Survey plans to include Area 2 edged black on plan LBS_3175(Layout4) at Appendix One or seek a separate compulsory purchase order, if negotiations are not concluded between Network Rail (the freeholder) and Bywater Properties (the tenant), should it be required;

f) make arrangements for the presentation of the council's case for confirmation of the CPO at any public inquiry;

g) exercise the compulsory purchase powers authorised by the CPO by way of general vesting declaration and/or notice to treat.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LBS_3175 (Layout3)Appendix 1 1 pages Download
PDF
LBS_3175 (Layout4)Appendix 1 1 pages Download
PDF
LBS_3175 (Layout5)Appendix 1 1 pages Download
PDF
Gateway to Peckham EqIA ReportAppendix 2 61 pages Download
PDF
Report: Gateway to Peckham update and CPOReport 14 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway to Peckham Project Update and Approval of the making of an application to the Secretary of State for a compulsory purchase order to acquire the property interests within the revised project boundaryThis decision
  2. Approval to Enter Grant Agreement with the GLA for the Gateway to Peckham ProjectAgreed
  3. Gateway to Peckham - Public Square and Station RegenerationNoted
  4. Gateway to Peckham - Public Square and Station Regeneration - Officer response to Overview and Scrutiny RecommendationsNoted
  5. Gateway to Peckham - Public Square and Station RegenerationNoted
  6. Gateway 1: Peckham Rye Station Redevelopment Procurement StrategyApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies