Gateway 1 - Procurement Strategy Approval: Management of the Council's Leisure Facilities
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved the strategy for an external competitive tender for leisure facilities from 21 June 2016, for seven years with an option for up to seven further years [D] [P1] [P86] [P90]. The target is a cost neutral contract [P179] [P200].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedExternal management will go to competitive tender [P86] [P90].
MoneyCost neutral contract possible [P179]At no more than the current price or less [P179].
What happens nextCompetitive EU tender [P90]Seek at least five tenders and assess price and quality [P90] [P133].
Who it affectsCouncil leisure facilities [P19]Named centres and sports facilities enter the tender [P19].
What was decided
The procurement strategy was approved for external management of the council's leisure facilities from 21 June 2016. The initial term is seven years, with an option to extend for a period or periods of up to a further seven years. Report P1, P86
The tender covers Camberwell Leisure Centre, Dulwich Leisure Centre, Peckham Pulse Healthy Living Centre, Seven Islands Leisure Centre, Southwark Athletics Centre, Surrey Docks Water Sports Centre, The Castle and Geraldine Mary Harmsworth Sports Facility. Report P19
The council will run a competitive EU tender seeking a minimum of five tenders. Tenders will be assessed on price and quality using a minimum 60:40 price to quality ratio. Report P90, P133, P136
Why
The existing leisure management contract expires in June 2016, so a decision on future management was needed. Report P3
External procurement was judged the most advantageous route to a high quality service at the lowest cost, with economies of scale and better retention of specialist staff. Report P86, P87
Soft market testing found that delivery could remain within the current budget while including London Living Wage and free swim and gym. Report P81, P88
What happens next
Complete the tender documentation and advertise in OJEU, Contracts Finder and other relevant websites. Report P106, P124
Invite and evaluate tenders on price and quality, then seek Gateway 2 approval for award in February 2016. Report P131, P133, P142, P200
Require the incumbent to supply eligible staff transfer details before invitation to tender and complete TUPE consultation. Report P107, P110
The money
at least £250k per annum Estimated net council cost of full NNDR under internal management. Report P51
more than £50 million Invested in leisure facilities over the last several years. Report P14
£2 million Planned for Seven Islands before the new Canada Water centre. Report P14
£12.3 million Council capital investment decided for leisure centre refurbishment. Report P5
30% Council share of NNDR payments under the current arrangement. Report P51
Options considered
Chosen: External contract. It was judged most advantageous for securing a high quality service at the lowest cost, with financial and scale advantages. Report P86, P87
Rejected: Internal service. The council would hold full maintenance costs, lacked current operational expertise and faced staffing and transfer difficulties. Report P42, P62, P64, P65
Rejected: Shared service with neighbouring boroughs. The closest boroughs already had long term contracts with external contractors. Report P24, P25
Implications
Financial: The target is a cost neutral contract, although free swim and gym makes a provider payment less likely. The report identifies financial advantages linked to NNDR and VAT under external management. Report P87, P179
Legal: The procurement is subject to procurement regulations 2015 because the service is being procured after 26 February 2015. External legal advisers will advise on compliance and any new provisions that could facilitate the process. Report P196, P197
Legal: TUPE will apply if the contractor changes. Current employees would be eligible to transfer if the service moved to the council, with one off transfer and pension costs. Report P65, P109
Risk: Controls cover value for money, competition, contractor failure, TUPE and service requirements. Reputational risk remains with the council under external management. Report P44, P94
Equalities: The contractor must reduce barriers to physical activity and meet participation targets for particular groups. Report P154
Climate: The contractor must meet waste and energy targets and implement carbon reduction plans, with deductions for non compliance. Report P161, P162
Staffing: The contractor handles recruitment, training, payroll and pensions. The council's four officer client team will manage performance within existing resources. Report P61, P174, P176
Other: The contract is intended to promote good health and social cohesion by delivering free swim and gym to all residents. Report P98
Who and where
All residents receiving free swim and gym Report P16, P98
People on low incomes and diverse communities Report P10, P138
People with disabilities and people under 16 or over 60 Report P171
Older residents Report P159
Current leisure members outside Southwark, 22 per cent of membership Report P49
Existing contract employees, approximately 120 FTE staff representing up to 200 individuals Report P64
Local residents and businesses, through apprenticeships, training and local supply chains Report P148, P149, P150
The council's sports and leisure client team Report P174
Timeline
17 March 2015: Gateway 1 approval listed in the procurement project plan. Report P106
May 2015: Free swim and gym pilot scheduled for targeted groups. Report P16
1 September 2015: Deadline for return of tenders. Report P106
February 2016: Contract award scheduled. Report P107, P200
21 June 2016: New contract due to start. Report P107
July 2016: Free swim and gym scheduled for all residents. Report P16
20 June 2023: Initial contract completion date. Report P107
20 June 2030: Completion date if extension options were exercised. Report P107
Plain English for the jargon
Gateway 1: Key procurement stage for approving the strategy [P1] [P96].
TUPE: Staff transfer rules that apply if the contractor changes [P109].
NNDR: Relief for charitable trusts, with the council receiving 30% of payments [P51].
OJEU: A channel where the tender will be advertised [P124].
PQQ: Pre Qualification Questionnaire used to assess providers' suitability [P127].
KPI: Monthly and annual measures monitored for contract performance [P170].
PCR 2015: Procurement regulations 2015 applying to this service procurement [P196].
London Living Wage: Pay requirement included in the new contract [P155].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
That the procurement strategy outlined in the report to go out to tender for the management of the council’s leisure facilities from 21 June 2016 for a period of seven years with an option to extend for a period or periods of up to a further seven years be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 21 pages
Recommendations
1. That the cabinet approves the procurement strategy outlined in this report to go out to tender for the management of the council’s leisure facilities from 21 June 2016 for a period of seven years with an option to extend for a period or periods of up to a further seven years.
BACKGROUND INFORMATION
2. The council’s leisure management contract with Fusion Lifestyle will expire in June 2016 and a decision needs to be taken on future management arrangements for the council’s leisure centres.
3. On 7 April 2000 the council, entered into a grant agreement with Southwark Community Leisure Limited (SCLL) for the management of the council’s leisure centres. SCLL has since changed its name to Fusion Lifestyle (Fusion). Fusion Lifestyle is a registered charity.
4. On 13 February 2007, the executive received a report on the Leisure Centre Investment Strategy. The council decided to invest £12.3 million of its own capital to refurbish the borough’s existing leisure centres. In light of this decision, the Executive asked officers to evaluate all options for management of the leisure centres and report the findings back to the Executive.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.